Fee Review-notes | 7/3/2000 | 7/3/2000 | 5/9/2001 | | DONE |
|
|
|
|
Permanent Occupancy | | 10/27/2000 | 10/27/2000 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 10/27/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8445 issued 10-27-00 to Washington Trust Bank.
|
FIRE-Final Inspection | 10/25/2000 | 10/26/2000 | 10/26/2000 | A | PASS |
Rick Jackson
|
|
|
Don, ###-#### - reinspect
|
BLD-Final | 10/25/2000 | 10/26/2000 | 10/26/2000 | P | PART |
Jim Storey
|
|
|
Don, ###-#### ok pending ele sign off for perm. 10/26/2000 2:04:28 PM
|
FIRE-Final Inspection | 10/24/2000 | 10/25/2000 | 10/25/2000 | A | FAIL |
Rick Jackson
|
|
|
Don Bryan, ###-#### alarms not complete; need damper at ceiling in janitors closet; exit signs; painted fusible links on dampers in bathrooms; c/n issued 10/25/2000 1:44:43 PM
|
BLD-Wall cover | 10/10/2000 | 10/11/2000 | 10/11/2000 | A | FAIL |
Jim Storey
|
|
|
Don Bryan, ###-#### supplys not supported / lights not wired / two dead bolts not allowed at main entry. 10/11/2000 4:18:16 PM
|
BLD-Framing/Rough-in | 9/28/2000 | 9/29/2000 | 9/29/2000 | A | PASS |
Jim Storey
|
|
|
Don Bryan, ###-#### ceilling fire stopped and ok for framing at attic. 9/29/2000 2:50:23 PM
|
BLD-Framing/Rough-in | 9/18/2000 | 9/18/2000 | 9/18/2000 | P | PART |
|
|
|
Don Bryan, ###-#### needto see firecaulking of the 2-hr ceiling prior to any fixture install 9/18/2000 2:35:50 PM
|
BLD-Framing/Rough-in | 9/12/2000 | 9/13/2000 | 9/13/2000 | P | NR |
|
|
|
Don Bryan, ###-#### work not complete enough for insp to be made 9/14/2000 9:23:21 AM
|
BLD-Framing/Rough-in | 9/8/2000 | 9/8/2000 | 9/8/2000 | P | PART |
|
|
|
Don Bryan, ###-#### ok to cover new ceiling only 9/8/2000 2:08:30 PM
|
BLD-Conference | 9/5/2000 | 9/5/2000 | 9/5/2000 | P | PART |
|
|
|
###-#### ok for thefront partition walls, need assy fr the 2-hr walls and deck as work has proceeded farther than planned 9/6/2000 9:37:51 AM
|
BLD-Framing/Rough-in | 8/29/2000 | 8/30/2000 | 8/30/2000 | P | FAIL |
Jim Storey
|
|
|
Don ###-#### arch. to address 2 hr. ceilling continuity of all walls top plates and ele,plm intagraty. 8/31/2000 12:22:40 PM
|
BLD-Foundation | 8/10/2000 | 8/11/2000 | 8/11/2000 | A | PART |
|
|
|
CONCRETE SLAB-- DON ###-#### sp insp not req per keith jones designd for 2500 psi 8/14/2000 8:12:50 AM
|
BLD-Framing/Rough-in | 8/8/2000 | 8/8/2000 | 8/8/2000 | P | PART |
|
|
|
Don ###-#### ok to hang rock on the demising wall with elec ok,s 8/8/2000 4:13:15 PM
|
Issue PAID IN FULL permit | | | 8/3/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/1/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/1/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/1/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/1/2000 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2000 | | DONE |
|
|
|
gary ###-####
|
Routing - FIRE | 7/31/2000 | 7/31/2000 | 7/31/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 7/31/2000 | | 7/31/2000 | | PEND |
|
|
|
Plans routed to Planning (Tom Curren) for Zoning Certificate approval. Building permit approval dependent on Planning approval.
|
Routing - PLANNING | 7/31/2000 | | 7/31/2000 | | PASS |
|
|
|
As per Zoning Certificate CZC00-00087.
|
Routing - PLAN CHECK | 7/31/2000 | | 7/31/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2000 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 7/6/2000 | | 7/31/2000 | | PASS |
Jason Blais
|
|
|
7/31/2000 14:32:57 JCB - activity updated through activity BLDA022 from case BLD00-01933.
|
Routing - PLAN CHECK | 7/14/2000 | | 7/28/2000 | | PEND |
|
|
|
Plan and Permit approval dependent on Fire Dept. approval and completion of Zoning Certificate. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 7/26/2000 | | DONE |
|
|
|
RECEIVED TWO SETS OF PLAN RESUBMITTALS FROM ZGA ARCHITECTS, ARCHITECTUAL, MECHANICAL AND ELECTRICAL PLANS, FORWARDED SAME TO JASON BLAIS. 7/26/00 DAR
|
Routing - FIRE | 7/13/2000 | 7/14/2000 | 7/14/2000 | | FAIL |
Bill Alexander
|
|
|
UFC UBC RELATED ISSUEA OF CONCERN.
|
Plan Review Completed(1st rev) | | | 7/14/2000 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/7/2000 | | 7/13/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Numerous items to address. Plan resubmittals required. Plans routed to fire dept. for review.
|
Plan resubmittals requested | | | 7/13/2000 | | PEND |
|
|
|
Plan resubmittals required for further review.
|
Routing - PUBLIC WORKS | 7/6/2000 | | 7/7/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 7/6/2000 | | 7/6/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 7/6/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 7/5/2000 | | PASS |
|
|
|
|
Received Certificate of Value | | | 7/3/2000 | | DONE |
|
|
|
|
Application received | | | 7/3/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/3/2000 | | DONE |
|
|
|
|