Case Summary (BLD) | | | 6/9/2014 | | DONE |
|
|
|
|
Fee Review-notes | 6/27/2003 | 6/27/2003 | 6/27/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/24/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9202 issued 6-24-02 to the Renaissance @ Liberty Lake Apts., Bldg. #9, east portion.
|
Permanent Occupancy | | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
|
BLD-Final | 6/13/2002 | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
Final - appprove/perm. occ.
|
BLD-Final | 1/16/2002 | 1/17/2002 | 1/17/2002 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 01/16/2002 at 12:06:42. Contact: ###-####. ok for temp 1/17/2002 11:53:25 AM
|
BLD-Final | 1/17/2002 | 1/17/2002 | 1/17/2002 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 1/17/2002 9:50:40 AM ok for temp 1/17/2002 11:57:25 AM
|
Temporary occupancy | | | 1/17/2002 | | PART |
|
|
|
Temp. Occ. Cert. #4703 issued 1-17-02 to the east side of Bldg. 9 of the Renaissance @ Liberty Lake apts.
|
FIRE-Final Inspection | 1/15/2002 | 1/15/2002 | 1/15/2002 | P | PASS |
Troy Cobbley
|
|
|
Fire life/safety passed 1/15/2002 2:54:53 PM
|
BLD-Aging Inspection | 1/14/2002 | 1/14/2002 | 1/14/2002 | | PART |
Tom Arcoraci
|
|
|
|
Print Occupancy Form | | | 12/5/2001 | | DONE |
|
|
|
|
BLD-Wall cover | 11/12/2001 | 11/13/2001 | 11/13/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/12/2001 at 07:59:33. Contact: (208) ok to cover bld 9 east 12
11/13/2001 2:00:49 PM
|
BLD-Wall cover | 11/8/2001 | 11/13/2001 | 11/12/2001 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/08/2001 at 10:52:52. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 11/12/2001 at 08:00:46.
|
BLD-Wall cover | 11/6/2001 | 11/7/2001 | 11/7/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 11/6/2001 3:04:57 PM ok to cover drops 11/7/2001 9:28:15 AM
|
BLD-Wall cover | 11/6/2001 | 11/7/2001 | 11/7/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/06/2001 at 16:24:06. Contact: ###-####. ok to insul bld 10 center 11/7/2001 4:58:51 PM
|
BLD-Wall cover | 11/2/2001 | 11/6/2001 | 11/6/2001 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 11/02/2001 at 12:08:46. Contact: ###-####.
|
BLD-Wall cover | 10/30/2001 | 10/31/2001 | 10/31/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/30/2001 at 12:05:09. Contact: ###-####. ok to cover repair 2 hr wall laps 10/31/2001 10:47:01 AM
|
BLD-Wall cover | 10/29/2001 | 10/31/2001 | 10/30/2001 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/29/2001 at 09:35:05. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/30/2001 at 12:03:57.
|
BLD-Wall cover | 10/30/2001 | 10/30/2001 | 10/30/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/30/2001 at 10:36:23. Contact: ###-####.
|
BLD-Wall cover | 10/25/2001 | 10/25/2001 | 10/25/2001 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/25/2001 at 09:16:36. Contact: ###-####. ok to cover west side with drops lower floor 2hr wall at tubs not ok 10/25/2001 3:07:55 PM
|
BLD-Wall cover | 10/18/2001 | 10/19/2001 | 10/19/2001 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/18/2001 at 09:11:41. Contact: ###-####.
|
BLD-Wall cover | 10/19/2001 | 10/19/2001 | 10/19/2001 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 10/19/2001 10:24:50 AM tubs ok to set except lower four center bld 9 10/19/2001 3:19:25 PM
|
BLD-Aging Inspection | 10/8/2001 | 10/8/2001 | 10/8/2001 | | PART |
Tom Arcoraci
|
|
|
wip 10/8/2001 11:20:31 AM
|
BLD-Aging Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Footing | 5/29/2001 | 5/30/2001 | 5/30/2001 | A | PASS |
Russ Owen
|
|
|
###-####
|
BLD-Foundation | 5/2/2001 | 5/4/2001 | 5/4/2001 | P | PASS |
Tom Arcoraci
|
|
|
###-####
|
BLD-Footing | 4/27/2001 | 4/30/2001 | 4/30/2001 | A | PASS |
Tom Arcoraci
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 3/15/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2001 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/3/2000 | | 3/6/2001 | | PASS |
Carl Westfall
|
|
|
3/6/01 13:38:26 CJW - activity updated through activity BLDA022 from case BLD00-02302.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2001 | | PASS |
|
|
|
|
Routing - PLANNING | 2/27/2001 | 2/27/2001 | 2/27/2001 | | PASS |
|
|
|
Approved per CUP99-127 Dave Abo and per DRH99-258 Marty S.
|
Plan Reviewer's activity | | | 2/24/2001 | | PASS |
|
|
|
See BLD00-02268 for more information.
|
Routing - FIRE | 2/14/2001 | 2/20/2001 | 2/20/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 10/18/2000 | 10/23/2000 | 10/24/2000 | | DONE |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 10/24/2000 | | |
|
|
|
Failed first UBC plan review.
|
Routing - PLAN CHECK | 9/1/2000 | | 10/18/2000 | | |
|
|
|
Failed first UBC plan review. Drawings were not routed until all plan reviews were done.
|
Plan Reviewer's activity | | | 10/6/2000 | | |
|
|
|
Failed first UBC plan review. UBC plan review started October 6, 2000 and finished October 10, 2000. A response from the architect was required. See the conditions list under permit BLD00-02300.
|
Routing - PLANNING | 8/30/2000 | | 8/31/2000 | | PASS |
|
|
|
See approval in DRH00-258
|
Routing - PLUMBING | 8/28/2000 | | 8/30/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/24/2000 | | 8/28/2000 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/24/2000 | | DONE |
|
|
|
RECEIVED PLAN REVIEW MONEY. STARTED ROUTING PLANS.
|
Application received | | | 8/3/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 2/27/2001 | | | | |
|
|
|
|