Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD00-02170
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMIC #35-(PCS 3158)
Customer Number35-003158
ePlanReviewNo
Description
MICRON BUILDING #35 * TO CONSTRUCT A NEW 52,000 SQ. FT., TWO STORY FACILITIES MAINTENANCE SHOP AND OFFICE BUILDING AND RELATED SITE IMPROVEMENTS. THIS BUILDING IS CONSTRUCTED OF CONCRETE TILT-UP EXTERIOR WALLS, STEEL INTERIOR FRAME, CONCRETE AND METAL FLOOR PAN AND METAL ROOF DECK WITH CLASS I ROOF COVERING. THIS BUILDING IS FULLY FIRE SPRINKLED. THE SPINKLERS ARE BEING USED FOR ALLOWABLE AREA INCREASE. THIS BUILDING WILL CONTAIN MAINTENANCE SHOPS AND LAUNDRY FACILITY AT THE FIRST FLOOR AND OFFICES ON THE SECOND FLOOR. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. PC#598-00/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes7/26/20007/26/20004/17/2002 DONE
Permanent occupancy  3/11/2002 DONE
Perm. Occ. Cert. #9060 issued 3-11-02 to Micron for their two story facilities maintenance shop.
Permanent Occupancy 3/4/20023/4/2002 DONE
Details
BLD-Final3/1/20023/4/20023/4/2002APASS
DetailsJim Storey
Scheduled by Inspector: 407 On 3/1/2002 11:26:04 AM final ok for c.o. 3/4/2002 2:52:12 PM
BLD-Final2/28/20023/1/20023/1/2002ACANC
DetailsRuss Owen
###-#### John ,I called left message to call me back I have set this back up for am monday.1/2002 11:51:03 AM 3/1/2002 11:54:03 AM
BLD-Final2/20/20022/21/20022/21/2002AFAIL
DetailsJim Storey
###-#### DON fire stopping needed at plm. 2/21/2002 9:20:13 AM
FIRE-Final Inspection1/31/20022/1/20022/1/2002APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/31/2002 at 08:03:29. Contact: ###-####.
BLD-Final1/31/20022/1/20022/1/2002PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 01/31/2002 at 08:04:18. Contact: ###-####. recieved engineers approval letter and special insp approval. ok for temp. 2/1/2002 2:41:28 PM
Temporary occupancy  2/1/2002 PART
Temp. Occ. Cert. #4716 issued 2-1-02 to Micron Technology, Bldg. #35.
FIRE-Final Inspection1/17/20021/17/20021/17/2002AFAIL
DetailsRick Jackson
Added by Inspector: 409 On 1/17/2002 11:01:35 AM need exit signs on second floor; sprinkler certification paperwork; tested alarms - okay with monor corections
BLD-Conference11/15/200111/16/200111/16/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/15/2001 at 10:55:35. Contact: ###-####. fire shudder test req/ fire stop top of corridor walls south east exit. pending all other trades. need engineers sign off and special insp. final letter. 11/16/2001 11:02:24 AM
BLD-Conference11/15/200111/19/200111/15/2001ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 11/15/2001 at 10:34:15. Contact: . Disp set to [CANC] by a contractor via Hello! on 11/15/2001 at 10:54:16.
BLD-Final10/30/200111/5/200111/1/2001ACANC
DetailsJim Storey
###-#### Disp set to [CANC] by a contractor via Hello! on 11/01/2001 at 14:37:43.
FIRE-Final Inspection10/29/200111/1/200111/1/2001ANR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/29/2001 at 14:46:09. Contact: ###-####. will reschedule 10/31/2001 5:07:37 PM
BLD-Conference10/18/200110/19/200110/19/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/18/2001 at 14:46:29. Contact: ###-####.
