Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-02219
StatusFinaled
Name CHURCH IN BOISE INC THE
Site Address 1301 JUANITA
Project NameTHE CHURCH IN BOISE
Customer Number 
ePlanReviewNo
Description
THE CHURCH IN BOISE * TO CONSTRUCT A 7853 S.F., TWO STORY WITH BASEMENT, TYPE VN WOOD FRAMED CHURCH WITH 19 PARKING STALLS. OTHER WORK INLCUDES ALL SITE IMPROVMENTS , PAVING AND LANDSCAPING PER APPROVED PLANS AND ATTACHMENTS.CUP99-00122 PC#611-00. THE BASEMENT HAS 292 SQ. FT. AND IS USED ONLY FOR MECHANICAL EQUIPMENT - NO STORAGE PERMITTED - THE FIRST FLOOR HAS 4,982 SQ. FT. WITH THE OCCUPANT LOAD OF THE SANCTURARY AT 225 PER PLAN WITH THE SECOND FLOOR HAVING 2580 SQ. FT.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes2/27/20012/27/20019/17/2001 DONE
Fee Review-notes8/1/20008/1/20009/17/2001 DONE
BLD-Final7/20/20017/23/20017/23/2001APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 07/20/2001 at 10:10:10. Contact: ###-####. talk with robert myer with health dept said I could sign for him for perm/ final ok bld. for occ. 7/23/2001 9:21:36 AM
Permanent Occupancy 7/23/20017/23/2001 DONE
Details
Permanent occupancy  7/23/2001 DONE
Perm. Occ. Cert. #8771 issued 7-23-01 to "The Church in Boise."
BLD-Final7/5/20017/6/20017/6/2001AFAIL
DetailsDave Hannah
Scheduled by a contractor via Hello! on 07/05/2001 at 14:13:56. Contact: ###-####. need per occ from dist health fire caulk mec rooms uni sex sign cry room 7/6/2001 11:07:05 AM
FIRE-Final Inspection7/5/20017/5/20017/5/2001PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/05/2001 at 08:00:25. Contact: ###-####.
Code Occupancy Approval  7/5/2001 PASS
Inspected and passed. It was noted that the City of Boise Forester had modified the locations and removal of diseased/dying trees. Of note, is the removal of a tree in the northeast corner of the lot, as it was in the 40' triangle of the corner.
FIRE-Final Inspection7/3/20017/3/20017/3/2001PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 07/03/2001 at 09:26:42. Contact: ###-####. occupant load sign adn bollards for gas meter 7/3/2001 1:48:01 PM
FIRE-Conference6/19/20016/19/20016/19/2001PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/19/2001 at 09:47:13. Contact: ###-####. reviewed exit signage; extinguishers and occupant load signs 6/20/2001 7:55:15 AM
BLD-Framing/Rough-in5/31/20016/1/20016/1/2001APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 05/31/2001 at 11:14:17. Contact: ###-####. suspended ceiling grid ok to cover 6/1/2001 11:24:27 AM
Case Summary (BLD)  5/18/2001 DONE
BLD-Framing/Rough-in4/19/20014/20/20014/20/2001APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 04/19/2001 at 16:08:24. Contact: ###-####. c/n items completed ok to cover 4/20/2001 10:53:47 AM
BLD-Framing/Rough-in4/19/20014/19/20014/19/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 04/19/2001 at 09:07:30. Contact: ###-####.c/n posted 4/23/2001 9:15:27 AM
Plan resubmittals received  4/18/2001 DONE
Received one copy of revised M1.0, M1.1, P1.0 and P1.1. Routed to David Lightfoot. KMM
BLD-Framing/Rough-in4/12/20014/13/20014/13/2001PNR
DetailsSteven Webb
Scheduled by a contractor via Hello! on 04/12/2001 at 16:05:26. Contact: ###-####. Mechanical, electrical and plumbing sign off needed. 4/13/2001 1:48:51 PM
BLD-Framing/Rough-in3/29/20013/30/20013/30/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 03/29/2001 at 13:17:25. Contact: ###-####. erterior sheer ok. 3/30/2001 3:08:16 PM
BLD-Foundation2/22/20012/22/20012/22/2001PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/22/2001 at 10:07:32. Contact: ###-####. wall 2/22/2001 2:49:02 PM
BLD-Footing2/20/20012/20/20012/20/2001PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 02/20/2001 at 08:18:23. Contact: ###-####.
(F) Reprint permit  12/14/2000 DONE
Issue PAID IN FULL permit  12/7/2000 DONE
Print Occupancy Form  11/28/2000 DONE
Inspection Record Card- Bld  11/28/2000 DONE
Telephone call  11/28/2000 DONE
called permit ready fees due and ACHD
Plan assigned to (MLO)8/1/2000 11/27/2000 PASS
DetailsMike Otto
11/27/2000 14:24:28 MLO - activity updated through activity BLDA022 from case BLD00-02219.
