Case Summary (BLD) | | | 6/9/2014 | | DONE |
|
|
|
|
Fee Review-notes | 6/27/2003 | 6/27/2003 | 6/27/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/24/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9204 issued 6-24-02 to the Renaissance @ Liberty Lake Apartments., Bldg. #10, center portion.
|
BLD-Final | 6/13/2002 | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
Final, approved/perm. occ.
|
Temporary occupancy | | | 1/30/2002 | | PART |
|
|
|
Temp. Occ. Cert. #4711 issued 1-30-02 to the Renaissance @ Liberty Lake Apts. center portion of Bldg. #10.
|
BLD-Final | 1/28/2002 | 1/29/2002 | 1/29/2002 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/28/2002 at 13:49:44. Contact: ###-####. ok for temp occ 1/29/2002 4:42:53 PM
|
FIRE-Final Inspection | 1/29/2002 | 1/29/2002 | 1/29/2002 | A | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 1/29/2002 10:19:12 AM Fire alarm, fire life/safety and fire sprinklers finaled
|
BLD-Final | 1/28/2002 | 1/29/2002 | 1/28/2002 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/28/2002 at 10:15:29. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 01/28/2002 at 13:48:43.
|
Code Occupancy Approval Temp | 1/25/2002 | 1/24/2002 | 1/24/2002 | P | FAIL |
Carol Montgomery
|
|
|
Scheduled by Inspector: CAM On 1/25/02 8:37:47 AM Bond is in place - signed temporary 1/25/02 8:40:54 AM
|
Case Summary (BLD) | | | 1/16/2002 | | |
|
|
|
|
BLD-Wall cover | 11/28/2001 | 11/28/2001 | 11/28/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/28/2001 at 08:35:51. Contact: ###-####. oc to cover north 4 units 11/28/2001 3:30:24 PM
|
BLD-Wall cover | 11/23/2001 | 11/27/2001 | 11/27/2001 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/23/2001 at 14:49:21. Contact: ###-####.
|
BLD-Wall cover | 11/19/2001 | 11/21/2001 | 11/20/2001 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/19/2001 at 08:11:03. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/20/2001 at 08:05:36.
|
BLD-Wall cover | 11/20/2001 | 11/20/2001 | 11/20/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 08:03:05. Contact: ###-####. ok to cover center 12 11/20/2001 4:11:30 PM
|
BLD-Framing/Rough-in | 11/15/2001 | 11/16/2001 | 11/15/2001 | A | CANC |
Tom Arcoraci
|
|
|
###-#### Disp set to [CANC] by a contractor via Hello! on 11/15/2001 at 16:08:13.
|
BLD-Wall cover | 11/13/2001 | 11/14/2001 | 11/14/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/13/2001 at 09:54:34. Contact: ###-####. ok to cover south 4 of bld 10 11/14/2001 3:18:10 PM
|
BLD-Wall cover | 11/8/2001 | 11/9/2001 | 11/9/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 10:45:27. Contact: ###-####.
|
BLD-Wall cover | 11/9/2001 | 11/9/2001 | 11/9/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 11/9/2001 10:32:53 AM ok to inul and build drops in north 4 units 11/9/2001 2:49:44 PM
|
BLD-Wall cover | 11/7/2001 | 11/9/2001 | 11/8/2001 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/07/2001 at 14:08:23. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/08/2001 at 10:47:34.
|
BLD-Wall cover | 11/8/2001 | 11/8/2001 | 11/8/2001 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 09:38:09. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/08/2001 at 10:46:28.
|
BLD-Wall cover | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/06/2001 at 12:52:13. Contact: ###-####.
|
BLD-Wall cover | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/06/2001 at 12:52:13. Contact: ###-####.
|
BLD-Wall cover | 11/2/2001 | 11/5/2001 | 11/5/2001 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/02/2001 at 12:06:40. Contact: ###-####. south 4 ok for drops 11/5/2001 4:41:57 PM
|
BLD-Wall cover | 10/30/2001 | 10/31/2001 | 10/31/2001 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/30/2001 at 12:18:08. Contact: ###-####.
|
BLD-Aging Inspection | 10/8/2001 | 10/8/2001 | 10/8/2001 | | PART |
Tom Arcoraci
|
|
|
wip 10/8/2001 11:20:49 AM
|
BLD-Aging Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Footing | 6/4/2001 | 6/4/2001 | 6/4/2001 | P | PART |
Tom Arcoraci
|
|
|
Jeff ###-#### wip 6/4/2001 2:49:59 PM
|
BLD-Foundation | 5/8/2001 | 5/9/2001 | 5/9/2001 | A | PASS |
Tom Arcoraci
|
|
|
larry ###-#### bldg #10
|
BLD-Footing | 5/1/2001 | 5/2/2001 | 5/2/2001 | A | PASS |
Russ Owen
|
|
|
Larry ###-####
|
Issue PAID IN FULL permit | | | 3/15/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/7/2001 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/3/2000 | | 3/6/2001 | | PASS |
Carl Westfall
|
|
|
3/6/01 13:21:12 CJW - activity updated through activity BLDA022 from case BLD00-02263.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 2/27/2001 | 2/27/2001 | 2/27/2001 | | PASS |
|
|
|
Approved per CUP99-127 Dave Abo and per DRH99-258 Marty S.
|
Plan Reviewer's activity | | | 2/24/2001 | | PASS |
|
|
|
See BLD00-02268 for more information.
|
Routing - FIRE | 2/14/2001 | 2/21/2001 | 2/21/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 10/18/2000 | 10/24/2000 | 10/24/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 10/24/2000 | | |
|
|
|
Failed first UBC plan review.
|
Routing - PLAN CHECK | 9/1/2000 | | 10/18/2000 | | |
|
|
|
Failed first UBC plan review. Drawings not routed until all plan reviews were done.
|
Plan Reviewer's activity | | | 10/11/2000 | | |
|
|
|
Failed first UBC plan review. UBC plan review started October 11, 2000 and finished the next day. A response from the architect was required. See the conditions list under BLD00-02260.
|
Routing - PLANNING | 8/30/2000 | | 8/31/2000 | | PASS |
|
|
|
See approval in DRH00-258
|
Routing - PLUMBING | 8/28/2000 | | 8/30/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/24/2000 | | 8/28/2000 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/24/2000 | | DONE |
|
|
|
PLAN REVIEW MONEY RECEIVED. STARTED ROUTING PLANS.
|
Application received | | | 8/3/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 2/27/2001 | | | | |
|
|
|
|