Fee Review-notes | 6/30/2003 | 6/30/2003 | 6/30/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent Occupancy | | 6/26/2001 | 6/26/2001 | | DONE |
|
|
|
|
BLD-Final | 6/26/2001 | 6/26/2001 | 6/26/2001 | | PASS |
Russ Owen
|
|
|
Final/ok to issue perm. occ.
|
Permanent occupancy | | | 6/26/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8731 issued 6-26-01 to SCP Global Technologies.
|
FIRE-Final Inspection | 6/22/2001 | 6/22/2001 | 6/22/2001 | A | PASS |
Rick Jackson
|
|
|
Added by Inspector: 409 On 6/22/2001 8:57:52 AM
|
Temporary occupancy | | | 5/23/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4548 issued 5-23-01 to SCP Global Technologies.
|
BLD-Final | 5/18/2001 | 5/21/2001 | 5/21/2001 | A | PART |
Russ Owen
|
|
|
guardrails have been completed ,need the final letter from s-i and efis contractor and signatures for final. 12/21/2001 11:04:18 AM
|
BLD-Final | 5/16/2001 | 5/17/2001 | 5/17/2001 | P | PART |
Russ Owen
|
|
|
temp occ Ted ###-#### ok temp oc,need final letter for s-i and efis system, guardrail.at front. and all other signature. 12/17/2001 5:39:14 PM
|
FIRE-Final Inspection | 5/14/2001 | 5/15/2001 | 5/15/2001 | P | PART |
Joe Tawney
|
|
|
Ted Parrott ###-#### Final OK for temporary occupancy. Remaining items exc FACP to be completed within 2 to 3 days 5/15/2001 3:46:41 PM
|
FIRE-Final Inspection | 5/9/2001 | 5/10/2001 | 5/10/2001 | P | FAIL |
Joe Tawney
|
|
|
###-#### Final Fail Alarm system 5/10/2001 2:28:05 PM
|
BLD-Framing/Rough-in | 5/4/2001 | 5/7/2001 | 5/7/2001 | A | PART |
Russ Owen
|
|
|
handrail ted ###-#### laft stairway at front face has cooetions,also left ramp req handrails or architect to submit. 12/7/2001 12:01:23 PM
|
BLD-Framing/Rough-in | 4/23/2001 | 4/24/2001 | 4/24/2001 | A | PART |
Russ Owen
|
|
|
ceiling ted ###-#### ok to install ceiling grid, noted ext handrails not incompliance,also need approved ext wall cover for studs at 24 oc as per plans. 11/24/2001 1:59:29 PM
|
BLD-Framing/Rough-in | 4/2/2001 | 4/3/2001 | 4/3/2001 | A | PART |
Russ Owen
|
|
|
Ted Parrot ###-#### complete upper floor lights and lower floor adnl pods. 4/3/2001 12:42:39 PM
|
BLD-Framing/Rough-in | 3/1/2001 | 3/1/2001 | 3/1/2001 | P | PASS |
Russ Owen
|
|
|
###-####corrections made and verified by pinacle,project engineer.ok to sheetrock.exterior parapet still requires addnl anchorage. 3/1/2001 5:36:00 PM
|
BLD-Framing/Rough-in | 2/21/2001 | 2/22/2001 | 2/22/2001 | A | PART |
Russ Owen
|
|
|
###-####meet with framer will ,correct items and recall. 2/22/2001 12:22:35 PM
|
BLD-Framing/Rough-in | 2/20/2001 | 2/21/2001 | 2/21/2001 | A | FAIL |
Russ Owen
|
|
|
###-####,will meet with framer am. to go over c/n. 2/21/2001 1:54:36 PM
|
BLD-Foundation | 11/28/2000 | 11/29/2000 | 11/29/2000 | A | PART |
Russ Owen
|
|
|
Ted Parrott ###-#### subject to s-i 11/29/2000 12:25:47 PM
|
BLD-Footing | 11/17/2000 | 11/20/2000 | 11/20/2000 | A | PART |
Tom Arcoraci
|
|
|
will pour at 1:00\\###-#### sp insp 11/20/2000 8:45:51 AM
|
BLD-Footing | 11/13/2000 | 11/14/2000 | 11/14/2000 | A | PART |
Carl Dependahl
|
|
|
###-####; spec insp report pending 11/14/2000 10:23:30 AM
|
Routing - PLAN CHECK | 11/3/2000 | | 11/9/2000 | | PASS |
|
|
|
Received missing engineering information & detail. Plans approved per red-lined notes & attached plan check comments as part of the approved plan.
|
Plan resubmittals received | | | 11/9/2000 | | PASS |
|
|
|
Received submittals to engineering details as requested from Darren Truchot, Pinnacle Engineers. Routing to issue permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2000 | | PASS |
|
|
|
Routing to permit desk for issuance.
|
Print Occupancy Form | | | 11/9/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/9/2000 | | DONE |
|
|
|
|
Telephone call | | | 11/9/2000 | | DONE |
|
|
|
called permit ready
|
Issue PAID IN FULL permit | | | 11/9/2000 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 9/6/2000 | | 11/9/2000 | | PASS |
Dan Stuart
|
|
|
11/9/2000 09:50:35 DRS - activity updated through activity BLDA022 from case BLD00-02474.
|
Routing Off Site - STRUCTURAL | 10/25/2000 | | 11/8/2000 | | PASS |
|
|
|
RESUBMITTAL RESPONSE TO STRUCTURAL REVIEW COMMENTS OF 10/16/00 RECEIVED 10/23/00. FORWARDING TO PLANS & COMMENTS TO ENGINEER FOR REVIEW. 10/25/00 DAR
11/8/00 - Received fax from AHJ stating structural plan review & response to previous review comments are okay.
