Case Summary (BLD) | | | 5/9/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/27/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 4/25/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/25/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 4/25/2005 | | |
|
|
|
|
Fee Review-notes | 9/23/2002 | 9/23/2002 | 12/6/2002 | | DONE |
|
|
|
|
Permanent Occupancy | | 2/25/2002 | 2/25/2002 | | DONE |
|
|
|
|
BLD-Final | 2/25/2002 | 2/25/2002 | 2/25/2002 | P | PASS |
Carl Dependahl
|
|
|
Cathy has the card; struct ok for c/o 2/25/2002 4:21:30 PM
|
BLD-Conference | 2/25/2002 | 2/25/2002 | 2/25/2002 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/25/2002 4:19:26 PM w/ 409 re final...fire ok
|
Permanent occupancy UNPAID FEE | | | 2/25/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9045 issued 2-25-02 to the Idanha Pub and Grill.
|
FIRE-Alarm Testing | 2/5/2002 | 2/6/2002 | 2/7/2002 | A | CANC |
Rick Jackson
|
|
|
###-#### BRETT per Dave Miller - not to sign for perm occupancy pending resolution of kitchen exhaust system 2/7/2002 3:55:43 PM
|
FIRE-Final Inspection | 2/4/2002 | 2/5/2002 | 2/5/2002 | A | NR |
Rick Jackson
|
|
|
fn fire christina ###-#### will reschedule for 2/6 2/5/2002 3:31:27 PM
|
BLD-Final | 2/4/2002 | 2/5/2002 | 2/5/2002 | P | NR |
Carl Dependahl
|
|
|
christina-- ###-#### fn occ
|
BLD-Conference | 1/28/2002 | 1/28/2002 | 1/28/2002 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/28/2002 9:46:30 AM w/GS re Schott's...south exit has had panic hdwe. installed
|
BLD-Final | 12/17/2001 | 12/18/2001 | 12/18/2001 | A | NR |
Carl Dependahl
|
|
|
BRET ###-####
|
BLD-Final | 12/18/2001 | 12/18/2001 | 12/18/2001 | P | NR |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 12/18/2001 11:44:00 AM ###-#### Brett...recall 12/18/2001 12:11:39 PM
|
BLD-Final | 12/18/2001 | 12/18/2001 | 12/18/2001 | P | NR |
Carl Dependahl
|
|
|
Scheduled by Inspector: 340 On 12/18/2001 2:37:55 PM ###-#### bret...need remove add'l latch at exit 12/18/2001 4:42:32 PM
|
BLD-Final | 11/29/2001 | 11/29/2001 | 11/29/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/29/2001 2:15:38 PM 2nd c/n re south exit doors, resolve grease duct issues; Notice & Order issued to complete c/n items or vacate (total 30 days)
|
BLD-Conference | 10/19/2001 | 10/19/2001 | 10/19/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/19/2001 2:27:01 PM w GS...need make corrections at exit door asap
|
BLD-Conference | 10/16/2001 | 10/16/2001 | 10/16/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/16/2001 2:01:33 PM w/ Brett re prior c/n
|
BLD-Conference | 10/9/2001 | 10/9/2001 | 10/9/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/9/2001 8:43:48 AM w/ GS re meeting w/ Ken Howell & Dave Miller...chimney/grease duct to be evaluated by Creighton Eng'g...keep c/n
|
BLD-Conference | 9/25/2001 | 9/25/2001 | 9/25/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 9/25/2001 4:52:41 PM re: Complaints of removal of exit & some exterior illumination; exit light must be provided, exterior is subject to "P&Z" or Historic review.
|
BLD-Conference | 8/28/2001 | 8/28/2001 | 8/28/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/28/2001 8:31:18 AM w/ Dave M & GS, re schotts grease duct
|
BLD-Conference | 8/20/2001 | 8/21/2001 | 8/21/2001 | A | PART |
Carl Dependahl
|
|
|
As per our phone call; W/ GS, need Fire Dept. clarification re grease duct. Keep c/n re exit door. 8/22/2001 10:09:28 AM
|
BLD-Conference | 8/17/2001 | 8/17/2001 | 8/17/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/17/2001 10:31:33 AM w/Christina re exit door, keep c/n.
