Permit Information
Permit NumberBLD00-02288
StatusFinaled
Name (BLD 14) (II) RENAISSANCE @ LIBERTY
Site Address 1303 N LIBERTY ST Unit: (CENTER PORTION)
Project NameRENAISSANCE @ LIBERTY
Customer Number 
ePlanReviewNo
Description
(RENAISSANCE AT LIBERTY LAKE - BUILDING 14 - Type II - CENTER PORTION) The entire building shall be of Type V-1hr construction for fire flow (2,500 gpm required). The 3 story center portion shall be fire sprinklered because it is 3 stories tall. To construct the center portion of a 3 story, 20 unit, 19,328 square foot (8,886 square feet projected roof area) apartment building. All ground floor units shall comply as "Type B" dwelling units. Work is to include concrete footings, foundations, and slabs on grade; wood stud wall systems; wood joist floor systems; wood truss roof systems; 1-hr corridors; exterior stairways; 2-hr area separation walls; vinyl siding; a fire alarm system; and composition shingles all per approved drawings, engineering, and plan review conditions on file (see BLD00-02268 for the conditions list). The fire sprinkler system within the 3 story center portion shall comply with NFPA 13R-1996 as regulated by the Fire Department. See BLD00-02286 for the EAST PORTION and BLD00-02287 for the WEST PORTION. DR99-00258 CUP99-00127 **CJW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  6/9/2014 DONE
Fee Review-notes6/27/20036/27/20036/27/2003 DONE
Permanent occupancy  6/25/2002 DONE
Perm. Occ. Cert. #9217 issued 6-25-02 to the Renaissance @ Liberty Lake Apts., Bldg. #14, center portion.
Permanent Occupancy 6/13/20026/13/2002 DONE
Details
BLD-Final6/13/20026/13/20026/13/2002 DONE
Final - approved/perm. occ.
BLD-Final3/26/20023/27/20023/27/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 03/26/2002 at 08:28:25. Contact: ###-####. ok for temp occ 3/27/2002 3:02:52 PM
FIRE-Conference3/26/20023/27/20023/27/2002APASS
DetailsTroy Cobbley
fire life/safety, fire alarm and fire sprinkler finaled 3/27/2002 9:55:23 AM
Temporary occupancy  3/27/2002 DONE
Temp. Occ. Cert. #4765 issued 3-27-02 to the Renaissance at Liberty Lake Apts., Bldg. #14, center portion.
FIRE-Final Inspection3/15/20023/18/20023/18/2002PPASS
DetailsTroy Cobbley
Life safety finaled. Fire alarm needs temporal pattern verified. 3/18/2002 3:04:04 PM
BLD-Wall cover1/23/20021/24/20021/24/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/23/2002 at 11:10:32. Contact: ###-####. ok to cover 1/24/2002 4:32:56 PM
BLD-Wall cover1/21/20021/22/20021/22/2002APASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 01/21/2002 at 16:10:39. Contact: ###-####.
BLD-Wall cover1/17/20021/18/20021/18/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/17/2002 at 15:53:38. Contact: ###-####. drops ok 2 and 3 floors 1/18/2002 4:33:46 PM
Case Summary (BLD)  1/16/2002  
BLD-Wall cover1/11/20021/15/20021/15/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/11/2002 at 09:29:53. Contact: ###-####. drop ceilings for cover east 4 units of bld 14 1/15/2002 10:42:13 AM
BLD-Wall cover1/8/20021/9/20021/9/2002PPASS
DetailsTom Arcoraci
Scheduled by Inspector: 408 On 1/8/2002 4:59:12 PM ok for drops and insul needs truss clips at east side 1/9/2002 12:12:13 PM
BLD-Wall cover1/7/20021/9/20021/9/2002APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/07/2002 at 14:02:37. Contact: ###-####. wip 1/9/2002 8:06:11 AM
BLD-Wall cover1/8/20021/8/20021/8/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/08/2002 at 07:42:25. Contact: ###-####.
BLD-Wall cover1/4/20021/7/20021/7/2002ANR
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/04/2002 at 10:37:14. Contact: ###-####.
BLD-Wall cover1/3/20021/4/20021/4/2002APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/03/2002 at 16:57:42. Contact: ###-####. center 12 ok for drops and insul 1/4/2002 10:19:41 AM
BLD-Wall cover1/3/20021/4/20021/3/2002PCANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/03/2002 at 16:48:34. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 01/03/2002 at 16:58:49.
BLD-Wall cover1/3/20021/3/20021/3/2002PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/03/2002 at 08:08:14. Contact: ###-####. 4 west units in 14 ok 1/3/2002 4:14:26 PM
BLD-Wall cover12/27/200112/27/200112/27/2001PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/27/2001 at 08:03:55. Contact: ###-####. ok to set tubs 12/27/2001 4:59:26 PM
BLD-Aging Inspection11/28/200111/28/200111/28/2001 PART
DetailsTom Arcoraci
BLD-Aging Inspection9/24/20019/24/20019/24/2001 PART
DetailsTom Arcoraci
BLD-Footing7/24/20017/25/20017/25/2001PPASS
DetailsTom Arcoraci
interior footings jeff ###-####
BLD-Foundation6/5/20016/6/20016/6/2001APASS
DetailsTom Arcoraci
late am please larry ###-####
BLD-Footing5/29/20015/30/20015/30/2001APASS
DetailsDave Hannah
late am pump set up at 12:00 Larry ###-####
Issue PAID IN FULL permit  3/15/2001 DONE
Print Occupancy Form  3/7/2001 DONE
Inspection Record Card- Bld  3/7/2001 DONE
Plan assigned to (CJW)8/3/2000 3/6/2001 PASS
DetailsCarl Westfall
3/6/01 13:31:52 CJW - activity updated through activity BLDA022 from case BLD00-02288.
PLANS/APPL TAKEN TO FRONT DESK  3/6/2001 PASS
Routing - PLANNING2/27/20012/27/20012/27/2001 PASS
Approved per CUP99-127 Dave Abo and per DRH99-258 Marty S.
Plan Reviewer's activity  2/24/2001 PASS
See BLD00-02268 for additional information.
Routing - FIRE2/14/20012/20/20012/20/2001 PASS
DetailsBill Alexander
Routing - FIRE10/18/200010/23/200010/24/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  10/24/2000  
Failed first UBC plan review.
Routing - PLAN CHECK9/1/2000 10/18/2000  
Failed first UBC plan review. Drawings not routed until all plan reviews were done.
Plan Reviewer's activity  9/27/2000  
Failed first UBC plan review. UBC plan review started September 27, 2000 and finished October 3, 2000. See the conditions list under BLD00-02268. A response from the architect was required.
Routing - PLANNING8/30/2000 8/31/2000 PASS
See approval in DRH00-258
Routing - PLUMBING8/28/2000 8/30/2000 PASS
Routing - PUBLIC WORKS8/24/2000 8/28/2000 PASS
Plan routing begun/NEW & ADDTN  8/24/2000 DONE
RECEIVED PLAN REVIEW MONEY. STARTED ROUTING PLANS.
Application received  8/3/2000  
Routing - PLAN CHECK2/27/2001