Case Summary (BLD) | | | 9/14/2009 | | DONE |
|
|
|
|
Fee Review-notes | 8/9/2000 | 8/9/2000 | 2/20/2003 | | DONE |
|
|
|
|
BLD-Aging Inspection | 2/12/2003 | 2/12/2003 | 2/12/2003 | | DONE |
Carl Dependahl
|
|
|
remodel of lobby...l/c only 2/12/2003 9:13:21 AM
|
DOC - Permit Finaled | 2/12/2003 | 2/12/2003 | 2/12/2003 | A | PASS |
Carl Dependahl
|
|
|
Finaled by inspector at 2/12/2003 9:13:53 AM
|
BLD-Final | 12/7/2000 | 12/8/2000 | 12/8/2000 | P | PASS |
Carl Dependahl
|
|
|
Tony ###-####
|
BLD-Framing/Rough-in | 11/1/2000 | 11/2/2000 | 11/2/2000 | A | CANC |
Tony Young
|
|
|
###-####
|
BLD-Framing/Rough-in | 11/2/2000 | 11/2/2000 | 11/2/2000 | P | PART |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 11/2/2000
NEED ICBO reports on efis system before installation, ok to insulate and rock on window areas 11/2/2000 1:47:08 PM
|
Issue PAID IN FULL permit | | | 10/23/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/28/2000 | | 9/28/2000 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 9/28/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/28/2000 | | DONE |
|
|
|
|
Telephone call | | | 9/28/2000 | | DONE |
|
|
|
TALKED TO GENE TO VERIFY PLANS ARE READY
|
Plan assigned to (JCB) | 8/15/2000 | | 9/28/2000 | | PASS |
Jason Blais
|
|
|
9/28/2000 14:22:19 JCB - activity updated through activity BLDA022 from case BLD00-02361.
|
Plan resubmittals received | | | 9/27/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A0.0, S1.0, A2.0 ROUTED TO JASON B. KMM
|
Routing - PLAN CHECK | 8/15/2000 | | 9/13/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review.
|
Plan resubmittals requested | | | 9/13/2000 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Plan routing begun/TENANTS | | | 8/15/2000 | | DONE |
|
|
|
Route to PLAN CHECK only.
|
Pending Assignment by MYS | 8/15/2000 | | 8/15/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/14/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 8/9/2000 | | DONE |
|
|
|
|
Application received | | | 8/9/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/9/2000 | | DONE |
|
|
|
|