Permit Information
Permit NumberBLD00-02077
StatusExpired
Name BOISE MTN VIEW CH OF BRETHERN
Site Address 2823 N COLE RD
Project NameMOUNTAIN VIEW CHURCH BRETHREN
Customer Number 
ePlanReviewNo
Description
To remodel the South half of the second story, a 2,907 sq. ft. area (original permit BLD#1028027, 1988) for additional sunday school classrooms & support areas. Work to include wood or metal frame, non-bearing walls to create classrooms, unisex accessible restroom; to verify and complete as necessary a 1-hour exit corridor system serving as one of the required exits from the second floor, south end, and upgrade as required of the second exit through the north end intervening room to the exterior landing & stairway. All per approved plans, to include red-line notes & attached plan review comments. THE 1988, 9,279 SQ. FT., TWO STORY CLASSROOM ADDITION AND SANCTUARY, ADDED TO THE EXISTING TWO STORY 7,497 SQ. FT. AREA, FOR A TOTAL AREA OF 16,776 SQ. FT., HAVE NEVER BEEN FINALED FOR OCCUPANCY. REVIEW OF EXISTING FACILITIES FOR IMMINENT HAZARDS, EXITS, HARDWARE, EXIT SIGNS & ILLUMINATION, ETC, FOR PURPOSE OF ISSUING A CERTIFICATE OF OCCUPANCY FOR THE ENTIRE PROJECT USE, IS A CONDITION OF THIS PERMIT. Occupant loads shall be posted in assembly use rooms as noted on approved plans. CUP00-00071 (P.C.#574-00)/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference6/5/20036/5/20036/5/2003PPASS
DetailsJim Sly
leon; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Conference6/2/20036/3/20036/3/2003PPASS
DetailsJim Sly
###-#### leon
BLD-Aging Inspection4/17/20034/17/20034/17/2003 PART
DetailsJim Sly
Talked to Leon.....He is still working on project (if rather slowly) and said he is within 3 weeks of calling for all finals. 4/17/2003 2:13:47 PM
BLD-Aging Inspection2/10/20032/10/20032/10/2003 FAIL
DetailsJim Sly
See previous insp notes. 2/10/2003 12:02:26 PM
BLD-Aging Inspection12/11/200212/11/200212/11/2002 FAIL
DetailsJim Sly
Talked to Leon 3764906 at job site.....still working on project....90% complete.....explained proceedure for obtaining final Occ. 12/12/2002 11:32:57 AM
BLD-Foundation1/4/20021/7/20021/7/2002AFAIL
DetailsRuss Owen
###-#### This permit does not include this work (exterior addition) also there are no approved plans. They may not have a permit for this construction. Also note the work is not complete,also the footings are not constructed as shown by the (UNAPPROVED) footing details on the site. A c/n has been posted. 1/7/2002 10:03:51 AM
BLD-Footing1/7/20021/7/20021/7/2002PNR
DetailsDave Hannah
###-####
BLD-Aging Inspection12/19/200112/19/200112/19/2001 DONE
DetailsDave Hannah
work in progress 12/19/2001 1:29:43 PM
BLD-Framing/Rough-in10/19/200110/19/200110/19/2001PPASS
DetailsDave Hannah
###-#### ok to cover 10/19/2001 2:01:02 PM
BLD-Aging Inspection9/3/20019/3/20019/3/2001 DONE
DetailsDave Hannah
work in progress 9/4/2001 12:35:02 PM
BLD-Aging Inspection7/2/20017/2/20017/2/2001 PASS
DetailsTony Young
BLD-Framing/Rough-in4/30/20014/30/20014/30/2001PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 04/30/2001 at 08:46:48. Contact: ###-####. need elec rough in 4/30/2001 4:09:02 PM
BLD-Conference3/14/20013/14/20013/14/2001PPART
DetailsDave Hannah
Lynn ###-#### need to go to plan review for changes on ada bath room 3/14/2001 1:56:07 PM
Issue PAID IN FULL permit  2/5/2001 DONE
Print Occupancy Form  2/2/2001 DONE
Telephone call  2/2/2001 DONE
called gave dollar amount
Routing - PLAN CHECK2/1/20012/1/20012/1/2001 PASS
New plans inserted into the original sets submitted 7/18/2000. Permit scope was modified to remove reference to a residential occupancy on the second floor and the plan review comments pertaining to an R3 residential occupancy and required separations was removed. New copies of review reports & permit scope were attached to plans. Plans routed to permit desk.
PLANS/APPL TAKEN TO FRONT DESK  2/1/2001 PASS
TO PERMIT DESK TO ISSUE.
