Fee Review-notes | 7/24/2000 | 7/24/2000 | 1/28/2004 | | DONE |
|
|
|
fire n/a on cert but there are fire permits
|
BLD-Final | 5/5/2003 | 5/6/2003 | 5/6/2003 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 5/5/2003 at 5:20:11 PM. Contact: ###-####. C/N Scope of 5/6/2003 5:05:48 PM
|
FIRE-Final Inspection | 5/2/2003 | 5/5/2003 | 5/5/2003 | A | PASS |
Troy Cobbley
|
|
|
hank; Phone #: ###-#### Fire life safety finaled 5/5/2003 10:27:04 AM
|
BLD-Aging Inspection | 4/4/2003 | 4/4/2003 | 4/4/2003 | | PART |
Jim Sly
|
|
|
Called for Electr insp....and called for fire insp for friday April 11 4/8/2003 4:13:42 PM
|
FIRE-Final Inspection | 10/21/2002 | 10/21/2002 | 10/21/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide city approved fire sprinkler drawings, provide exit signs as shown of the plans, provide approved door hardware on doors in the remodeled areas, repair and/or provide emergency lights in corridor and portable "EFG"
|
BLD-Conference | 9/3/2002 | 9/4/2002 | 9/4/2002 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/03/2002 at 09:55:01. Contact: ###-####. hank will start calling in finals for other trades 9/4/2002 10:28:34 AM
|
BLD-Conference | 2/26/2002 | 2/27/2002 | 2/27/2002 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/26/2002 at 10:02:56. Contact: ###-####. Called and talked with them, they wanted to know about changing door locations, I recommended the consult with the architect first. (Note see inspection history). 2/27/2002 4:20:35 PM
|
BLD-Conference | 2/7/2002 | 2/8/2002 | 2/8/2002 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 02/07/2002 at 11:55:39. Contact: ###-####. will resume work this spring 2/8/2002 11:18:16 AM
|
BLD-Conference | 9/6/2001 | 9/7/2001 | 9/7/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 09/06/2001 at 16:19:46. Contact: ###-####. they are finishing up the srinkler and alarm system ph 2 they will start ph 3 in the sring we will keep permit open so they can finish work next summer 9/7/2001 9:21:20 AM
|
FIRE-Final Inspection | 8/23/2001 | 8/27/2001 | 8/27/2001 | A | NR |
Joe Tawney
|
|
|
fire fn delilah- ###-####
|
Extend Permit 180 days | | 4/12/2001 | 4/12/2001 | | DONE |
|
|
|
per Dave Hannah
|
BLD-Conference | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | PASS |
Dave Hannah
|
|
|
Per Dave H.
|
BLD-Framing/Rough-in | 9/7/2000 | 9/8/2000 | 9/8/2000 | A | PART |
Jim Sly
|
|
|
Murray ###-#### Partial...OK to cover beams and framing in classrm and library Pend Elect, Mech and Sprinkler R/I approval. 9/8/2000 10:30:06 AM
|
FIRE-Final Inspection | 9/8/2000 | 9/8/2000 | 9/8/2000 | P | PART |
Joe Tawney
|
|
|
Russ ###-#### Spklr rough in One head too close to wall in closet 9/8/2000 4:33:08 PM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/7/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/7/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/7/2000 | | DONE |
|
|
|
|
Telephone call | | | 9/7/2000 | | DONE |
|
|
|
left message w/dollar amount
|
Issue PAID IN FULL permit | | | 9/7/2000 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 7/25/2000 | | 9/7/2000 | | PASS |
Mike Otto
|
|
|
9/7/2000 09:05:35 MLO - activity updated through activity BLDA022 from case BLD00-02141.
|
Routing - FIRE | 9/1/2000 | 9/6/2000 | 9/6/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 9/6/2000 | | 9/6/2000 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/5/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM HUTCHSON SMITH ARCHITECTS, TWO SETS OF SHEETS A0, A1 AND A2, FORWARDED SAME TO MIKE OTTO.
9/5/00 DAR
|
Routing - PLAN CHECK | 8/28/2000 | | 8/31/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT.
|
Plan resubmittals requested | | | 8/31/2000 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 8/28/2000 | | DONE |
|
|
|
1 response to city comments 1 revised drwas 1 ea details. A0 A1A2 1 EA SHEET 600 SHEET 601 SHEET 800 SHEET 801 SHEET 802 SHEET 803 SHEET 804
|
Routing - FIRE | 7/31/2000 | 8/3/2000 | 8/4/2000 | | FAIL |
Bill Alexander
|
|
|
Need UBC and UFC related seperation, exiting with relation to alarms, sprinklers, etc.
|
Plan Review Completed(1st rev) | | | 8/4/2000 | | FAIL |
|
|
|
plans sent to plan check
|
Routing - PLAN CHECK | 7/26/2000 | | 7/31/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Plan resubmittals requested | | | 7/31/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Routing - PUBLIC WORKS | 7/25/2000 | | 7/26/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 7/24/2000 | | 7/25/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 7/25/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE. No Planning approval required per Marty Santoyo.
|
Plans ACCEPTED BY PLAN TECH | | | 7/24/2000 | | DONE |
|
|
|
FAXED DON HUTCHISON ARCHITECT/ENGINEER OF RECORD FORM TO FILL OUT AND GET SIGNED. 7/24/00 DAR
|
Application received | | | 7/24/2000 | | |
|
|
|
|