Fee Review-notes | 6/27/2003 | 6/27/2003 | 6/27/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/20/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8795 issued 8-20-01 to Image Auto Sales.
|
BLD-Other | 8/17/2001 | 8/17/2001 | 8/17/2001 | P | DONE |
Bob Archibald
|
|
|
Bond has been posted - ok to sign off for final
|
Permanent Occupancy | | 8/17/2001 | 8/17/2001 | | DONE |
|
|
|
|
BLD-Conference | 8/9/2001 | 8/9/2001 | 8/9/2001 | P | DONE |
Dave Hannah
|
|
|
Leave CN requirering posting of bond with Public works for issuance of certificate of occupancy. 8/10/2001 3:28:49 PM owner is allready working with bill shoud have bond some time next week 8/10/2001 3:29:52 PM
|
Fee Review-notes | 8/15/2000 | 8/15/2000 | 7/16/2001 | | DONE |
|
|
|
|
BLD-Aging Inspection | 7/9/2001 | 7/9/2001 | 7/9/2001 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 7/9/2001 | 7/9/2001 | 7/9/2001 | A | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 7/9/2001 11:17:41 AM
|
BLD-Final | 5/7/2001 | 5/8/2001 | 5/8/2001 | A | PASS |
Dave Hannah
|
|
|
Final - reinspect
|
Print Occupancy Form | | | 5/8/2001 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 5/7/2001 | | PASS |
|
|
|
This project was staffing with Tempra Wilson and it was determined that it had met the legal requirements of the permit. I then met with Brandon Roberts to sign off the card, but he could not locate it as the contractor was the last one to have it.
|
Code Occupancy Approval | | | 5/4/2001 | | FAIL |
|
|
|
I met with Brandon Roberts to discuss the location of the ramp, as there was a concern on whethet it was over 7' back of the property line. According to Mr. Roberts. there are two parcels of land in this project. The eastern parcel had additional property taken by ACHD for future development. The western parcel had no land taken, as ACHD said they would do that later. This meant that the western parcel's property line is further south than the eastern parcel.
I was shown the survey stakes and I measured the ramp as being 8' from the property line. Issued to be staffed with Tempra Wilson.
|
Code Occupancy Approval | | | 5/3/2001 | | FAIL |
|
|
|
I received a call from Bill, Cascade Builders ###-####, stating that they are finished with the revisions. At 2pm I visited the site. Of note was was the "ramp" at the front westend of the lot. The ramp does not match the summited revision plans dated 4/19/2001 in that it is in front of the curbing in the lot. Based on the summited plans, it shows that the curbing is at the front setback. However, the ramp protrudes into the setback. Additionally, the tree for the northwest corner is missing.
|
Code Occupancy Approval | | | 4/4/2001 | | FAIL |
|
|
|
I met with Bill, ###-####, at the site to discuss getting final approval. I provided him with a copy of the letter from Termpra Wilson to Brandon Richards dated 3/23/01. I told him that the rear landscape area was not the necessary 10' and the ramp in the front was in the set back.
I was told that Brandon Richards was going to file for a variance for these items. Per a staffing between Tempra Wilson and I, I told him that we would consider a temporary occupancy if they posted for the work not completed in the DRH. This would be regardless of whether the variance was/was not approved.
|
BLD-Final | 3/30/2001 | 4/3/2001 | 4/3/2001 | A | CANC |
Dave Hannah
|
|
|
Bill, ###-####
|
BLD-Final | 4/2/2001 | 4/3/2001 | 4/3/2001 | A | NR |
Dave Hannah
|
|
|
###-#### 4/3/2001 4:26:31 PM
|
FIRE-Final Inspection | 3/29/2001 | 3/30/2001 | 3/30/2001 | A | PASS |
Joe Tawney
|
|
|
###-#### Reinsp OK for permanant occupancy 3/30/2001 12:43:03 PM
|
BLD-Final | 3/29/2001 | 3/30/2001 | 3/30/2001 | P | FAIL |
Dave Hannah
|
|
|
###-#### 3/30/2001 2:33:59 PM NEED TO FIRE CALLOR PLUMBING VENTS AND BOTTOM OF WALL IN ATTIC 3/30/2001 2:35:37 PM
|
FIRE-Final Inspection | 3/13/2001 | 3/14/2001 | 3/14/2001 | A | FAIL |
Joe Tawney
|
|
|
fire fn bill ###-#### Reinsp Fail C/N not done 3/14/2001 12:30:43 PM
|
FIRE-Final Inspection | 3/5/2001 | 3/6/2001 | 3/6/2001 | A | FAIL |
Joe Tawney
|
|
|
Bill, ###-#### Reinsp Fail C/N issued 3/6/2001 12:38:34 PM
|
FIRE-Final Inspection | 3/1/2001 | 3/1/2001 | 3/1/2001 | P | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail C/N issued 3/2/2001 8:17:05 AM
|
Code Occupancy Approval | | | 3/1/2001 | | FAIL |
|
|
|
A request was made for temp occupancy inspection by Bill, ###-####. Inspection was done and it was found that the landscaping area along the rear fence was only six (6) feet wide and not the ten (10) feet as indicated in the plans. Additionally, the landscaping scrubbs along the rear fence and the east side had not been completed. Curbing and sidewalk was also not completed, nor is the stripping. Bill was faxed a copy of the bonding requirements.