Routing - PLUMBING11/22/2000 11/27/2000 PASS
ROUTE TO PLUMBING WHEN RESUBMITTALS RECEIVED THAT INLCLUDE PLUMBING PLANS FOR ROOF DRAINS AND ADDED MOP SINK. MLO
PLANS/APPL TAKEN TO FRONT DESK  11/27/2000 DONE
Plan resubmittals received  11/22/2000 DONE
Received two copies of revised sheets A1.1, A4.2 AND P1.1 dated 11/1/00 . Two copies of revised sheets A1.1, A1.2, A4.2, A7.1 P1.1 dated 11/21/00 ROUTED TO MIKE O. KMM
Routing - PLAN CHECK11/22/2000 11/22/2000 PASS
Routing - FIRE11/16/200011/16/200011/16/2000 PASS
DetailsBill Alexander
Routing - FIRE11/13/200011/14/200011/14/2000 FAIL
DetailsBill Alexander
Lack hydrant flows. 3rd request? plans returned to plan review
Routing Off Site - STRUCTURAL11/8/2000 11/13/2000 PASS
Sent one set of plans to consultanting engineer via PDQ. 11/8/00 DAR
Routing - PLAN CHECK11/8/2000 11/13/2000 FAIL
CORRECTIONS SENT TO ARCHITECT.
Plan resubmittals requested  11/13/2000 FAIL
UBC CORRECTIONS.
Routing - PUBLIC WORKS11/13/2000 11/13/2000 PASS
have added additional fixture (mop sink)
Routing - FIRE11/6/200011/8/200011/8/2000 FAIL
DetailsBill Alexander
Lack Fire Flows on hydrant located. Called and requested submittal
Plan resubmittals received  11/7/2000 DONE
Received plan resubmittals from Design Resources, two sets of sheets A1.1, A3.1, A4.2, A7.1, S2.2, forwarded same to Mike Otto. 1/7/00 DAR
Routing - PLAN CHECK10/30/2000 11/6/2000 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT.
Plan resubmittals requested  11/6/2000 FAIL
UBC CORRECTIONS AND SHORT STRUCTURAL SET FOR REVIEWING ENGINEER. MLO
Plan resubmittals received  10/27/2000 DONE
RECEIVED THW COPIES OF REVISED PLANS AND TWO COPIES OF REVISED CALCULATIONS FROM ROCKY TOWLE. ROUTED TO MIKE O. KMM
Routing - FIRE8/23/20008/28/20008/29/2000 FAIL
DetailsBill Alexander
Routing Off Site - STRUCTURAL8/11/2000 8/29/2000 FAIL
Plan resubmittals requested  8/29/2000 FAIL
STRUCTURAL CORRECTIONS FAXED TO ARCHITECT.
Plan Review Completed(1st rev)  8/29/2000 FAIL
plans returned to plan check
Routing - PLAN CHECK8/15/2000 8/23/2000 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT.
Plan resubmittals requested  8/23/2000 FAIL
UBC CORRECTIONS
Routing - PLUMBING8/14/2000 8/15/2000 FAIL
turn down
Routing - PLANNING8/11/2000 8/14/2000 PASS
Routing - PUBLIC WORKS8/8/2000 8/11/2000 PASS
Plans ACCEPTED BY PLAN TECH  8/11/2000 DONE
Plans ACCEPTED BY PLAN TECH  8/8/2000 PEND
RECEIVED ONE ADDITIONAL SET OF PRINTS FOR OUTSIDE ENG. HOWEVER THEY WERE NOT STAMPED OR SIGNED. CALLED ROCKY OF THIS NEED
RECEIVED TWO ADITIONAL COPIES OF SHEETS M1.0 AND M3.0 ( SHEET M1.0 IS A MODIFIED SHEET). ONE SHEET OF C1.2 ONE VICINITY MAP AND ONE DEED OR LEGAL DESCRIPTION. PUT WITH PLANS.
Plans ACCEPTED BY PLAN TECH  8/2/2000 HOLD
REQUIRES: 1. OUTSIDE ENG. COPY.
2. M3 SHEET NOT SIGNED
3. THREE ADDITIONAL CIVIL SETS. RECEIVED 8/1/00
4. COMPLETE LEGAL DESCRIPTION
5. VICINITY MAP
6. FIRE SPRINKLER, FIRE ALARM AND SMOKE SYSTEMS PART OF DESIGN?
FAXED AND LEFT MESAGES FOR ROCKY. KMM
Received Certificate of Value  8/1/2000 DONE
Application received  8/1/2000  
Recd Pcfee & Taken To Pln CK  8/1/2000 DONE
Routing Off Site - A.C.H.D12/7/200012/7/2000   
received a.c.h.d- # 01-00160 for $2,713/mls
Plan routing begun/NEW & ADDTN     
Routing Off Site - STRUCTURAL