To construct a new 1,663 sq.ft. tenant space for office use in Suite A of this building per approved plans on file. Building shell done under BLD98-3707. Work to include a new unisex accessible restroom, new interior walls with doors and one window, interior finish, new plumbing, new mechanical, and new electrical work. One-hour rated tenant demising wall existing from previous permits. (P.C.#542-00) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/30/20006/30/20005/9/2001 DONE
BLD-Final8/23/20008/25/20008/25/2000APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 08/23/2000 at 09:27:51. Contact: ###-####.
Permanent Occupancy 8/25/20008/25/2000 DONE
Details
Permanent occupancy UNPAID FEE  8/25/2000 DONE
Perm. Occ. Cert. #8344 issued 8-25-00 to Stargate Investments.
FIRE-Final Inspection8/23/20008/24/20008/24/2000APASS
DetailsJoe Tawney
Dennis ###-#### - cell ###-#### suite a Final OK for permanant occupancy 8/24/2000 12:24:31 PM
BLD-Energy code compliance8/8/20008/9/20008/9/2000APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 08/08/2000 at 12:50:20. Contact: ###-####.
BLD-Framing/Rough-in8/4/20008/7/20008/7/2000PPASS
DetailsTony Young
Scheduled by a contractor via Hello! on 08/04/2000 at 12:38:33. Contact: ###-####.
Routing - FIRE7/31/20008/3/20008/4/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  8/4/2000 FAIL
Routing - PLAN CHECK8/4/2000 8/4/2000 PASS
Plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  8/4/2000 PASS
Print Occupancy Form  8/4/2000 DONE
Inspection Record Card- Bld  8/4/2000 DONE
Issue PAID IN FULL permit  8/4/2000 DONE
Plan assigned to (JCB)7/13/2000 8/4/2000 PASS
DetailsJason Blais
8/4/2000 11:15:09 JCB - activity updated through activity BLDA022 from case BLD00-01901.
Plan resubmittals received  8/1/2000 PEND
Plan response received and approved. Permit and plan approval dependent on Fire Dept. approval.
Routing - PLAN CHECK7/14/2000 7/31/2000 FAIL
Plan review report sent and faxed to architect. Clarification and written response needed for a couple of items. Plans routed to fire dept.
Plan resubmittals requested  7/31/2000 PEND
Written response to plan review report required.
Routing - PUBLIC WORKS7/13/2000 7/14/2000 PASS
Pending Assignment by MYS7/13/2000 7/13/2000 DONE
DetailsMarlene Southard
Plan routing begun/TENANTS  7/13/2000 DONE
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  7/10/2000 DONE
Received Certificate of Value  6/30/2000 DONE
Application received  6/30/2000  
Recd Pcfee & Taken To Pln CK  6/30/2000 DONE