|
Inspection Record Card- Bld | | | 2/28/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/28/2001 | | DONE |
|
|
|
|
BLD-Other | 1/16/2001 | 1/17/2001 | 1/17/2001 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/16/2001 at 18:03:23. Contact: ###-####.insulation and seal kit ok tocover 1/17/2001 1:06:23 PM
|
BLD-Framing/Rough-in | 1/15/2001 | 1/16/2001 | 1/16/2001 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 01/15/2001 at 15:24:11. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/10/2001 | 1/11/2001 | 1/11/2001 | A | FAIL |
Dave Hannah
|
|
|
brent ###-#### fr not ready they didnt have
mec elec rough ins 1/11/2001 11:53:45 AM
|
Plan resubmittals received | | | 1/10/2001 | | DONE |
|
|
|
Received 6 sheets of sheet number 4 from Cascade Builders, forwarded same to Mike Otto. 1/10/01 DAR
|
Plan assigned to (MLO) | 12/19/2000 | | 1/10/2001 | | PASS |
Mike Otto
|
|
|
1/10/2001 15:29:32 MLO - activity updated through activity BLDA022 from case BLD00-02434.
|
Routing - PLAN CHECK | 1/10/2001 | | 1/10/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/10/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/10/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/10/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/9/2001 | | DONE |
|
|
|
Received three sets of plan resubmittals, sheets 4 and 5, plus structural caculations, forwarded same to Mike Otto. 1/9/01 DAR
|
Routing - PLAN CHECK | 1/9/2001 | | 1/9/2001 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/19/2000 | | 12/26/2000 | | FAIL |
|
|
|
Plan Modification
|
BLD-Framing/Rough-in | 12/18/2000 | 12/19/2000 | 12/19/2000 | A | PART |
Dave Hannah
|
|
|
Bill ###-#### shear nailing ok to cover north west& south walls east wall has three staps that are wrong need eng fix ok to cover if fix is on inside of wall
12/19/2000 11:04:11 AM
12/19/2000 11:05:55 AM
|
Plan resubmittals received | | | 12/15/2000 | | DONE |
|
|
|
|
CHANGE STATUS TO (PND) | | | 12/15/2000 | | DONE |
|
|
|
|
BLD-Conference | 12/12/2000 | 12/13/2000 | 12/13/2000 | P | PART |
Tom Arcoraci
|
|
|
CONF-- BILL-- ###-#### 12/13/2000 2:33:48 PM may have eng design cut for trusss at one hour wall 12/13/2000 5:16:15 PM
|
BLD-Conference | 12/8/2000 | 12/8/2000 | 12/8/2000 | P | PASS |
Dave Hannah
|
|
|
BRENT ###-#### FOR CONF 12/8/2000 2:02:03 PM
|
BLD-Conference | 12/4/2000 | 12/5/2000 | 12/5/2000 | A | FAIL |
Tom Arcoraci
|
|
|
FOR CONF-- BRENT ###-#### 12/5/2000 9:15:19 AM occ sep not per plan 12/5/2000 11:11:30 AM
|
Routing Off Site - A.C.H.D | 11/6/2000 | 11/6/2000 | 11/6/2000 | | DONE |
|
|
|
cert. #00-10844 paid 1877.00 on 10/12/00 by j newton
|
BLD-Footing | 11/3/2000 | 11/6/2000 | 11/6/2000 | A | PASS |
Dave Hannah
|
|
|
###-#### brent
|
(F) Reprint permit | | | 11/6/2000 | | DONE |
|
|
|
|
Routing - FIRE | 11/1/2000 | 11/3/2000 | 11/3/2000 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2000 | | DONE |
|
|
|
|
Inspector's copy Bld permit | | | 11/3/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/3/2000 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/3/2000 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 8/18/2000 | | 11/3/2000 | | PASS |
Mike Otto
|
|
|
11/3/2000 15:09:36 MLO - activity updated through activity BLDA022 from case BLD00-02434.