|
BLD-Conference | 8/16/2001 | 8/16/2001 | 8/16/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/16/2001 8:08:17 AM w/ P Schott re c/n, UBC 1007.2.5 & 1003.3.1.1 re exit doors
|
BLD-Final | 8/14/2001 | 8/15/2001 | 8/15/2001 | P | FAIL |
Carl Dependahl
|
|
|
FN OCC KRISTINA- ###-#### c/n re exit door; partial insp only, need resolve kitchen exhaust issues w BFD, obtain all other perm ok's. 8/15/2001 1:17:24 PM
|
BLD-Framing/Rough-in | 8/1/2001 | 8/3/2001 | 8/3/2001 | A | NR |
Carl Dependahl
|
|
|
unable to contact; keep c/n (to meet w/ door hdwe sales at site ... called Brett to ask to reset insp 8/8/2001 4:35:41 PM 8/8/2001 4:36:34 PM
|
Telephone call | | | 7/23/2001 | | DONE |
|
|
|
Talked to Brett (contractor) re: status of temp. occ.
|
BLD-Conference | 7/11/2001 | 7/11/2001 | 7/11/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/11/2001 11:05:25 AM w/ Brett re south exit mod. install permanent door stop so doors don't conflict
|
BLD-Conference | 6/11/2001 | 6/11/2001 | 6/11/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/11/2001 2:18:03 PM w/ Sam Rogers...req'd exit should be ok if doorstop made permanent or appropriate method of blocking or coordinating door swing at "conflicting" doors to exterior
|
BLD-Final | 6/11/2001 | 6/11/2001 | 6/11/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/11/2001 4:25:41 PM Per UBC 1007 .2.5. install panic or "3-point" latch,(or approved equal) c/n issued to Peter Schott; also need permanent door stop from bsmt/banquet rm. exit
|
Fee Review-notes | 7/27/2000 | 7/27/2000 | 5/30/2001 | | DONE |
|
|
|
|
BLD-Final | 5/22/2001 | 5/23/2001 | 5/23/2001 | A | PART |
Jim Storey
|
|
|
Brett ###-#### panic hard ware back ordered for lobby exit to be maintaned/ handrail in 108 temp to be rechecked on perm instaltion. occ load signs temp to be check at perm occ. 5/23/2001 10:03:03 AM
|
FIRE-Final Inspection | 5/23/2001 | 5/23/2001 | 5/23/2001 | P | FAIL |
Rick Jackson
|
|
|
Brett ###-#### still on TCO. gas valve operated properly for kitchen hood system; door hardware still not compliant for bar area; exit signs need repair in banquest room; extinguishers need to hung and current inspection tag 5/23/2001 2:23:24 PM
|
Temporary occupancy | | | 5/23/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4547 issued 5-23-01 to the Idanha Pub and Grill.
|
FIRE-Final Inspection | 5/22/2001 | 5/22/2001 | 5/22/2001 | P | PART |
Rick Jackson
|
|
|
###-#### Brett per agreement with Dave Miller and owner the kitchen system to be reviewed by engineer; okay to occupy bar 5/23/2001 9:12:15 AM
|
BLD-Final | 5/22/2001 | 5/22/2001 | 5/22/2001 | P | FAIL |
Jim Storey
|
|
|
###-#### handrail and occ signage/ panic hardware to lobby pending fire sign off. 5/22/2001 4:14:08 PM
|
FIRE-Final Inspection | 5/21/2001 | 5/21/2001 | 5/21/2001 | P | NR |
Rick Jackson
|
|
|
Brett ###-####
|
BLD-Final | 5/21/2001 | 5/21/2001 | 5/21/2001 | P | NR |
Carl Dependahl
|
|
|
###-#### Brett
|
Plan resubmittals received | | | 5/2/2001 | | DONE |
|
|
|
Received three copies of revsied sheets P2.1 One cover letter to Dave Lightfoot, One cover letter with adendum to Carl D. Routed plans and letter to David L. and one letter to Carl D. with adendum. KMM
|
BLD-Framing/Rough-in | 4/17/2001 | 4/18/2001 | 4/18/2001 | A | CANC |
Jim Storey
|
|
|
cover for kitchen Ron ###-####
|
BLD-Conference | 4/17/2001 | 4/17/2001 | 4/17/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/17/2001 5:47:05 PM w/ bldr, owner (Schotts), hvac installer, etc.re kitchen finals
|
BLD-Conference | 4/9/2001 | 4/9/2001 | 4/9/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/9/2001 1:54:25 PM w/ contractor re c/n...& w/ Rick J. & GS re range grease duct/shaft...not part of project???
