Case Summary (BLD) | | | 6/9/2014 | | DONE |
|
|
|
|
Fee Review-notes | 6/27/2003 | 6/27/2003 | 6/27/2003 | | DONE |
|
|
|
|
BLD-Conference | 6/21/2002 | 6/21/2002 | 6/21/2002 | | DONE |
|
|
|
C/N for exit sign and electrical needs to be approved
|
Permanent occupancy | | | 6/21/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9193 issued 6-21-02 to the Renaissance @ Liberty Lake Apts., Bldg. #6, center portion.
|
BLD-Final | 6/13/2002 | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
Final - approved for perm. occ.
|
Permanent Occupancy | | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
|
BLD-Aging Inspection | 1/21/2002 | 1/21/2002 | 1/21/2002 | | PART |
Tom Arcoraci
|
|
|
|
Case Summary (BLD) | | | 1/16/2002 | | |
|
|
|
|
BLD-Final | 11/16/2001 | 11/19/2001 | 11/19/2001 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 11/16/2001 at 13:10:10. Contact: ###-####. OK for Temp Occ. 11/19/2001 12:30:01 PM
|
Temporary occupancy | | | 11/19/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4651 issued 11-19-01 to the Renaissance at Liberty Lake Apts. Bldg. #6, center portion.
|
FIRE-Final Inspection | 11/15/2001 | 11/16/2001 | 11/16/2001 | A | PASS |
Troy Cobbley
|
|
|
Address sign installed. OK for perm occ 11/16/2001 2:09:09 PM
|
FIRE-Alarm Testing | 11/13/2001 | 11/14/2001 | 11/14/2001 | A | FAIL |
Troy Cobbley
|
|
|
Contractor to install building address 11/14/2001 9:38:23 AM
|
BLD-Wall cover | 10/3/2001 | 10/4/2001 | 10/4/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 10/03/2001 at 09:25:20. Contact: ###-####.ok to rock. 10/4/2001 4:33:40 PM
|
BLD-Wall cover | 10/1/2001 | 10/2/2001 | 10/2/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/01/2001 at 11:29:32. Contact: ###-####. ok to cover 6 10/2/2001 3:12:50 PM
|
BLD-Wall cover | 9/28/2001 | 10/2/2001 | 10/1/2001 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/28/2001 at 16:16:21. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/01/2001 at 11:31:37.
|
BLD-Wall cover | 9/21/2001 | 9/24/2001 | 9/24/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/21/2001 at 13:41:02. Contact: ###-####. ok to set tub 9/24/2001 3:32:55 PM
|
BLD-Wall cover | 9/19/2001 | 9/20/2001 | 9/20/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/19/2001 at 15:55:47. Contact: ###-####. ok to insul 9/20/2001 3:17:39 PM
|
BLD-Wall cover | 9/17/2001 | 9/18/2001 | 9/18/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/17/2001 at 11:46:07. Contact: ###-####. ok to insul center 9/18/2001 3:20:39 AM
|
BLD-Wall cover | 9/14/2001 | 9/17/2001 | 9/17/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/14/2001 at 16:21:11. Contact: ###-####. ok to insul south side of bld 6 9/16/2001 10:49:17 PM
|
BLD-Wall cover | 9/14/2001 | 9/14/2001 | 9/14/2001 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/14/2001 at 07:31:00. Contact: ###-####.
|
BLD-Wall cover | 9/12/2001 | 9/13/2001 | 9/13/2001 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 09/12/2001 at 13:29:06. Contact: ###-####.
|
BLD-Other | 9/4/2001 | 9/5/2001 | 9/5/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/04/2001 at 15:05:15. Contact: 94197488. ok to cover tub area 9/5/2001 3:06:04 AM
|
BLD-Aging Inspection | 7/23/2001 | 7/23/2001 | 7/23/2001 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Footing | 5/18/2001 | 5/21/2001 | 5/21/2001 | P | PASS |
Tom Arcoraci
|
|
|
jeff ###-#### interior ft
|
BLD-Footing | 4/19/2001 | 4/20/2001 | 4/20/2001 | A | PASS |
Tom Arcoraci
|
|
|
###-####
|
BLD-Foundation | 4/19/2001 | 4/20/2001 | 4/20/2001 | A | PASS |
Tom Arcoraci
|
|
|
Larry ###-####
|
BLD-Footing | 4/19/2001 | 4/19/2001 | 4/19/2001 | P | PART |
Russ Owen
|
|
|
###-####
|
BLD-Foundation | 4/18/2001 | 4/18/2001 | 4/18/2001 | P | PASS |
Tom Arcoraci
|
|
|
###-####
|
BLD-Footing | 4/12/2001 | 4/16/2001 | 4/16/2001 | A | PASS |
Tom Arcoraci
|
|
|
###-#### larry
|
Issue PAID IN FULL permit | | | 3/15/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/7/2001 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/3/2000 | | 3/6/2001 | | PASS |
Carl Westfall
|
|
|
3/6/01 13:24:26 CJW - activity updated through activity BLDA022 from case BLD00-02274.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 2/27/2001 | 2/27/2001 | 2/27/2001 | | PASS |
|
|
|
Approved per CUP99-127 Dave Abo and per DRH99-258 Marty S.
|
Routing - FIRE | 2/14/2001 | 2/20/2001 | 2/20/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 10/18/2000 | 10/23/2000 | 10/24/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 10/24/2000 | | |
|
|
|
Failed first UBC plan review.
|
Routing - PLAN CHECK | 9/1/2000 | | 10/18/2000 | | |
|
|
|
Failed first UBC review. Drawings not routed until all plan reviews were done.
|
Plan Reviewer's activity | | | 9/27/2000 | | |
|
|
|
Failed first UBC plan review. UBC plan review started September 27, 2000 and finished October 3, 2000. See the conditions list under BLD00-02268. A response from the architect was required.
|
Routing - PLANNING | 8/30/2000 | | 8/31/2000 | | PASS |
|
|
|
See approval in DRH00-258
|
Routing - PLUMBING | 8/28/2000 | | 8/30/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/24/2000 | | 8/28/2000 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/24/2000 | | DONE |
|
|
|
PLAN REVIEW MONEY RECEIVED. STARTED ROUTING PLANS.
|
Application received | | | 8/3/2000 | | |
|
|
|
|
Plan Reviewer's activity | | | | | PASS |
|
|
|
See BLD00-02268 for additional information.
|
Routing - PLAN CHECK | 2/27/2001 | | | | |
|
|
|
|