Permanent occupancy | | | 3/27/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9087 issued 3-27-02 to Micron Technology, Inc., Bldg. #36.
|
Permanent Occupancy | | 3/15/2002 | 3/15/2002 | | DONE |
|
|
|
|
BLD-Final | 3/15/2002 | 3/15/2002 | 3/15/2002 | P | PASS |
Jim Storey
|
|
|
Scheduled by Inspector: 301 On 3/15/2002 4:19:52 PM final ok 3/15/2002 4:32:26 PM
|
Fee Review-notes | 2/27/2001 | 2/27/2001 | 12/14/2001 | | DONE |
|
|
|
|
Fee Review-notes | 8/7/2000 | 8/7/2000 | 12/14/2001 | | DONE |
|
|
|
|
Temporary occupancy | | | 12/10/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4682 issued 12-10-01 to Micron, Bldg. #36 offices.
|
FIRE-Final Inspection | 11/20/2001 | 11/21/2001 | 11/21/2001 | A | PASS |
Rick Jackson
|
|
|
dave- ###-#### fire fn
|
FIRE-Final Inspection | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | FAIL |
Rick Jackson
|
|
|
Added by Inspector: 409 On 11/20/2001 7:34:23 PM basement battery room doors; hazard signs
|
BLD-Final | 11/15/2001 | 11/16/2001 | 11/16/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/15/2001 at 07:50:17. Contact: ###-####. temp ok pendingf others. 11/16/2001 12:56:24 PM
|
BLD-Conference | 10/18/2001 | 10/19/2001 | 10/19/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/18/2001 at 10:10:23. Contact: ###-####.
|
Print Occupancy Form | | | 10/19/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/19/2001 | | DONE |
|
|
|
|
BLD-Final | 10/13/2001 | 10/15/2001 | 10/15/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/13/2001 at 16:05:47. Contact: ###-####. steve will e-mail c/n punch list. door isues/ some fire chalking. 10/15/2001 3:49:38 PM
|
BLD-Final | 10/9/2001 | 10/10/2001 | 10/10/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/09/2001 at 14:40:52. Contact: ###-####. need door butt listing for rated assemblie. 10/11/2001 9:46:08 AM
|
BLD-Final | 9/26/2001 | 9/26/2001 | 9/26/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/26/2001 at 09:39:30. Contact: ###-####. fire stopping/fire prooffing 1st floor. 9/27/2001 6:24:12 PM
|
BLD-Final | 9/20/2001 | 9/21/2001 | 9/21/2001 | A | NR |
Jim Storey
|
|
|
###-#### STEVE
|
BLD-Final | 9/13/2001 | 9/14/2001 | 9/14/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/13/2001 at 17:23:16. Contact: ###-####. cable trays 2 floor ok all but 2 locations/ c/n for grid wires. 9/17/2001 1:04:54 PM
|
BLD-Final | 9/12/2001 | 9/14/2001 | 9/13/2001 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/12/2001 at 14:17:25. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/13/2001 at 17:21:53.
|
BLD-Framing/Rough-in | 6/27/2001 | 6/28/2001 | 6/28/2001 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/27/2001 at 17:20:17. Contact: ###-####. cafatria curtian walls ok/ interior framing ok pending others 6/29/2001 10:37:15 AM
|
FIRE-Sprinkler Rough-in | 5/21/2001 | 5/22/2001 | 5/22/2001 | P | FAIL |
Rick Jackson
|
|
|
Forrest ###-#### heads overspaced in areas 7 and 8 first floor. main office areas from soffit and office walls; not approved for cover 5/22/2001 3:24:48 PM
|
BLD-Wall cover | 5/17/2001 | 5/18/2001 | 5/18/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/17/2001 at 12:11:42. Contact: ###-####. cable coridor assemblies in place at south end of coridor ok at marked locations only ok. 5/18/2001 11:39:38 AM
|
BLD-Other | 5/14/2001 | 5/14/2001 | 5/14/2001 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 05/14/2001 at 09:42:10. Contact: . fire stopping and lights for grid/ need fire and mec. insp. 5/15/2001 11:06:27 AM
|
BLD-Framing/Rough-in | 5/4/2001 | 5/4/2001 | 5/4/2001 | P | PART |
Jim Storey
|
|
|
wall cover steve- ###-####
|
BLD-Wall cover | 4/24/2001 | 4/25/2001 | 4/25/2001 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/24/2001 at 09:22:04. Contact: ###-####. previous c/n made ok. 4/25/2001 4:58:09 PM
|