|
Plan resubmittals received | | | 11/8/2000 | | |
|
|
|
Recieved copy of approved EIFS system for use over wood.
|
Telephone call | | | 11/8/2000 | | DONE |
|
|
|
Call to Darren Trouchot of Pinnacle Engineers to request his details for 8/SD3; Special inspection list & deferred submittal comment on plans. He will fax to me.
|
Plan Reviewer's activity | | | 11/8/2000 | | PEND |
|
|
|
Organized plans & verified same data on both sets. Only need engineers thre resubmital resposnes to issued permit.
|
Plan resubmittals received | | | 11/7/2000 | | |
|
|
|
Partial submittal received.
|
Plan resubmittals received | | | 11/6/2000 | | |
|
|
|
Partial submittal.
|
Routing - PLANNING | 10/25/2000 | 10/25/2000 | 11/3/2000 | | PASS |
|
|
|
Approved resubmitted plans.
|
Plan resubmittals received | | | 11/3/2000 | | DONE |
|
|
|
Received plan resubmittals from BRS Architects, Mike Capshaw, small documents, forwarded same to Dan Stuart. 11/3/00 DAR Submittals received were all incorrect. No change that are in compliance with code are shown. Phone call to Mike Capshaw to review accessible shower section of CABO/ANSIn A117.1-92 for room width & shower dimensions for transfere type shower; the EIFS insulation system receieved was for SBSSI land not ICBO. Product not approved for here; access ladder details incorrect and the structural support detail of beam & column not correct. Also did not include structural details referenced by structural engineer in his response. Mike will resubmit.
|
Plan resubmittals requested | | | 10/25/2000 | | |
|
|
|
FAXED AND MAILED ANOTHER REQUEST TO THE ARCHITECT ASKING HIM TO PROVIDE THE DETAILS AND CLARIFICATIONS HE SAID WERE SUBMITTED BUT WERE NOT OR ITEMS THAT WERE ONLY PART RESPONDED TO.
|
Routing - PLAN CHECK | 10/17/2000 | | 10/25/2000 | | FAIL |
|
|
|
REORGANIZED NEW SUBMITTALS. SENT ONE NEW SET OF PLANS WITH STRUCTURAL ENGINEERS RESPONSE & NEW PLAN MODIFICATIONS TO OUR CONTRACT OUTSIDE ENGINEERING FIRM FOR A SECOND REVIEW. I DISCUSSED CHANGES TO LANDSCAPING OF ORIGINAL REVIEW WITH TEMPRA WILSON, PLANNING, TO SEE IF SHE WANTED TO REVIEW AGAIN. SHE DOES SO I AM ROUTING THEM BACK TO HER.
REVIEW OF THE ARCHITECT RESPONSE TO MY INITIAL PLAN REVIEW COMMENTS OF 10/12/00, INDICATED HE HAD SAID A RESPONSE WAS PROVIDED BUT THE PLANS DID NOT REFLECT ANY CHANGES OR NEW RESPONSE SUBMITTALS TO SEVERAL OF THE QUESTIONS NEEDING ADDRESSED TO SHOW COMPLIANCE WITH CODE. I FAXED AND MAILED ANOTHER FOUR PAGE REQUEST FOR RESUBMITTALS TO MOKE CAPSHAW, TRYING TO BE SPECIFIC ABOUT WHAT WAS ORIGINALLY ASK FOR; WHAT HIS RESPONSE WAS; AND WHAT HE STILL NEEDED TO PROVIDE.
|
Plan resubmittals received | | | 10/23/2000 | | DONE |
|
|
|
RECEIVED THREE SETS OF RESUBMITTALS FROM BRS ARCHITECTS, PLUS SMALL DOCUMENTS, FORWARDED SAME TO DAN STUART. 10/23/00 DAR
|
Routing - FIRE | 10/13/2000 | 10/17/2000 | 10/17/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 10/17/2000 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/28/2000 | 9/28/2000 | 10/16/2000 | | FAIL |
|
|
|
REPORT ON OUTSIDE STRUCTURAL PLAN REVIEW. RESUBMITTALS REQUIRED & ROUT BACK FOR ADDITIONAL REVIEW. COPY OF REPORT TO ARCHITECT, MIKE CAPSHAW FOR RESPONSE ON 10/16/00
|
Plan resubmittals requested | | | 10/12/2000 | | FAIL |
|
|
|
Mailed & faxed copy of plan correction requirements to architect, Mike Capshaw.
|
Routing - PLAN CHECK | 9/19/2000 | | 10/12/2000 | | FAIL |
|
|
|
Started review of plan 9/28/00. Structural review sent to outside engineering review this day. Response from architect required to plan review comments. Routing to fire code analyst for review while waiting for architects response.
|
Plan resubmittals received | | | 10/4/2000 | | DONE |
|
|
|
PLAN RESUBMITTALS RECEIVED FROM BRS ARCHITECTS, TWO SETS OF SMALL DOCUMENTS AND TWO SETS OF PLANS WITH THE FOLLOWING SHEETS SO.1, S1.1, S2.1, S3.1 AND S3.2, FORWARDED SAME TO DAN STUART. 10/4/00 DAR
|
Routing - PLUMBING | 9/14/2000 | | 9/19/2000 | | PASS |
|
|
|
extend 3" waste to 1st urinal, min. 1/4" per foot grade on all 4" roof drain and overflow, verify floor sink locations with field inspector
|
Routing - PLANNING | 9/11/2000 | | 9/14/2000 | | PASS |
|
|
|
Approve per DRH00-76 & 136
|
Routing - PUBLIC WORKS | 9/7/2000 | | 9/11/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/7/2000 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/31/2000 | | DONE |
|
|
|
|
Application received | | | 8/18/2000 | | |
|
|
|
|