BLD-Other9/17/20019/18/20019/18/2001PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/17/2001 at 12:59:16. Contact: ###-####. 2 nd floor ceilling/ need speader bars. 9/18/2001 10:40:59 AM
BLD-Other9/5/20019/7/20019/7/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 09/05/2001 at 15:22:43. Contact: ###-####. south 1/2 ceilling ok. 9/10/2001 5:54:47 PM
BLD-Framing/Rough-in8/8/20018/9/20018/9/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 08/08/2001 at 09:42:32. Contact: ###-####. hard ceilling at west dock beams protccted and support grid ok for cover/ grid ceilling 2 nd floor work in progess no problems. 8/9/2001 11:39:12 AM
(F) Reprint permit  8/3/2001 DONE
BLD-Framing/Rough-in7/9/20017/10/20017/10/2001APASS
DetailsJim Storey
Jualo ###-####
BLD-Framing/Rough-in5/16/20015/17/20015/17/2001APASS
DetailsJim Storey
Hulo ###-#### 1 & 2nd floor framing ok for cover / arch to address west stair for opening protection. 5/17/2001 9:50:16 AM
BLD-Framing/Rough-in5/10/20015/14/20015/14/2001APASS
DetailsJim Storey
###-#### 2nd floor ok for cover. 5/14/2001 4:34:15 PM
BLD-Framing/Rough-in5/3/20015/8/20015/8/2001AFAIL
DetailsJim Storey
Jullo ###-#### c/n for rfi to arch. 5/8/2001 1:03:24 PM
BLD-Framing/Rough-in5/1/20015/3/20015/3/2001APART
DetailsSteven Webb
julio-- ###-#### fr Partial--Building 35-2nd floor offices at east and west end. 5/3/2001 9:55:27 AM
BLD-Framing/Rough-in4/16/20014/16/20014/16/2001PPART
DetailsJim Storey
###-#### fur out walls ok for cover / c/n for out standing special insp. issues. 4/16/2001 6:31:30 PM
BLD-Framing/Rough-in3/14/20013/15/20013/15/2001APART
DetailsJim Storey
###-#### diaphram roof welds ok south end. reviewed col/fire assemblie/ 3/15/2001 4:37:51 PM
BLD-Framing/Rough-in3/12/20013/13/20013/13/2001AFAIL
DetailsJim Storey
WELDING ON ROOF AND FLOOR DECKING\\###-#### missing welds and botton punching on roof and 2 nd floor / special insp need to verify when corected. 3/13/2001 10:18:49 AM
BLD-Other2/28/20012/28/20012/28/2001 FAIL
DetailsJim Storey
special insp report feb 16 2001. tilt panels 14,15,16,20,22,23 air spec. 4% to 7% test results were 2% need engineer of record to justify not meetting freeze protection provision and design spec.
BLD-Foundation1/18/20011/18/20011/18/2001PPART
DetailsJim Storey
re-bar julio ###-#### placed with special insp. pending report. 1/18/2001 4:14:29 PM
BLD-Framing/Rough-in1/4/20011/5/20011/5/2001PPART
DetailsJim Storey
REBAR JULIO-- ###-#### placed with special insp. pending report. 1/8/2001 7:57:48 AM
BLD-Other12/29/200012/29/200012/29/2000AFAIL
DetailsBill VanDegrift
Added by Inspector: 330 On 12/29/2000 3:57:54 PM left correction notice - secure a permit for sewer and water lines relocated outside the building, provide documentation from micron reguarding testing and inspection for determination of code compliance, - secure a licensed plumbing contractor to permit 10" storm drain under the building apply test and call for inspection- do not lay asphalt over exterior piping or concrete over interior storm drain untill all waor has been approved for cover.
BLD-Footing12/21/200012/22/200012/22/2000APART
DetailsCarl Dependahl
Garry ###-####; pend spec. insp reports 12/22/2000 10:14:24 AM
BLD-Footing12/14/200012/15/200012/15/2000ANR
DetailsJim Storey
###-####
BLD-Foundation12/13/200012/13/200012/13/2000PPART
DetailsJim Storey
###-#### REBAR placed with special insp. 12/13/2000 4:43:04 PM
BLD-Foundation12/5/200012/5/200012/5/2000PPART
DetailsJim Storey
###-#### work in progess covered with s/i 12/5/2000 3:34:36 PM
FIRE-Final Inspection11/27/200011/28/200011/28/2000PCANC
DetailsRick Jackson
Scheduled by a contractor via Hello! on 11/27/2000 at 14:55:29. Contact: ###-####.//// entered by contractor in error 11/28/2000 3:22:58 PM
BLD-Footing11/27/200011/28/200011/28/2000PPART
DetailsJim Storey
###-#### p/w/s/i/ pending report. 11/28/2000 3:49:21 PM
(F) Reprint permit  10/16/2000 DONE
Print Occupancy Form  10/13/2000 DONE
Inspection Record Card- Bld  10/13/2000 DONE
Telephone call  10/13/2000 DONE
emailed permit ready
Issue & PRINT permit  10/13/2000 DONE
Plan resubmittals received  10/12/2000 DONE
RECEIVED TWO COPIES OF REVISED SHEETS O, C1.1, C2.0, A0.2, A0.3, A2.1.3, A3.2.1, A4.3.1 ROUTED TO JOHN M. KMM
Plan Reviewer's activity  10/12/2000 PASS
REVIEWED AND APPROVED FINAL PLAN RESUBMITTALS. JCM
Routing - FIRE10/12/2000 10/12/2000 PASS
Resubmittal acceptable
PLANS/APPL TAKEN TO FRONT DESK  10/12/2000 PASS
Plan assigned to (JCM)7/27/2000 10/12/2000 PASS
DetailsJohn Menard
10/12/00 16:02:25 JCM - activity updated through activity BLDA022 from case BLD00-02170.
