Fee Review-notes | 8/7/2000 | 8/7/2000 | 5/9/2001 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 1/18/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8539 issued 1-18-01 to Westside Body Works.
|
Permanent Occupancy | | 1/16/2001 | 1/16/2001 | | DONE |
|
|
|
|
BLD-Final | 1/12/2001 | 1/16/2001 | 1/16/2001 | A | PASS |
Tom Arcoraci
|
|
|
FN -TIM ###-#### ok for perm occ 1/16/2001 10:36:09 AM
|
BLD-Final | 1/11/2001 | 1/12/2001 | 1/12/2001 | A | FAIL |
Russ Owen
|
|
|
Tim ###-####need engineers approval on purlin splice not on plans.also achd and zoning. 1/12/2001 1:13:37 PM
|
Code Occupancy Approval | | | 1/12/2001 | | PASS |
|
|
|
Meets compliance with DRH00-00012. Signed Final Occupancy.
|
FIRE-Final Inspection | 1/10/2001 | 1/11/2001 | 1/11/2001 | P | PASS |
Joe Tawney
|
|
|
###-#### Reinsp OK FOR PERMANANT OCCUPANCY 1/12/2001 8:13:34 AM
|
BLD-Foundation | 10/31/2000 | 11/1/2000 | 11/1/2000 | A | PASS |
Dave Hannah
|
|
|
Jed ###-####
|
BLD-Concrete | 10/31/2000 | 10/31/2000 | 10/31/2000 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 10/31/2000 pad ftgs
|
BLD-Footing | 10/30/2000 | 10/30/2000 | 10/30/2000 | P | PART |
Carl Dependahl
|
|
|
Jed ###-####
|
Print Occupancy Form | | | 10/23/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/23/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/23/2000 | | DONE |
|
|
|
|
Telephone call | | | 10/23/2000 | | DONE |
|
|
|
called permit ready and fees due and need ACHD
|
Issue PAID IN FULL permit | | | 10/23/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/3/2000 | | 10/20/2000 | | PASS |
|
|
|
Received approval on structural engineering. Issued permit.
|
Routing Off Site - STRUCTURAL | 10/16/2000 | | 10/20/2000 | | PASS |
|
|
|
CONTACTED PDQ TO TAKE RESUBMITTALS RECEIVED ON 10/13/00 TO OUTSIDE ENG. KMM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2000 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 8/10/2000 | | 10/20/2000 | | PASS |
Mike Otto
|
|
|
10/20/2000 16:03:17 MYS - activity updated through activity BLDA022 from case BLD00-02331.
|
Plan resubmittals received | | | 10/13/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM DALE BINNING, TWO SETS OF SHEET A-3a AND A-4a, PLUS TWO SETS SMALL DOCUMENTS FORWARDED SAME TO MIKE OTTO . 10/13/00 DAR
|
Plan resubmittals requested | | | 10/12/2000 | | FAIL |
|
|
|
STRUCTURAL CORRECTIONS ON FOUNDATION DESIGN.
|
Routing Off Site - STRUCTURAL | 10/4/2000 | | 10/12/2000 | | FAIL |
|
|
|
CORRECTIONS FAXED TO ARCHITECT.
|
Plan resubmittals received | | | 10/3/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM DALE BINNING TWO SETS OF SHEETS A-2A AND M-1A, FORWARDED SAME TO MIKE OTTO. 10/3/00 DAR
|
Routing - FIRE | 9/26/2000 | 9/29/2000 | 9/29/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 9/29/2000 | | FAIL |
|
|
|
plans returned to plan check
|
Plan resubmittals received | | | 9/27/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM DALE BINNING ARCHITECT THREE OF SHEET G AND SMALL DOCUMENTS, FORWARDED SAME TO MIKE OTTO. 9/27/00
|
Plan resubmittals requested | | | 9/26/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Routing - PLAN CHECK | 9/20/2000 | | 9/26/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Routing - PLUMBING | 9/14/2000 | | 9/19/2000 | | PASS |
|
|
|
use pvc or castiron drainage piping, abs is not suitable where petroleum products may be present in the waste stream
|
Routing - PLANNING | 9/12/2000 | | 9/14/2000 | | PASS |
|
|
|
Please see approval in DRH00-12
|
Routing - PUBLIC WORKS | 9/11/2000 | | 9/12/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/11/2000 | | DONE |
|
|
|
RECEIVED LETTER TO BRIAN M. REGARDING DRAINAGE ISSUES. WILL ROUTE TO PW. KMM
|
Routing Off Site - STRUCTURAL | 8/14/2000 | | 9/5/2000 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM CORRECTIONS FAXED TO ARCHITECT. MLO
|
Plans ACCEPTED BY PLAN TECH | | | 8/14/2000 | | HOLD |
|
|
|
STILL REQUIRES INFORMATION FOR BRIAN M. I TOLD DALE THAT I WILL SEND TO OUTSIDE ENG. BUT WILL HAVE TO HOLD UNTIL I RECEIVE BRIANS INFORMATION. PLAN IN MY HOLD BOX. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 8/10/2000 | | HOLD |
|
|
|
REQUIRES 1. COMMERCIAL ADDITION APPL. TO BE FILLED OUT
2. INVOLVED PARTIES SHEET NOT TO BE SIGNED.
3. CERT. OF VALUE NOT REQUIRED TO BE SIGNED.
4. FIVE COPIES OF CIVIL SHEETS WITH CALCS.
5. WHAT IS SOILS PRESSURE? MAY REQUIRE SOILS REPORT.
6. REQUIRES ONE ADDITIONAL COPY OF PLANS FOR OUTSIDE ENG.
FAXED REQUIREMENTS TO DALE BINNING. KMM
6. ENG. CALCS. NOT SIGNED BY DALE.
|
Pending Assignment by MYS | 8/7/2000 | | 8/10/2000 | | DONE |
Marlene Southard
|
|
|
8/10/00 13:09:32 JCM - activity updated through activity BLDA174 from case BLD00-02331.
|
Application received | | | 8/7/2000 | | |
|
|
|
|
Received Certificate of Value | | | 8/7/2000 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | | | |
|
|
|
|