BLD-Wall cover | 4/18/2001 | 4/19/2001 | 4/19/2001 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/18/2001 at 14:43:14. Contact: ###-####. corridor bld b an c 1st and 2nd floors ok top of walls/raised floor sys need to fire stop bld b. 4/19/2001 5:25:35 PM
|
BLD-Conference | 4/2/2001 | 4/5/2001 | 4/5/2001 | A | PASS |
Jim Storey
|
|
|
11:00 is the time you set with him. ###-#### ext 241
|
BLD-Framing/Rough-in | 3/28/2001 | 3/29/2001 | 3/29/2001 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/28/2001 at 16:50:54. Contact: ###-####. area septration and shaft opening protection c/n/// 3/30/2001 11:41:06 AM
|
BLD-Wall cover | 3/9/2001 | 3/12/2001 | 3/12/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/09/2001 at 08:51:19. Contact: ###-####. 1 st floor area 7 and 8 ok for cover. 3/12/2001 9:38:50 AM
|
BLD-Framing/Rough-in | 3/2/2001 | 3/5/2001 | 3/5/2001 | A | PART |
Jim Storey
|
|
|
###-#### ext 241 2nd floor area 7/8 ok to top hang walls pending ele approval. for balance of wall cover reinsp required. 3/5/2001 4:34:34 PM
|
BLD-Framing/Rough-in | 2/22/2001 | 2/23/2001 | 2/23/2001 | A | NR |
Jim Storey
|
|
|
Steve Smith ###-####
|
BLD-Framing/Rough-in | 2/12/2001 | 2/12/2001 | 2/12/2001 | P | PART |
Jim Storey
|
|
|
Added by Inspector: 301 On 2/12/2001 1:02:44 PM c/n submital for colum protection, ele box protection < 24 spacing, pre rock for plumb pipe fire stopping at 17/d,e , wrap beam to maintain corrdor at 16,17/d,e.
|
Plan resubmittals received | | | 11/6/2000 | | DONE |
|
|
|
Received two copies of revised sheet A2.1.0.1FX, and one copy of letter to John M. from Rick Hunter. Routed to John M. KMM
|
Issue & PRINT to be Invoiced | | | 11/3/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/26/2000 | | 11/2/2000 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 7/28/2000 | | 11/2/2000 | | PASS |
John Menard
|
|
|
11/2/00 11:38:14 JCM - activity updated through activity BLDA022 from case BLD00-02159.
|
Plan resubmittals received | | | 10/31/2000 | | DONE |
|
|
|
RECEIVED ONE COPY OF RESPONSE LETTER TO INFO REQUEST FROM BLD. DEPT. TWO COPIES OF ORIT. INFO REQUEST LETTER. TWO COPIES OF SPECT. SECT. 15891. TWO COPIES OF ICBO REPORT ON FIRE MASTER RATED (GREASE DUCT) WRAP. TWO COPIES OF REVISED SHEETS A2.10.1EX, A2.1.0.1FX, A2,1,01, A2.1.1, A2.1.2, A3.1.0, A9.1.0.1, A9.1.1. ROUTED TO JOHN M. KMM
|
Routing - FIRE | 10/24/2000 | 10/26/2000 | 10/26/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals requested | | | 10/24/2000 | | |
|
|
|
SENT RICK HUNTER AT HDR ARCHITECTS A LETTER REQUESTING ADDITIONAL REVISIONS. JCM
|
Plan resubmittals received | | | 10/18/2000 | | DONE |
|
|
|
RECEIVED TWO SETS OF UPDATED DRAWINGS PLUS TWO SETS OF REVISED AND REISSUED DRAWINGS PLUS SMALL DOCUMENTS. FORWARDED SAME TO JOHN MENARD. 10/18/00 DAR
|
Routing - FIRE | 9/5/2000 | 9/8/2000 | 9/8/2000 | | FAIL |
Bill Alexander
|
|
|
Many UFC issues needing addressed
|
Plan Review Completed(1st rev) | | | 9/8/2000 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 9/5/2000 | | |
|
|
|
MAILED THE ARCHTECT OF RECORD A COPY OF THE COMMENT LIST REQUESTING REVISIONS. JCM
|
Routing - PLAN CHECK | 8/7/2000 | | 9/5/2000 | | FAIL |
|
|
|
|
Routing - PLUMBING | 8/3/2000 | | 8/7/2000 | | PASS |
|
|
|
refer to bld00-02158 for comments
|
Routing - PUBLIC WORKS | 7/31/2000 | | 8/3/2000 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 7/31/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/31/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/26/2000 | | HOLD |
|
|
|
PLANS WENT OUT TO CENTRAL DISTRICT HEALTH FOR THE CAFETERIA PORTION OF THE PLANS. OFFICE AND CAFETERIA WERE SUBMITTED ON THE SAME SET OF PLANS SEPARATE PERMITS . THIS PERMIT IS FOR THE OFFICE T.I. DAVE R. CONTACTED MARY CAHILL AT ###-#### TO TAKE PLANS TO CDH. KMM
|
Received Certificate of Value | | | 7/26/2000 | | DONE |
|
|
|
|
Application received | | | 7/25/2000 | | |
|
|
|
|