Case Summary (BLD) | | | 5/6/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 4/11/2002 | | DONE |
|
|
|
|
Fee Review-notes | 8/8/2000 | 8/8/2000 | 9/17/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/14/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8814 issued 9-14-01 to Wall Enterprises, Inc.
|
Permanent Occupancy | | 9/13/2001 | 9/13/2001 | | DONE |
|
|
|
|
BLD-Final | 9/13/2001 | 9/13/2001 | 9/13/2001 | P | PASS |
Dave Hannah
|
|
|
###-#### ok for pem occ 9/13/2001 2:34:33 PM
|
FIRE-Final Inspection | 8/15/2001 | 8/15/2001 | 8/15/2001 | P | PASS |
Rick Jackson
|
|
|
fire fn matt- ###-####
|
FIRE-Final Inspection | 8/3/2001 | 8/3/2001 | 8/3/2001 | P | FAIL |
Joe Tawney
|
|
|
Final Fail C/N issued 8/3/2001 3:30:24 PM
|
BLD-Final | 5/29/2001 | 5/30/2001 | 5/30/2001 | A | NR |
Dave Hannah
|
|
|
bill ###-#### need all other finals 5/30/2001 10:18:33 AM
|
BLD-Framing/Rough-in | 12/4/2000 | 12/5/2000 | 12/5/2000 | A | PASS |
Tom Arcoraci
|
|
|
###-#### pending bath room fixture change see cabo ansi have arch re submit 12/5/2000 12:03:27 PM
|
BLD-Framing/Rough-in | 12/4/2000 | 12/5/2000 | 12/5/2000 | A | PASS |
Tom Arcoraci
|
|
|
###-#### pending bath room fixture change see cabo ansi have arch re submit 12/5/2000 12:03:27 PM
|
Routing Off Site - A.C.H.D | 11/6/2000 | 11/6/2000 | 11/6/2000 | | DONE |
|
|
|
cert #01-00048-paid 11/6/00*Nan $751.00
|
Issue PAID IN FULL permit | | | 11/6/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/9/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/9/2000 | | DONE |
|
|
|
|
Telephone call | | | 10/9/2000 | | DONE |
|
|
|
called permit ready
|
Routing - PLAN CHECK | 9/29/2000 | | 10/6/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2000 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 8/15/2000 | | 10/6/2000 | | PASS |
Jason Blais
|
|
|
10/6/2000 17:05:13 MYS - activity updated through activity BLDA022 from case BLD00-02345.
|
Routing - FIRE | 9/26/2000 | | 9/29/2000 | | PASS |
|
|
|
Resubmittal acceptable.
|
Routing - PLAN CHECK | 9/15/2000 | | 9/26/2000 | | PEND |
|
|
|
Permit and plan approval dependent on Fire Dept. approval of plans. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 9/21/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM DALE BINNING, TWO SETS OF SHEETS A-1a, A-1b AND A2a. FROWARDED SAME TO JASON BLAIS. 9/21/00 DAR
|
Plan Review Completed(1st rev) | | | 9/14/2000 | | FAIL |
|
|
|
failed building and fire reviews.
|
Routing - PLAN CHECK | 8/25/2000 | | 9/8/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Plan resubmittals requested | | | 9/8/2000 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLANNING | 8/22/2000 | | 8/25/2000 | | PASS |
|
|
|
AS PER DRH00-00088.
|
Routing - PUBLIC WORKS | 8/15/2000 | | 8/22/2000 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 8/15/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE.
|
Pending Assignment by MYS | 8/15/2000 | | 8/15/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/11/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 8/8/2000 | | DONE |
|
|
|
|
Application received | | | 8/8/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|