Permanent occupancy | | | 6/27/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8736 issued 6-27-01 to the China Grand Buffet.
|
BLD-Final | 6/25/2001 | 6/26/2001 | 6/26/2001 | A | PASS |
Dave Hannah
|
|
|
Cathy has the card
|
Permanent Occupancy | | 6/26/2001 | 6/26/2001 | | DONE |
|
|
|
|
Fee Review-notes | 8/4/2000 | 8/4/2000 | 5/9/2001 | | DONE |
|
|
|
this needs final cert. there were changes to review and no additional values....will need to find out who the GC is
|
FIRE-Final Inspection | 4/26/2001 | 4/27/2001 | 4/27/2001 | A | FAIL |
Joe Tawney
|
|
|
4/27/2001 12:06:37 PM REinsp Fail test duct detectors 4/27/2001 12:07:06 PM
|
BLD-Final | 4/27/2001 | 4/27/2001 | 4/27/2001 | P | PART |
Dave Hannah
|
|
|
Added by Inspector: 425 On 4/27/2001 3:51:12 PM
|
FIRE-Final Inspection | 4/27/2001 | 4/27/2001 | 4/27/2001 | P | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 4/27/2001 3:13:00 PM
|
Temporary occupancy | | | 4/27/2001 | | PART |
|
|
|
Temp. Occ. cert. #4541 issued 4-27-01 to the China Grand Buffet.
|
BLD-Framing/Rough-in | 4/12/2001 | 4/13/2001 | 4/13/2001 | A | PASS |
Dave Hannah
|
|
|
Gene ###-#### ###-#### suspended ceiling and lights 4/13/2001 9:55:13 AM
|
FIRE-Final Inspection | 4/9/2001 | 4/10/2001 | 4/10/2001 | P | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail C/N issued 4/11/2001 8:20:44 AM
|
Print Occupancy Form | | | 4/5/2001 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 3/16/2001 | 3/19/2001 | 3/19/2001 | A | PART |
Russ Owen
|
|
|
Gene Brown ###-####added support wires to lighting fixtures. 3/19/2001 10:18:53 AM
|
Override - Parcel Holds | | | 3/16/2001 | | |
|
|
|
|
BLD-Foundation | 3/7/2001 | 3/8/2001 | 3/8/2001 | A | PASS |
Dave Hannah
|
|
|
Gene Brown ###-#### or ###-#### engineering on openning in east wall crew installed all bracing ok to cover 3/8/2001 9:40:50 AM
|
Override - Parcel Holds | | | 3/7/2001 | | |
|
|
|
|
BLD-Framing/Rough-in | 3/1/2001 | 3/2/2001 | 3/2/2001 | A | PART |
Russ Owen
|
|
|
Gene Brown ###-#### or ###-#### please call before going out. needs wires at lights. 3/2/2001 11:38:06 AM
|
Print Occupancy Form | | | 3/1/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 3/1/2001 | | |
|
|
|
|
Override - Parcel Holds | | | 3/1/2001 | | |
|
|
|
|
Plan assigned to (R_H) | 2/9/2001 | | 2/28/2001 | | PASS |
|
|
|
2/28/2001 08:33:42 RMH - activity updated through activity BLDA022 from case BLD00-02320.
|
Case Summary (BLD) | | | 2/28/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2001 | | PASS |
Ron Hill
|
|
|
|
BLD-Framing/Rough-in | 2/23/2001 | 2/26/2001 | 2/26/2001 | A | FAIL |
Dave Hannah
|
|
|
###-#### or ###-#### drop ceiling needs wires on lights and struts 2/26/2001 12:09:29 PM
|
Override - Parcel Holds | | | 2/23/2001 | | |
|
|
|
|
Routing - FIRE | 2/20/2001 | | 2/23/2001 | | PASS |
|
|
|
modified plans approved as noted
|
Case Summary (BLD) | | | 2/20/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 2/20/2001 | | FAIL |
Ron Hill
|
|
|
Faxed and mailed requirements to Barbra Beiers, on 2-20-01 at 8:00 am
|
Routing - PLUMBING | 2/9/2001 | | 2/13/2001 | | PASS |
|
|
|
Second Plan Modification. KMM add 2 hand siks required by cdhd
|
Plans ACCEPTED BY PLAN TECH | | | 2/9/2001 | | DONE |
|
|
|
Second Plan Modification.
