Case Summary (BLD) | | | 6/9/2014 | | DONE |
|
|
|
|
Fee Review-notes | 6/27/2003 | 6/27/2003 | 6/27/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/24/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9206 issued 6-24-02 to the Renaissance @ Liberty Lake Apts., Bldg. #11, center portion.
|
Permanent Occupancy | | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
|
BLD-Final | 6/13/2002 | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
Final - approved/perm. occ.
|
Temporary occupancy | | | 2/15/2002 | | DONE |
|
|
|
Temp Occ. #4726 issued 2-15-02 to the Renaissance @ Liberty Lake Apts., Bldg. #11, center portion.
|
BLD-Final | 2/12/2002 | 2/12/2002 | 2/12/2002 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 02/12/2002 at 09:39:56. Contact: ###-####. ok for temp 2/12/2002 5:11:50 PM
|
FIRE-Final Inspection | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 2/8/2002 2:10:32 PM Fire life/safety finaled
|
Case Summary (BLD) | | | 1/16/2002 | | |
|
|
|
|
BLD-Wall cover | 12/10/2001 | 12/11/2001 | 12/11/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/10/2001 at 09:21:18. Contact: ###-####. wip 12/11/2001 12:57:22 PM
|
BLD-Wall cover | 12/11/2001 | 12/11/2001 | 12/11/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 12/11/2001 9:47:08 AM ok to cover need repair on 2 hr wall east 4 units 12/11/2001 2:32:22 PM
|
BLD-Wall cover | 12/5/2001 | 12/6/2001 | 12/6/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/05/2001 at 17:23:48. Contact: ###-####. ok to rock 12/6/2001 12:27:03 PM
|
BLD-Wall cover | 12/6/2001 | 12/6/2001 | 12/6/2001 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 12/6/2001 10:29:18 AM
|
BLD-Wall cover | 12/3/2001 | 12/5/2001 | 12/5/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/03/2001 at 11:54:44. Contact: ###-####. wip 12/5/2001 10:08:40 AM
|
BLD-Wall cover | 12/5/2001 | 12/5/2001 | 12/5/2001 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 12/5/2001 10:08:21 AM wip 12/5/2001 3:10:38 PM
|
BLD-Wall cover | 12/3/2001 | 12/5/2001 | 12/3/2001 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/03/2001 at 10:01:00. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 12/03/2001 at 11:56:17.
|
BLD-Wall cover | 11/30/2001 | 11/30/2001 | 11/30/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/30/2001 at 08:49:02. Contact: ###-####. ok to cover west 4 units 11/30/2001 2:48:39 PM
|
BLD-Wall cover | 11/20/2001 | 11/21/2001 | 11/21/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/20/2001 at 14:57:04. Contact: ###-#### 11/20/2001 4:11:10 PM east 4 units of 11 ok for insul and drops 11/21/2001 11:26:06 AM
|
BLD-Wall cover | 11/19/2001 | 11/20/2001 | 11/20/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/19/2001 at 10:58:58. Contact: ###-####. ok to insul an buid drops in center 12 units 11/20/2001 10:10:59 AM
|
BLD-Wall cover | 11/15/2001 | 11/16/2001 | 11/16/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/15/2001 at 13:32:30. Contact: ###-####. ok to insul and install drops in west 4 units 11/16/2001 10:53:03 AM
|
BLD-Wall cover | 11/14/2001 | 11/16/2001 | 11/15/2001 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/14/2001 at 15:37:26. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/15/2001 at 13:33:55.
|
BLD-Wall cover | 11/8/2001 | 11/9/2001 | 11/9/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 11:04:14. Contact: ###-####. ok to set tubs 11/9/2001 2:48:09 PM
|
BLD-Aging Inspection | 10/15/2001 | 10/15/2001 | 10/15/2001 | | PASS |
Tom Arcoraci
|
|
|
wip 10/15/2001 8:41:12 AM
|
BLD-Aging Inspection | 8/13/2001 | 8/13/2001 | 8/13/2001 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Footing | 6/12/2001 | 6/13/2001 | 6/13/2001 | P | PASS |
Tom Arcoraci
|
|
|
Jeff Burns ###-####
|
BLD-Footing | 5/3/2001 | 5/4/2001 | 5/4/2001 | P | PASS |
Tom Arcoraci
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 3/15/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/7/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2001 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/3/2000 | | 3/6/2001 | | PASS |
Carl Westfall
|
|
|
3/6/01 13:29:05 CJW - activity updated through activity BLDA022 from case BLD00-02283.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 2/27/2001 | 2/27/2001 | 2/27/2001 | | PASS |
|
|
|
Approved per CUP99-127 Dave Abo and per DRH99-258 Marty S.
|
Plan Reviewer's activity | | | 2/24/2001 | | PASS |
|
|
|
See BLD00-02268 for more information.
|
Routing - FIRE | 2/14/2001 | 2/20/2001 | 2/20/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 10/18/2000 | 10/23/2000 | 10/24/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 10/24/2000 | | |
|
|
|
Failed first UBC plan review.
|
Routing - PLAN CHECK | 9/1/2000 | | 10/18/2000 | | |
|
|
|
Failed first UBC plan review. Drawings not routed until all plan reviews were done.
|
Plan Reviewer's activity | | | 9/27/2000 | | |
|
|
|
Failed first UBC plan review. UBC plan review started September 27, 2000 and finished October 3, 2000. See the conditions list under BLD00-02268. A response from the architect was required.
|
Routing - PLANNING | | | 8/31/2000 | | PASS |
|
|
|
See approval in DRH00-258
|
Routing - PLUMBING | 8/28/2000 | | 8/30/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/24/2000 | | 8/28/2000 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/24/2000 | | DONE |
|
|
|
RECEIVED PLAN REVIEW MONEY. STARTED ROUTING PLANS.
|
Application received | | | 8/3/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 2/27/2001 | | | | |
|
|
|
|