BLD-Final | 6/13/2002 | 6/14/2002 | 6/14/2002 | A | PASS |
Tony Young
|
|
|
call 1st before insp -expired permit- tom -###-#### or homeowner chris-###-####
|
DOC - Permit Finaled | 6/14/2002 | 6/14/2002 | 6/14/2002 | A | PASS |
Tony Young
|
|
|
Finaled by inspector at 6/14/2002 10:33:42 AM
|
(F) Reprint permit | | | 1/7/2002 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/21/2001 | 11/21/2001 | 11/21/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 11/21/2001 2:59:59 PM fire sprinklers complete
|
BLD-Final | 4/19/2001 | 4/20/2001 | 4/20/2001 | A | FAIL |
Dave Hannah
|
|
|
Tom ###-#### - fire sprinkler requirements ok by Chief Renn Ross - bond on file for grading & revegetation n/n on site 4/20/2001 10:29:16 AM
|
BLD-Final | 4/20/2001 | 4/20/2001 | 4/20/2001 | P | PART |
Steven Webb
|
|
|
###-#### Temp. C. of C. #20416 issued--ok by Insp. 325. Letter dated to Chief Ross, ok while pending fire sprinkler issues are addressed. 4/20/2001 2:22:25 PM
|
BLD-Grading Inspection | 4/18/2001 | 4/18/2001 | 4/18/2001 | | BOND |
Rita DeYoung
|
|
|
Rough grading complete according to approved plan. Fine grading and reveg must be bonded. Engineer recommended $1000.00 bond. Upon receipt of bond grading is conditionally approved.
|
BLD-Energy code compliance | 1/3/2001 | 1/4/2001 | 1/4/2001 | A | PASS |
Tony Young
|
|
|
TOM CELL ###-#### ENERGY CODE
|
BLD-Framing/Rough-in | 12/29/2000 | 12/29/2000 | 12/29/2000 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 12/29/2000 at 09:27:01. Contact: ###-####. items on prior correction notice ok,. 12/29/2000 2:49:55 PM
|
BLD-Framing/Rough-in | 12/27/2000 | 12/27/2000 | 12/27/2000 | P | FAIL |
Dave Hannah
|
|
|
fr tom-- ###-#### call 1st before insp c/n on site 12/27/2000 2:01:05 PM
|
BLD-Framing/Rough-in | 11/8/2000 | 11/8/2000 | 11/8/2000 | P | PASS |
Steven Webb
|
|
|
SHEAR NAIL-- TOM ###-####
|
BLD-Framing/Rough-in | 9/12/2000 | 9/13/2000 | 9/13/2000 | A | CANC |
Tony Young
|
|
|
shear wall Tom ###-####
|
BLD-Foundation | 9/11/2000 | 9/12/2000 | 9/12/2000 | A | PART |
Tony Young
|
|
|
###-####
work in progress,,, ok w/ verbal corrections 9/12/2000 12:05:49 PM
|
BLD-Grading Inspection | 9/1/2000 | 9/1/2000 | 9/1/2000 | | PASS |
Rita DeYoung
|
|
|
Soils engineer has approved the subgrade for placement of footings.
|
BLD-Footing | 8/31/2000 | 8/31/2000 | 8/31/2000 | P | FAIL |
Tony Young
|
|
|
###-#### ft insp
need engineer letter on soil, all else appears ok 8/31/2000 2:00:14 PM
|
BLD-Footing | 8/30/2000 | 8/30/2000 | 8/30/2000 | P | NR |
Tony Young
|
|
|
Tim ###-#### early pm
|
Plan assigned to (DJO) | 8/11/2000 | 8/11/2000 | 8/15/2000 | | PASS |
Dan Overy
|
|
|
8/15/2000 08:53:35 DJO - activity updated through activity BLDA022 from case BLD00-02120.
|
Plan Review Report | | | 8/15/2000 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/15/2000 | | DONE |
|
|
|
revised plans received
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2000 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/15/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/15/2000 | | DONE |
|
|
|
|
Telephone call | | | 8/15/2000 | | DONE |
|
|
|
###-#### permit ready for pickup
|
Issue PAID IN FULL permit | | | 8/15/2000 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/14/2000 | | DONE |
|
|
|
08-14-2000 plans returned to ken reed to incorporate engineering to plan sets. will issue when re-submittals are returned if all items have been addressed.
|
Plans ACCEPTED BY PLAN CHECK | | | 8/11/2000 | | PEND |
|
|
|
|
Routing - PLANNING | 7/27/2000 | 7/27/2000 | 7/28/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/21/2000 | 7/21/2000 | 7/27/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 7/21/2000 | 7/21/2000 | 7/27/2000 | | DONE |
Rita DeYoung
|
|
|
Approved as Category 3 with conditions of approval in letter attached to plans. took to terry records 7/21/2000
|
Application received | | | 7/21/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 7/28/2000 | 7/28/2000 | | | PEND |
|
|
|
|
Pending Assignment by DJO | 7/21/2000 | | | | PEND |
Dan Overy
|
|
|
|