Fee Review-notes | 6/27/2003 | 6/27/2003 | 6/27/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent occupancy | | | 5/31/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8707 issued 5-31-01 to St. Luke's Hospital (addn.)
|
BLD-Final | 5/29/2001 | 5/29/2001 | 5/29/2001 | P | PASS |
Tony Young
|
|
|
###-#### Dan Wilson
ok for c of o 5/29/2001 4:02:19 PM
|
Permanent Occupancy | | 5/24/2001 | 5/24/2001 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 4/20/2001 | | PASS |
|
|
|
Mike Meloy ###-####
|
BLD-Final | 4/18/2001 | 4/18/2001 | 4/18/2001 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 04/18/2001 at 07:22:53. Contact: ###-####.
C/N POSTED, a.d.a. and sign offs 4/18/2001 2:34:16 PM
|
BLD-Final | 4/18/2001 | 4/18/2001 | 4/18/2001 | P | FAIL |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 4/18/2001 11:48:42 AM
|
FIRE-Final Inspection | 4/11/2001 | 4/12/2001 | 4/12/2001 | A | PASS |
Rick Jackson
|
|
|
Dan Wilson ###-####
|
BLD-Framing/Rough-in | 12/13/2000 | 12/14/2000 | 12/14/2000 | A | PASS |
Steven Webb
|
|
|
Bill ###-####Transfer to #408 12/14/2000 9:30:01 AM
|
BLD-Framing/Rough-in | 12/14/2000 | 12/14/2000 | 12/14/2000 | A | FAIL |
Tom Arcoraci
|
|
|
Scheduled by Inspector: 408 On 12/14/2000 11:15:57 AM per plan 12/14/2000 11:16:18 AM
|
BLD-Framing/Rough-in | 11/30/2000 | 12/1/2000 | 12/1/2000 | P | PART |
Tony Young
|
|
|
nailing Bill ###-####
exterior shear ok 12/1/2000 12:37:30 PM
|
BLD-Framing/Rough-in | 11/30/2000 | 11/30/2000 | 11/30/2000 | P | PART |
Tony Young
|
|
|
BILL ###-####- NAILING INSP--FOR A ROOF
roof nailing ok, upper east shear ok 11/30/2000 1:20:47 PM
|
BLD-Foundation | 11/8/2000 | 11/9/2000 | 11/9/2000 | P | PART |
Jim Storey
|
|
|
Bill ###-#### they are pouring at 2pm and they have a special inspector so as soon after lunch as possible placed with special insp. pending report. 11/13/2000 8:46:30 AM
|
Issue & PRINT to be Invoiced | | | 10/23/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/5/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/5/2000 | | DONE |
|
|
|
|
Telephone call | | | 10/5/2000 | | DONE |
|
|
|
EMAILED PERMIT READY AND FEES DUE AND NEED ACHD CERT
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/2000 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 8/23/2000 | | 10/4/2000 | | PASS |
Mike Otto
|
|
|
10/4/2000 14:36:25 MLO - activity updated through activity BLDA022 from case BLD00-02460.
|
Routing - PUBLIC WORKS | 9/29/2000 | | 10/3/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/25/2000 | | 9/29/2000 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/22/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS TWO SETS OF SHEETS A2.1 AND A8.1 FROM CSHQA ARCHITECTS, FORWARDED SAME TO MIKE OTTO. 9/22/00 DAR
|
Routing - FIRE | 9/15/2000 | 9/20/2000 | 9/20/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 9/20/2000 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 9/15/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Routing - PLAN CHECK | 9/13/2000 | | 9/15/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT.
|
Routing - PLUMBING | 9/11/2000 | | 9/13/2000 | | PASS |
|
|
|
per plans and 97 upc
|
Routing - PLANNING | 9/7/2000 | | 9/11/2000 | | PASS |
|
|
|
Please see approval in DRH00-28
|
Plan resubmittals received | | | 9/11/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM CSHQA ARCHITECTSVIA GREGG OSTROW, TWO SETS OF SHEETS A2.2, A4.1, A4.3, A4.4, S2.1. FORWARDED SAME TO MIKE OTTO. 9/11/00 DAR
|
Routing - PUBLIC WORKS | 8/31/2000 | | 9/7/2000 | | FAIL |
|
|
|
FIVE COPIES OF CIVIL SHEETS WITH CALCS. REQUIRED.REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. 9/7/00 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 8/31/2000 | | DONE |
|
|
|
received five copies of c1.0 put two copies with plans and three for brian m. kmm
|
Plan routing begun/NEW & ADDTN | | | 8/31/2000 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/23/2000 | | HOLD |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/23/2000 | | |
|
|
|
REQUIRES
FIVE COPIES OF CIVIL DRAWINGS WITH CALCS. FAXED JOHN MAULIN AND GREGG OSTROW OF THESE NEEDS. KMM
|
Received Certificate of Value | | | 8/17/2000 | | DONE |
|
|
|
|
Application received | | | 8/17/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/17/2000 | | DONE |
|
|
|
|