Case Summary (BLD) | | | 12/30/2008 | | |
|
|
|
|
Fee Review-notes | 7/27/2000 | 7/27/2000 | 2/8/2002 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/7/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/24/2000 | 8/25/2000 | 8/25/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 08/24/2000 at 12:14:28. Contact: ###-####. Final Fail C/N issued 8/25/2000 12:53:21 PM
|
Plan assigned to (JCB) | 8/2/2000 | | 8/17/2000 | | PASS |
Jason Blais
|
|
|
8/17/2000 11:14:47 JCB - activity updated through activity BLDA022 from case BLD00-02186.
|
Routing - PLAN CHECK | 8/16/2000 | | 8/17/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/17/2000 | | DONE |
|
|
|
|
Telephone call | | | 8/17/2000 | | DONE |
|
|
|
Jamie ###-####
|
Print Occupancy Form | | | 8/17/2000 | | DONE |
|
|
|
|
Telephone call | | | 8/17/2000 | | DONE |
|
|
|
Jamie ###-####
|
Issue PAID IN FULL permit | | | 8/17/2000 | | DONE |
|
|
|
|
Routing - FIRE | 8/16/2000 | 8/16/2000 | 8/16/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 8/15/2000 | | 8/16/2000 | | PEND |
|
|
|
Plan and permit approval dependent on Fire Dept. approval. Plans routed to Fire Dept. for second review.
|
Plan resubmittals received | | | 8/15/2000 | | |
|
|
|
rebubmittal 2 sheet a-1 1 brsa memo-1 prime equipments letter- 1 msds sheets 23 sheets.
|
Routing - FIRE | 8/8/2000 | 8/9/2000 | 8/9/2000 | | FAIL |
Bill Alexander
|
|
|
Need to verify Haz Mat classifications and quantities. Floor drain requirements.
|
Plan Review Completed(1st rev) | | | 8/9/2000 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/2/2000 | | 8/8/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept.
|
Plan resubmittals requested | | | 8/8/2000 | | PEND |
|
|
|
Plan resubmittals and response required for further review.
|
Pending Assignment by MYS | 8/2/2000 | | 8/4/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan resubmittals received | | | 8/1/2000 | | DONE |
|
|
|
RECEIVED TWO SETS OF SHEETS A-1 FROM BRS ARCHITECTS. FORWARDED SAME TO MARLENE. 8/1/00 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 7/28/2000 | | DONE |
|
|
|
ADVISED CLINTON YAKA THAT PLANS MUST BE DIMENSIONED, AND INFO ON YEAR AND CODE THAT PLANS ARE TO BE REVIEWED UNDER MUST BE RESUBMITTED. 7/28/00 DAR
|
Application received | | | 7/27/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|