Case Summary (BLD) | | | 7/11/2011 | | |
|
|
|
|
Fee Review-notes | 8/17/2000 | 8/17/2000 | 4/19/2001 | | DONE |
|
|
|
|
Letter of compliance | | | 12/22/2000 | | DONE |
|
|
|
Letter of Compliance #21300 issued 12-22-00.
|
BLD-Final | 12/20/2000 | 12/21/2000 | 12/21/2000 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/20/2000 at 08:55:46. Contact: ###-####.ok for perm occ
12/21/2000 5:59:01 PM
|
FIRE-Final Inspection | 12/14/2000 | 12/15/2000 | 12/15/2000 | P | PASS |
Joe Tawney
|
|
|
###-#### Reinsp OK for permanant occupancy 12/17/2000 8:34:47 PM
|
FIRE-Final Inspection | 12/11/2000 | 12/13/2000 | 12/13/2000 | P | FAIL |
Joe Tawney
|
|
|
Jay ###-#### at 6:00 ###-#### cell Final Fail Hood test and spklr heads 12/14/2000 7:58:26 AM
|
BLD-Framing/Rough-in | 11/28/2000 | 11/29/2000 | 11/29/2000 | P | PART |
Tom Arcoraci
|
|
|
Jay Shatto ###-#### conf on shaft in kit 11/29/2000 3:46:58 PM
|
FIRE-Sprinkler Rough-in | 11/28/2000 | 11/29/2000 | 11/29/2000 | P | PART |
Joe Tawney
|
|
|
Jay Shatto ###-#### Conf with Jay Shatto on cafeteria remodel 11/30/2000 8:00:35 AM
|
Plan resubmittals received | | | 10/23/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTLES FROM HEWLETT PACKARD, SMALL DOCUMENTS PLUS TWO SETS OF PL;ANS WITH SHEETS A3.0, A4.0, A5.0,S-1, M-1, M-2, FORWARDED SAME TO TOM ARCORACI. DAN STUART ALSO RECEIVED THE SAME ITEMS. B
|
Inspection Record Card- Bld | | | 10/11/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/11/2000 | | DONE |
|
|
|
|
Telephone call | | | 10/11/2000 | | DONE |
|
|
|
Kathy ###-####
|
Issue & PRINT permit | | | 10/11/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/5/2000 | | 10/10/2000 | | PASS |
|
|
|
Approved as noted and attached to plans. Items required to be provided in field to appropriate inspector for review and approval. The system to be used to provide the required 1-hour shaft enclosure for the exhause grease duct is a deferred submittal under UBC section 106.4.3.2 and will be submitted for approval before installation per code section. Copies of report faxed and mailed to John Maulin & faxed copy to Cathy Miller, ECI.
|
Routing - FIRE | 10/10/2000 | | 10/10/2000 | | PASS |
|
|
|
Reviewed scope of work with Bill Alexander to determine if plans needed routing for Fire Code Analysis or if I could make comments concerning section 1006 and existing sprinkler & alarm system maintenance and upgrade requirements part of my review comments and make field review for compliance a condition of final approval & occupancy use for the area. This is what was determined. Processing for issuance of permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2000 | | PASS |
|
|
|
Processing for issuance of pemit.
|
Plan assigned to (DRS) | 8/29/2000 | | 10/10/2000 | | PASS |
Dan Stuart
|
|
|
10/10/2000 21:26:06 DRS - activity updated through activity BLDA022 from case BLD00-02463.
|
Routing - PLUMBING | 8/31/2000 | | 9/5/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/29/2000 | | 8/31/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 8/17/2000 | | 8/29/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 8/29/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE. Reviewed and signed by Bud Fulleton, Central District Health, on 8/17/00.
|
Plans ACCEPTED BY PLAN TECH | | | 8/24/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 8/17/2000 | | DONE |
|
|
|
|
Application received | | | 8/17/2000 | | |
|
|
|
|