Routing Off Site - STRUCTURAL8/25/2000 10/12/2000 PASS
ROUTED REVISED PLANS TO OUTSIDE ENG. KMM RECEIVED AN E-MAIL FROM THE CONSULTING STRUCTURAL ENGINEER APPROVING THE STRUCTURAL RESUBMITTALS. JCM
Routing - FIRE10/10/2000 10/11/2000 FAIL
Plan resubmittals received  10/11/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM ZGA ARCHITECTS SMALL DOCUMENTS AND TWO SETS OF SHEET C1.1 AND C2.0, FORWARDED SAME TO JOHN MENARD. 10/11/00 DAR
Routing - PLAN CHECK10/9/2000 10/10/2000  
Routing - FIRE10/5/2000 10/9/2000 FAIL
Resubmittal does not address the 9/15/2000 Fire Review comments. Spoke with Frank Kvapil and Jared Hetherington 10/9. They will fax a written response and will re-submit C2.0 showing gate at NE corner to provide required access.
Plan resubmittals requested  10/5/2000  
REVIEWED RESUBMITTED PLAN SHEETS AND MAILED RON MOSS AT ZGA A LETTER REQUESTING ADDITIONAL REVISIONS. JCM
Routing - PLAN CHECK9/18/2000 10/5/2000  
Plan resubmittals received  10/3/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM ZGA , FORWARDED SAME TO JOHN MENARD. 10/3/00 DAR
Plan Reviewer's activity  9/22/2000 FAIL
REVIEWED RESPONSE LETTER FROM ARCHITECT OF RECORD AND RESPONSED WITH A LETTER TO THE ARCHITECT AGAIN REQUESTING THE REQUIRED RESUBMITTALS. JCM
Plan Review Completed(1st rev)  9/15/2000 FAIL
Not approved by Bldg and failed Fire review.
Routing - FIRE9/8/2000 9/15/2000 FAIL
faxed comments to architect
Plan resubmittals received  9/14/2000 DONE
RECEIVED TWO COPIES OF RESPONSE TO PLAN REVIEW. NONE OF THE COMMENTS HAVE DRAWING REVISIONS. ALL RESPONSES ARE IN WRITTEN FORM. ROUTED TO JOHN M. KMM
Routing - PLAN CHECK8/25/2000 9/8/2000 FAIL
Plan resubmittals requested  9/8/2000  
MAILED THE ARCHITECT OF RECORD A COPY OF THE COMMENT LIST REQUESTING REVISIONS. JCM
Plan resubmittals received  8/25/2000  
1 COPY OF STRUCTURAL PLAN REVIEW RESPONSE LETTER
3 COPIES STRUCTURAL CALCULATION-SUPPLEMENT
3 COPIES STRUCTURAL DRAWINGS-REVISED S2.1 S2.2 S2.3 S3..1 S3.2 S4.1 S4.2 S5.1 S5.2 S5.2.1 S5.5 S5.6 S6.7/TAKEN TO JOHN M
Routing - PLUMBING8/18/2000 8/25/2000 PASS
per plans and 97 upc
Routing Off Site - STRUCTURAL7/27/2000 8/18/2000 FAIL
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM RECEIVED COMMENT LIST FROM CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS. JCM
Plan resubmittals requested  8/18/2000  
FAXED A COPY OF THE CONSULTING ENGINEER'S COMMENT LIST TO FRANK KVAPIL AND PAUL MARCOLINA REQUESTING REVISIONS. JCM
Routing - PLANNING8/3/2000 8/18/2000 PASS
NO DESIGN REVIEW REQUIRED PER T-2 ORDINANCE
Plan resubmittals received  8/10/2000  
RECIVED 5 COPIES OF RIVISED P2.1.2. BLUELINES 8/10/2000/PE
Routing - PUBLIC WORKS7/27/2000 8/3/2000 PASS
Plan routing begun/NEW & ADDTN  7/27/2000 DONE
Plans ACCEPTED BY PLAN TECH  7/27/2000 DONE
DID NOT RECEIVE DRAINAGE CALCS. LET BRIAN DEAL WITH IT. KMM
Received Certificate of Value  7/27/2000 DONE
Application received  7/26/2000