Plan assigned to (DRS)7/24/2000 2/1/2001 PASS
DetailsDan Stuart
2/1/2001 09:43:41 DRS - activity updated through activity BLDA022 from case BLD00-02077.
Additional plans submitted  1/26/2001 DONE
Received small documents and two sets of plan resubmittals from Olson and Associates, forwarded same to Dan Stuart. 1/26/01 DAR
Plan resubmittals received  1/26/2001  
Cover letter declaring the residential occupancy addition to the second floor has been removed from the scope of this permit and the second floor will be used for classrooms and support areas. Plans indicating this condition were provided.
Meeting  1/23/2001  
Met with Leon Burt, Mt. View Church of The Brethren and Russ Phillips, Architect W/ Olson & Associates. After review of outstanding items from the 1988 permitted addition and the upgrades that would be required to add a residential occupancy on the second floor as part of the remodel finish of the 2,907 sq. ft. south portion of the second floor, it was determined that the residential use would be removed from the scope of the permit request. Architect to provide written notice of this request & declaration.
Routing - PLAN CHECK1/19/2001 1/19/2001 FAIL
FIRE CODE ANALYST RECEIVED RESUBMITTALS ON FIRE FLOW & HYDRANTS AND APPROVED THIER PORTION OF PLAN REVIEW WITH APPROAL AS NOTED. Plans on hold until resubmittals in response to plan review are provided by architect.
Routing - FIRE1/18/20011/18/20011/18/2001 PASS
Approved as Noted in Plan Review
Routing - FIRE1/18/20011/18/20011/18/2001 PASS
DetailsBill Alexander
Documentation attached.
Routing - PLAN CHECK12/22/2000 12/22/2000 FAIL
Plans on hold pending resubmittals to fire code and building code plan review comments.
Routing - FIRE12/18/200012/21/200012/21/2000 FAIL
DetailsBill Alexander
Lack UFC information including water supply, hydrants and seperation issues.
Plan Review Completed(1st rev)  12/21/2000 FAIL
Routing - PLAN CHECK7/18/20008/24/200012/18/2000 FAIL
Corrections faxed and mailed to architec. Routing plans to fire code analysts for review.
Plan resubmittals requested  12/18/2000 FAIL
PLANS RE-SUBMITTED ARE IN COMPLETE. NEED DIMENSIONS; BETTER DETAILS FOR FLOOR & ROOF CEILING ASSEMBLIES FOR 1-HOUR OCCUPANCY SEPARATION; CORRECTED DOOR SCHEDULE TO REFLECT 60 MINUTE FIRE DOOR ASSEMBLIES IN PLACE OF 20 MINUTE LISTED, TO INCLUDE THE DOOR FRAMES ARE REQUIRED TO BE LABELED; TO VERIFY THE HYDRANTS REQUIRED IN 1988 WERE PUT IN AND FIRE-FLOW IS AVAILABLE; MORE COMPLETE ACCESSIBLE RESTROOM DETAILS FULLY DIMENSIONED; RESIDENTIAL ESCAPE WINDOW DETAILS TO SHOW COMPLIANCE. ROUTING TO FIRE CODE ANALYST FOR THEIR REVIEW WHILE WAITING FOR FURTHER RESPONSE.
Plan resubmittals received  11/13/2000 DONE
RECEIVED TWO COPIES OF REVISED SHEETS A0, A1, A2, A3, A4, ONE COPY OF LETTER SHEET, ONE COPY OF REVISED COVER SHEET OF APPLICATION, ONE COPY OF PLAN REVIEW COMMENTS. ROUTED TO DAN STUART. KMM
Plan resubmittals requested  8/24/2000 HOLD
Copy of plan review comments faxed and mailed to architects, George Slaughter & Russell Phillips, Olson & Assoctiate Architects with notice that plan review cannot continue until proper plans and application have been re-submitted.
Routing - PLAN CHECK7/26/2000 8/24/2000 HOLD
Plans submitted inadequate for review. Plan review comments to architect for new plan submittals befor eplan review process can continue. Plans on hold behind my desk.
Routing - PUBLIC WORKS7/24/2000 7/26/2000 PASS
Routing - PLANNING7/26/2000 7/26/2000 PASS
Approved as per plans contained in file #CUP00-71
Plan routing begun/TENANTS  7/24/2000 DONE
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE.
Pending Assignment by MYS7/24/2000 7/24/2000 DONE
DetailsMarlene Southard
Plans ACCEPTED BY PLAN TECH  7/20/2000 DONE
Received Certificate of Value  7/18/2000 DONE
Application received  7/18/2000  
Recd Pcfee & Taken To Pln CK  7/18/2000 DONE
Fee Review-notes7/18/20007/18/2000   
Inspection Record Card- Bld