Fee Review-notes | 6/27/2003 | 6/27/2003 | 6/27/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/13/2003 | | DONE |
|
|
|
Perm. Occ. Cert. #9584 issued 3-13-03 to the Boise Convention & Visitor's Bureau on the 1st floor of the parking garage.
|
BLD-Final | 3/11/2003 | 3/12/2003 | 3/12/2003 | A | PASS |
Carl Dependahl
|
|
|
DAVID; Phone #: ###-#### Internet Inspection Request from: Darla Downs..struct c/n ok ok for c/o pending verification other finals 3/12/2003 11:26:57 AM
|
BLD-Conference | 3/3/2003 | 3/4/2003 | 3/4/2003 | P | FAIL |
Carl Dependahl
|
|
|
Rick...c/n issued to arrange final 3/4/2003 2:05:19 PM
|
BLD-Aging Inspection | 2/27/2003 | 2/27/2003 | 3/4/2003 | | DONE |
Carl Dependahl
|
|
|
left c/n to obtain c/o spoke w/ Krista 3/4/2003 5:16:08 PM
|
Permanent Occupancy | | 2/21/2003 | 2/21/2003 | | DONE |
|
|
|
|
Fee Review-notes | 1/9/2003 | 1/9/2003 | 1/9/2003 | | DONE |
|
|
|
COULD NOT GET A HOLD OF THE ELE CONTRACTOR ( BIG SKY ELECTRIC ) SO I COULD NOT GET A FINAL CERT OF VALUE 1-9-03 ///DLD
|
Fee Review-notes | 6/30/2000 | 6/30/2000 | 3/19/2001 | | DONE |
|
|
|
|
BLD-Final | 11/28/2000 | 11/29/2000 | 11/29/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/28/2000 at 11:09:26. Contact: ###-####. ###-#### 11/29/2000 9:52:43 AM c/n, firestops, remove chase at duct. 11/29/2000 3:02:04 PM
|
FIRE-Final Inspection | 11/28/2000 | 11/28/2000 | 11/28/2000 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 11/28/2000 11:26:52 AM
|
BLD-Conference | 11/28/2000 | 11/28/2000 | 11/28/2000 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/28/2000 11:30:27 AM w/ Dave Blodgett re duct penetration...ok to remove enclosure per 711.3 UBC
|
BLD-Final | 11/22/2000 | 11/27/2000 | 11/27/2000 | A | FAIL |
Carl Dependahl
|
|
|
FN-TEMP--BRICE ###-#### CELL OR ###-####, nr 11/27/2000 11:25:54 AM
|
FIRE-Final Inspection | 11/22/2000 | 11/24/2000 | 11/24/2000 | A | FAIL |
Rick Jackson
|
|
|
FIRE FN BRICE ###-#### //// exit sign not working; scaffolding blocking exit 11/27/2000 9:19:26 AM
|
FIRE-Sprinkler Rough-in | 11/16/2000 | 11/17/2000 | 11/17/2000 | A | PASS |
Rick Jackson
|
|
|
###-#### ////okay to cover 11/17/2000 9:58:12 AM
|
FIRE-Final Inspection | 11/16/2000 | 11/16/2000 | 11/16/2000 | P | NR |
Rick Jackson
|
|
|
DON PAGER ###-#### FIRE FN // not ready will reschedule 11/16/2000 3:58:31 PM
|
BLD-Framing/Rough-in | 10/10/2000 | 10/11/2000 | 10/11/2000 | A | PASS |
Jim Storey
|
|
|
fire caulking Herb Brice ###-####firechalking ok for this scope of work. 10/11/2000 8:26:52 AM
|
BLD-Framing/Rough-in | 10/5/2000 | 10/6/2000 | 10/6/2000 | A | PART |
Jim Storey
|
|
|
FR HERB- ###-#### fire stopping occ septration. sprinkler drop at hard ceilling/ remove wood. 10/6/2000 10:09:37 AM
|
Issue PAID IN FULL permit | | | 8/22/2000 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 7/12/2000 | | 7/31/2000 | | PASS |
Carl Westfall
|
|
|
7/31/00 08:11:18 CJW - activity updated through activity BLDA022 from case BLD00-01913.
|
Routing - PLAN CHECK | 7/26/2000 | | 7/31/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/31/2000 | | DONE |
|
|
|
|
Telephone call | | | 7/31/2000 | | DONE |
|
|
|
###-#### david
|
Print Occupancy Form | | | 7/31/2000 | | DONE |
|
|
|
|
Routing - FIRE | 7/21/2000 | 7/26/2000 | 7/26/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 7/26/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/14/2000 | | 7/21/2000 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 7/20/2000 | | PASS |
|
|
|
UBC plan review started July 20, 2000 and finished the next day. The drawings were approved with conditions. See the conditions list.
|
Routing - PUBLIC WORKS | 7/12/2000 | | 7/14/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 7/12/2000 | | 7/12/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 7/12/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 7/10/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 6/30/2000 | | DONE |
|
|
|
|
Application received | | | 6/30/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/30/2000 | | DONE |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Received Certificate of Value | | | | | |
|
|
|
RECIVED FINAL CERTIFICATE OF VALUE 1 COPY IN FILE 1 COPY TO FRONT DESK/PE
|