|
CHANGE ISSUED DATE | | | 11/3/2000 | | |
|
|
|
|
Plan resubmittals received | | | 11/2/2000 | | DONE |
|
|
|
Received plan resubmittals from Cascade Builders, two sets of sheets 1 and 2. Forwarded same to Mike Otto. 11/2/00 DAR THESE PLANS WERE SUBMITTED IN HOPES OF A FOUNDATION PERMIT BUT THE ADDITION OF THE FIRE SPRINKLERS SATISFIED THE HYDRANDT ISSUE AND FIRE APPROVED THE PROJECT. LETTER WAS SENT TO BILL ALEXANDER FROM THE OWNER BRANDON ROBERTS STATING THE BUILDING WOULD BE FULLY FIRE SPRINKLERED . RECEVD ON 11-3-2000.
|
Routing - PLAN CHECK | 10/31/2000 | | 11/1/2000 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/30/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS 1,2,3,4,5,6, TWO COPIES OF GREASE INTERCEPTOR INFORMATION AND TWO COPIES OFCALCULATIONS FROM RALPH A. KANGAS. ROUTED TO MIKE OTTO. KMM
|
Additional plans submitted | | | 10/30/2000 | | DONE |
|
|
|
RECEIVED PLANS FROM MTC, INC. FORWARDED SAME TO MIKE OTTO. 10/30/00 DAR
|
Routing - PLAN CHECK | 10/23/2000 | | 10/27/2000 | | FAIL |
|
|
|
CORRECTIONS FAXED AND COVERED WITH PHONE CALL TO ARCHITECT. MLO
|
Plan resubmittals requested | | | 10/27/2000 | | FAIL |
|
|
|
CORRECTIONS FROM 9-27-2000 UBC REVIEW INCOMPLETE.
|
Plan resubmittals received | | | 10/26/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS 2,3,4,5,6 FROM MIKE FAIRCHILD. ROUTED TO MIKE O. KMM
|
Plan resubmittals received | | | 10/23/2000 | | DONE |
|
|
|
RECEILVED PLAN RESUBMITTALS FROM MIKE FAIRCHILD, ARCHITECT.TWO SETS OF SHEETS 1, 2, 3, 4, 5 AND 6. ALSO SMALL DOCUMENTS, FORWARDED SAME TO MIKE OTTO. 10/23/00
|
Routing - FIRE | 9/29/2000 | 10/4/2000 | 10/4/2000 | | FAIL |
Bill Alexander
|
|
|
Lack hydrant location and minimum flow requirement certification. Other issues related to the UBC
|
Plan Review Completed(1st rev) | | | 10/4/2000 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 9/22/2000 | | 9/29/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED TO ARCHITECT
|
Plan resubmittals requested | | | 9/29/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Routing - PLUMBING | 9/15/2000 | | 9/18/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/13/2000 | | 9/15/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/13/2000 | | 9/13/2000 | | FAIL |
|
|
|
REQUIRES PROOF OF LEGAL LAND DIVISIONAND SIT PLAN DOES NOT COMPLY WITRECORDED PLAT/ OR LEGAL DESCRIPTION PEER JIM RICH. 9/13/00 DAR
|
Routing - PLUMBING | 9/11/2000 | | 9/13/2000 | | FAIL |
|
|
|
ROUTE BACK TO PW WHEN PLANS ARE BACK FROM PLUMBING. KMM
|
Routing - PLANNING | 8/7/1999 | | 9/9/2000 | | PASS |
|
|
|
Please see approval in DRH00-173
|
Routing - PUBLIC WORKS | 8/25/2000 | | 9/7/2000 | | FAIL |
|
|
|
REQUIRES PROOF OF LEGAL LAND DIVISION PER JIM RICH. 9/7/00 DAR
|
Plan routing begun/NEW & ADDTN | | | 8/25/2000 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/25/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 8/24/2000 | | DONE |
|
|
|
RECEIVED REVISED CERT. OF VALUE . PROJECT VALUE $120,000 ELECT. $24,000 PLUMB. $6,000 MECH. $15,000 FIRE ALARM $1,000 FIRE SPRINKLER N/A
|
Pending Assignment by JCM | 8/17/2000 | | 8/18/2000 | | DONE |
John Menard
|
|
|
8/18/00 08:10:42 JCM - activity updated through activity BLDA174 from case BLD00-02434.
|
Plans ACCEPTED BY PLAN TECH | | | 8/17/2000 | | PEND |
|
|
|
CONTACTED WILLIAM REES REQUESTING AN O&M MANUEL.
|
Received Certificate of Value | | | 8/15/2000 | | PEND |
|
|
|
WILL NEED TO BE REVISED DUE TO GRADING PERMIT. KMM
|
Application received | | | 8/15/2000 | | |
|
|
|
|