Fee Review-notes | 8/24/2000 | 8/24/2000 | 5/23/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/31/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8552 issued 1-31-01 to Northwest Title Loans.
|
Permanent Occupancy | | 1/30/2001 | 1/30/2001 | | DONE |
|
|
|
|
BLD-Final | 1/30/2001 | 1/30/2001 | 1/30/2001 | P | PASS |
Tom Arcoraci
|
|
|
ok for perm occ 1/30/2001 5:19:48 PM
|
BLD-Final | 1/11/2001 | 1/12/2001 | 1/12/2001 | P | PART |
Tom Arcoraci
|
|
|
fn occ ###-#### lucretia ok for temp cn issued 1/12/2001 1:04:37 PM
|
Temporary occupancy | | | 1/12/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4504 issued 1-12-01 to Northwest Title Loans.
|
FIRE-Final Inspection | 1/9/2001 | 1/10/2001 | 1/10/2001 | A | PASS |
Joe Tawney
|
|
|
Reinsp OK for permanant occupancy 1/10/2001 12:39:25 PM
|
FIRE-Final Inspection | 1/5/2001 | 1/8/2001 | 1/8/2001 | P | FAIL |
Joe Tawney
|
|
|
Lucretia ###-#### Final Fail Door hdwre 1/8/2001 5:20:40 PM
|
BLD-Framing/Rough-in | 12/18/2000 | 12/19/2000 | 12/19/2000 | A | PASS |
Tom Arcoraci
|
|
|
FR INSP-- CELL ###-#### DANIEL 12/19/2000 9:49:55 AM
|
Print Occupancy Form | | | 11/14/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/14/2000 | | DONE |
|
|
|
|
Telephone call | | | 11/14/2000 | | DONE |
|
|
|
talked to steve 1-###-####
|
Issue PAID IN FULL permit | | | 11/14/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/25/2000 | | 11/13/2000 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/13/2000 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 8/31/2000 | | 11/13/2000 | | PASS |
Jason Blais
|
|
|
11/13/2000 13:16:32 JCB - activity updated through activity BLDA022 from case BLD00-02525.
|
Plan resubmittals received | | | 11/9/2000 | | DONE |
|
|
|
Received two copies of revised sheet A1.0. Routed to Jason B. KMM
|
Plan resubmittals received | | | 10/31/2000 | | DONE |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A1.0 ONE COPY OF RESPONSE LETTER FROM PAT MCKEEGAN AND ONE COPY OF LETTER FROM LUCRETIA ETIENNE. ROUTED TO JASON B. KMM
|
Routing - PLAN CHECK | 10/16/2000 | | 10/25/2000 | | FAIL |
|
|
|
Plan resubmittals and response did not address several items requiring correction from the intial review. Second plan review report sent and faxed to architect and tenant. Plan resubmittals and response required for further review, again.
|
Plan resubmittals received | | | 10/25/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PATRICK McKEEGAN ARCHITECT, SMALL DOCUMENTS AND TWO SETS OF SHEETS A1.0., FORWARDED SAME TO JASON BLAIS. 10/25/00 DAR
|
Plan resubmittals requested | | | 10/25/2000 | | |
|
|
|
Plan resubmittals and response required again. All deficient items were not addressed from the initial review.
|
Routing - FIRE | 10/12/2000 | 10/16/2000 | 10/16/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 10/16/2000 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 10/12/2000 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLAN CHECK | 9/8/2000 | | 10/12/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept.
|
Routing - PLANNING | 9/1/2000 | | 9/8/2000 | | PASS |
|
|
|
Approved per CZC00-95 (for exterior paint).
|
Routing - PUBLIC WORKS | 8/31/2000 | | 9/1/2000 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 8/31/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE.
|
Pending Assignment by MYS | 8/31/2000 | | 8/31/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/25/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/24/2000 | | PEND |
|
|
|
PLANS NEED TO BE DIMENSIONED. FAXED PAT OF THIS NEED. KMM
|
Received Certificate of Value | | | 8/24/2000 | | DONE |
|
|
|
|
Application received | | | 8/24/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/24/2000 | | DONE |
|
|
|
|