|
BLD-Conference | 4/3/2001 | 4/3/2001 | 4/3/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/3/2001 9:33:58 AM w/ Cary of A-1 lock...need approved plans for determination of hdwe...have plans onsite.
|
BLD-Framing/Rough-in | 3/29/2001 | 3/29/2001 | 3/29/2001 | P | PART |
Tom Arcoraci
|
|
|
1st floor ###-#### wip ok to cover lid in office behind elevator 3/29/2001 2:25:47 PM
|
BLD-Conference | 3/20/2001 | 3/20/2001 | 3/20/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/20/2001 10:02:27 AM w/ bldr re firestops at lids
|
BLD-Framing/Rough-in | 3/15/2001 | 3/16/2001 | 3/16/2001 | A | PART |
Carl Dependahl
|
|
|
1st floor ###-####; restaurant area lid ok, wine bar area lid only ok 3/16/2001 10:45:49 AM
|
BLD-Framing/Rough-in | 3/6/2001 | 3/7/2001 | 3/7/2001 | A | PART |
Carl Dependahl
|
|
|
###-#### ok to cover main bar area only 3/7/2001 4:28:33 PM
|
BLD-Framing/Rough-in | 3/6/2001 | 3/6/2001 | 3/6/2001 | P | PART |
Carl Dependahl
|
|
|
###-####; walls ok 3/6/2001 2:48:06 PM
|
BLD-Conference | 12/13/2000 | 12/14/2000 | 12/14/2000 | A | FAIL |
Carl Dependahl
|
|
|
c/n issued for PROFIT meeting 12/14/2000 2:42:45 PM
|
Issue PAID IN FULL permit | | | 9/13/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/11/2000 | | DONE |
|
|
|
|
Telephone call | | | 9/11/2000 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY
|
Routing - PLUMBING | 9/6/2000 | | 9/11/2000 | | PASS |
|
|
|
hot and cold water connections may be required to be extended to mains, verify with field inspector
|
Routing - PLAN CHECK | 9/11/2000 | | 9/11/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/11/2000 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 8/11/2000 | | 9/11/2000 | | PASS |
Carl Westfall
|
|
|
9/11/00 11:03:44 CJW - activity updated through activity BLDA022 from case BLD00-02175.
|
Routing - PLAN CHECK | 8/29/2000 | | 9/6/2000 | | PASS |
|
|
|
Resubmittal review.
|
Plan Reviewer's activity | | | 9/6/2000 | | PASS |
|
|
|
The drawings were approved, with conditions, after resubmittal review.
|
Routing - FIRE | 8/22/2000 | 8/23/2000 | 8/29/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 8/29/2000 | | |
|
|
|
Failed in plumbing and plan review.
|
Routing - PLAN CHECK | 8/15/2000 | | 8/22/2000 | | |
|
|
|
Drawings failed first review.
|
Plan resubmittals received | | | 8/21/2000 | | DONE |
|
|
|
RECEIVED REVISED SHEETS P1.0, P2.0, P2.1. ROUTED TO CARL .
|
Plan Reviewer's activity | | | 8/21/2000 | | |
|
|
|
UBC plan review started August 21, 2000 and finished the next day. A response is required from the architect. See the conditions list.
|
Routing - PLUMBING | 8/14/2000 | | 8/15/2000 | | |
|
|
|
First review failed. Additional cross connection may be required, vents required downstream of all traps, provide a plan showing the size, location, and loading for the connections to existing waste and water systems.
|
Routing - PUBLIC WORKS | 8/11/2000 | | 8/14/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 7/27/2000 | | 8/11/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 8/11/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2000 | | DONE |
|
|
|
|
Application received | | | 7/27/2000 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/27/2000 | | |
|
|
|
JOHN PRICE HAD TO TAKE PLANS TO CDH TO GET SIGNED OFF. KMM
|
Plan resubmittals received | | | | | |
|
|
|
RESPONSE LETTER. REVISED SHEETS A.2.1 A3.0
|
Inspection Record Card- Bld | | | | | |
|
|
|
|