Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-02512
StatusFinaled
Name IDAHO ELKS REHAB (PARKING LOT)
Site Address 600 N ROBBINS RD
Project NameIDAHO ELKS REHAB-PARKING LOT
Customer Number 
ePlanReviewNo
Description
ELKS REHABILITATION HOSPITAL * PARKING LOT PHASE IV * TO EXCAVATE, GRADE AND PAVE A PARKING LOT PER ENGINEERED PLANS ON FILE AS APPROVED BY THE PUBLIC WORKS DEPARTMENT. INSTALL CURBING, SRTIPING AS NOTED ON THE PLANS. NO BUILDINGS TO BE CONSTRUCTED, INTSTALLED, OR DEMOLTIONED UNDER THIS PERMIT. NO SITE UTILITES INCLUDED IN THIS PERMIT. CUP97-0087 DRH97-0195 PC#679-00 KMM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  3/11/2014 DONE
BLD-Final6/19/20016/19/20016/19/2001PPASS
DetailsCarl Dependahl
parking ok for l/c 6/19/2001 2:30:17 PM
BLD-Final6/19/20016/19/20016/19/2001PPASS
DetailsCarl Dependahl
parking ok for l/c 6/19/2001 2:34:27 PM
Letter of compliance  6/19/2001 DONE
Letter of Compliance #21545 issued 6-19-01.
Fee Review-notes8/31/20008/31/20005/31/2001 DONE
Code Occupancy Approval  5/31/2001 PASS
approved.
BLD-Conference5/25/20015/25/20015/25/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 5/25/2001 10:58:14 AM w/ Mike Wilson...need all other sig's for final & completetion of project
Print Occupancy Form  8/31/2000 DONE
Inspection Record Card- Bld  8/31/2000 DONE
Telephone call  8/31/2000 DONE
permit ready and fees due
Issue PAID IN FULL permit  8/31/2000 DONE
Routing - PLAN CHECK8/29/2000 8/30/2000 PASS
Routing - PUBLIC WORKS8/30/2000 8/30/2000 PASS
Print Pending Permit.LaserJet4  8/30/2000 DONE
PLANS/APPL TAKEN TO FRONT DESK  8/30/2000 DONE
Plan assigned to (KMM)8/23/2000 8/30/2000 PASS
DetailsKathy Miller
8/30/00 15:40:33 PME - activity updated through activity BLDA022 from case BLD00-02512.
Routing - FIRE8/28/2000 8/29/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  8/29/2000 FAIL
PW failed
Routing - PUBLIC WORKS8/23/2000 8/25/2000 FAIL
PUBLIC SEWER REROUTE NEEDS TO BE ACCEPTED PRIOR TO PAVING. CONTACT RICK CUMMINGS ###-#### FOR CONDITIONS OF ACCEPTIONS PER JOHN JOHNSON.
Routing - PLANNING8/25/2000 8/25/2000 PASS
x-ref. DRH97-195
Plan routing begun/NEW & ADDTN  8/23/2000 DONE
Application received  8/23/2000  
Application received  8/23/2000 DONE
Plans ACCEPTED BY PLAN TECH  8/23/2000 DONE
Received Certificate of Value  8/23/2000 DONE