Fee Review-notes | 6/29/2000 | 6/29/2000 | 4/19/2001 | | DONE |
|
|
|
|
Letter of compliance | | | 11/8/2000 | | DONE |
|
|
|
Letter of Compliance #20011 issued 11-9-00.
|
BLD-Final | 10/27/2000 | 10/27/2000 | 10/27/2000 | | PASS |
Jim Storey
|
|
|
final ok
|
BLD-Final | 9/12/2000 | 9/12/2000 | 9/12/2000 | P | PART |
Jim Storey
|
|
|
###-#### page 99710 Greg Adams ok for final upon aproval of ele. sign off. 9/13/2000 12:02:22 PM
|
FIRE-Final Inspection | 9/7/2000 | 9/8/2000 | 9/8/2000 | P | PASS |
Rick Jackson
|
|
|
Greg Adams pager # ###-#### 99710 told Greg we would review the corridor situation on the upcoming TI work. The duct entering the corridor from the RM TI doesn't open into the corridor. 9/8/2000 3:43:18 PM
|
FIRE-Final Inspection | 8/14/2000 | 8/15/2000 | 8/15/2000 | P | FAIL |
Rick Jackson
|
|
|
GREGG-- ###-#### FIRE FN alarms not complete; door to corridor 8/15/2000 4:49:37 PM
|
Telephone call | | | 7/27/2000 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Issue & PRINT permit | | | 7/27/2000 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 7/5/2000 | | 7/26/2000 | | PASS |
John Menard
|
|
|
7/26/00 08:05:40 JCM - activity updated through activity BLDA022 from case BLD00-01893.
|
Routing - PLAN CHECK | 7/26/2000 | | 7/26/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/26/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/26/2000 | | DONE |
|
|
|
|
Routing - FIRE | 7/21/2000 | | 7/25/2000 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 7/25/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/12/2000 | | 7/21/2000 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 7/21/2000 | | PASS |
|
|
|
PLANS REVIEWED AND APPROVED AS SUBMITTED.
|
FIRE-Conference | 7/17/2000 | 7/17/2000 | 7/13/2000 | | PART |
Rick Jackson
|
|
|
reviewed project with superintendant
|
Routing - PLUMBING | 7/7/2000 | | 7/12/2000 | | PASS |
|
|
|
relocation of one sink and mis. piping
|
Routing - PUBLIC WORKS | 7/5/2000 | | 7/7/2000 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 7/5/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/5/2000 | | PASS |
|
|
|
|
Received Certificate of Value | | | 6/29/2000 | | DONE |
|
|
|
|
Application received | | | 6/29/2000 | | |
|
|
|
|