|
Received Certificate of Value | | | 2/9/2001 | | DONE |
|
|
|
Second Plan Modification. KMM
|
Plan routing begun/TENANTS | | | 2/9/2001 | | DONE |
|
|
|
Second Plan Modification. KMM
|
Routing - PUBLIC WORKS | 2/9/2001 | | 2/9/2001 | | PASS |
|
|
|
Second Plan Modification. KMM
|
CHANGE STATUS TO (PND) | | | 2/9/2001 | | DONE |
|
|
|
changed to Pending as per KMM-2nd plan modification mps
|
Plan resubmittals received | | | 2/6/2001 | | DONE |
|
|
|
Received two copies of revised sheetsM1.1, M2.0, M3.0. ROUTED TO DIXIE FELLOWS. KMM
|
CHANGE STATUS TO (ISS) | | | 1/22/2001 | | DONE |
|
|
|
|
Receive PAYMENT IN FULL PRINT | | | 1/9/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/1/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/30/2000 | | PASS |
Ron Hill
|
|
|
PLAN MODIFICATIONS READY TO ISSUE
|
Routing - PLAN CHECK | 11/29/2000 | | 11/30/2000 | | PASS |
Ron Hill
|
|
|
Plan Modification
|
Plan assigned to (R_H) | 11/24/2000 | | 11/30/2000 | | PASS |
|
|
|
11/30/2000 13:57:44 RMH - activity updated through activity BLDA022 from case BLD00-02320.
|
Routing - PUBLIC WORKS | 11/27/2000 | | 11/29/2000 | | PASS |
|
|
|
Plan Modification
|
Routing - PLANNING | 11/29/2000 | | 11/29/2000 | | PASS |
|
|
|
Plan Modification
|
Routing Off Site - C.D.H | 11/24/2000 | | 11/27/2000 | | PASS |
|
|
|
Plan Modification
|
Plans ACCEPTED BY PLAN TECH | | | 11/24/2000 | | DONE |
|
|
|
Plan Modification
|
Telephone call | | | 11/24/2000 | | DONE |
|
|
|
Telephoned Barbbara Beier and advised her that the Plan Modification had to go to Central District Health for approval. 11/14/00 DAR
|
CHANGE STATUS TO (PND) | | | 11/22/2000 | | DONE |
|
|
|
resubmittal
|
Print Occupancy Form | | | 10/26/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/26/2000 | | DONE |
|
|
|
|
Telephone call | | | 10/26/2000 | | DONE |
|
|
|
called permit ready
|
Issue PAID IN FULL permit | | | 10/26/2000 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 10/26/2000 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/25/2000 | | PASS |
Ron Hill
|
|
|
|
Plan assigned to (R_H) | 8/14/2000 | | 10/25/2000 | | PASS |
|
|
|
10/25/2000 16:20:15 RMH - activity updated through activity BLDA022 from case BLD00-02320.
|
Routing - PLAN CHECK | 9/20/2000 | | 10/25/2000 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/13/2000 | | 10/16/2000 | | PASS |
|
|
|
Routed resubmitted plumbing plans to Plumbing dept.
|
Plan resubmittals received | | | 10/16/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF SHEETS 5 0F 6 AND 6 0F 6. ONE COPY OF REVISED SHEET PL.1 ROUTED TO RON HILL. KMM
|
Routing - FIRE | 9/14/2000 | 9/19/2000 | 9/20/2000 | | DONE |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 9/20/2000 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 9/14/2000 | | FAIL |
Ron Hill
|
|
|
Address or Fax number for the architect was not provided. Emailed requirements to the architect. Will route to fire department for review
|
Routing - PLAN CHECK | 8/21/2000 | | 9/14/2000 | | FAIL |
|
|
|
Route to fire department
|
Routing - PUBLIC WORKS | 8/14/2000 | | 8/21/2000 | | PASS |
|
|
|
|
Routing - PLUMBING | 8/18/2000 | | 8/21/2000 | | PASS |
|
|
|
PLANS APPROVED WITH CORRECTIONS NOTED.
|
Application received | | | 8/18/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 8/14/2000 | | 8/14/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 8/14/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE. Previously signed and approved by Bud Fulleton, Central District Health.
|
Plans ACCEPTED BY PLAN TECH | | | 8/9/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 8/4/2000 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/4/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/13/2001 | | | | FAIL |
|
|
|
Second Plan Modification KMM. Routed plans to fire for review at 8:00 am on 02-20-01 RMH
|
Routing - PLAN CHECK | 2/23/2001 | | | | |
|
|
|
|