Information based on query as of Monday, July 1, 2024.
Permit Information
Permit NumberBLD00-02533
StatusFinaled
Name H & W INCORPORATED
Site Address 11400 EXECUTIVE DR
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 16,800 sq.ft. warehouse structure for 4 future individual tenants per approved plans on file. Construction to be concrete block with unprotected metal truss roof system with metal roof covering. Ceiling height is 14 ft. at the outside walls. NO OCCUPANCY FOR INDIVIDUAL TENANTS IS ALLOWED UNDER THIS PERMIT. SEPARATE PERMITS WILL BE REQUIRED TO ESTABLISH OCCUPANCY. (P.C.#687-00) DRH00-00129
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference3/18/20033/18/20033/18/2003ACANC
DetailsRuss Owen
just looking at permit hist. 3/18/2003 10:27:31 AM
Fee Review-notes8/24/20008/24/20005/23/2001 DONE
DOC - Permit Finaled2/28/20012/28/20012/28/2001PPASS
DetailsRuss Owen
Added by Inspector: 407 On 2/28/2001 1:37:03 PM ok pem oc.
Letter of compliance  2/28/2001 DONE
Letter of Compliance #21348 issued 2-28-01.
BLD-Final2/7/20012/8/20012/8/2001AFAIL
DetailsRuss Owen
###-####raise bath room sinks,letter from engineer ok special insp def.and zoning insp reqd. 2/8/2001 11:27:44 AM
FIRE-Final Inspection2/7/20012/8/20012/8/2001APASS
DetailsJoe Tawney
###-#### ###-#### Final OK for certificate of completion 2/8/2001 12:41:45 PM
BLD-Final1/30/20011/31/20011/31/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/30/2001 at 17:25:20. Contact: ###-####. grid ok 1/31/2001 11:18:43 AM
FIRE-Final Inspection1/29/20011/30/20011/30/2001AFAIL
DetailsRick Jackson
###-#### met with contractor for conference; reviewed items for final: fire lanes, signage, door hardware; address; exit signs 1/30/2001 9:34:03 AM
BLD-Framing/Rough-in1/9/20011/10/20011/10/2001PPASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 01/09/2001 at 18:21:15. Contact: ###-####.
BLD-Foundation10/31/200011/1/200011/1/2000APART
DetailsDave Hannah
Late AM, please. Bob, ###-####
BLD-Footing10/26/200010/27/200010/27/2000APART
DetailsCarl Dependahl
###-####; ext ftgs ok; centerline n/r 10/27/2000 12:13:05 PM
(F) Reprint permit  10/23/2000 DONE
Issue PAID IN FULL permit  10/20/2000 DONE
Inspection Record Card- Bld  10/19/2000 DONE
Print Occupancy Form  10/19/2000 DONE
Telephone call  10/19/2000 DONE
Bob Lemoine at ###-#### permit ready
Telephone call  10/18/2000 DONE
BOB LAMOINE, LAMOINE CONSTRUCTION CALLED TO CHECK ON PERMIT PROGRESS. I REVIEWED THE NEW SUBMITTAL CHANGES ON A4 FOR THE STEL SPANDRAL BEAM REQUIRED PER ENGINEERING AND ASK HIM TO PROVIDE A DETAIL SHOWING THE HEIGHT ON THE WALL FOR INSTALLATION AND THE SIZE OF THE BEAM PER DESIGN OF BEHLEN MANUFACTURING AS NOTED IN ENGINEERS PLAN REVIEW RE-SUBMITTAL RESPONSE. HE IS GETTING INFORMATION FOR ATTACHMENT TO PLANS.
PLANS/APPL TAKEN TO FRONT DESK  10/18/2000 PASS
ROUTED TO FRONT DESK FOR ISSUANCE OF PERMIT.
Routing - PLAN CHECK10/16/2000 10/18/2000 PASS
PLAN RE-SUBMITTALS ASSEMBLED INTO ORIGINAL PLAN SUBMITTALS WITH ENGINEERING RESPONSE AND SPECIAL INSPECTION APPLIACATION FORM TO BE COMPLETED AND DELIVERED TO STRUCTURAL INSPECTOR. MR. LEMOINE STATED DAVE CRAM, MTI, WILL BE THE SPECIAL INSPECTION AGENCY / INSPECTOR. CHECKED OFF ITEMS MIKE OTTO HAD MARKED FOR RESUBMITTAL.
Plan resubmittals received  10/18/2000  
Details
RECEIVED NEW SHEET A7 FOR DOOR MODIFICATIONS TO 3/4 HOUR ASSEMBLIES AT THE WEST SIDE WALL W/I 10 FEET OF PROPERTY LINE PER OSCAR. INSERTED INTO PLANS.
Meeting  10/18/2000 PASS
TOOK PLANS TO TEMPRA WILSON TO SHOW HER THE MODIFICATIONS TO THE WEST WALL SHOWING INSTALLATION OF NEW EXTERIOR FIRE-RATED DOORS REQUIRED BECAUSE OF EXCESSIVE TRAVEL DISTANCE WITHIN FUTURE TENANT SPACES (>75 FEET) AND NEW 4' X 4' EXTERIOR LANDINGS AT EACH DOOR. SHE STATED SHE WOULD NOT HAVE TO REVIEW PLANS AGAIN.
Application received  10/18/2000 DONE
Plan assigned to (MLO)8/31/2000 10/18/2000 PASS
DetailsMike Otto
10/18/2000 17:22:49 DRS - activity updated through activity BLDA022 from case BLD00-02533.
Meeting  10/17/2000 PASS
DISCUSSED RESUBMITTAL OF SITE PLAN WITH BILL ALEXANDER. FIRE CODE ANALYST. GRADING PERMIT HAD BEEN APPROVED WITH CONDITIONS. ARCHITECT HAD ADDRESSED SOME OF THE CONDITIONS ON THE RESUBMITTAL. BILL SIAD THE FIELD INSPECTOR WOULD REVIEW PER COMMENTS ON HIS PLAN REVIEW COMMENTS. DID NOT NEED TO ROUTE BACK.
Routing - PLUMBING10/11/2000 10/13/2000 PASS
per plans and 97 upc, project will require both P-1's, !st resubmitted sept. 21st. the second oct. 11th one has plumbing the other has site utilities.
Plan resubmittals received  10/12/2000 DONE
RECEIVED TWO COPIES OF REVISED SHEET P1. PUT WITH PLANS. KMM
Plan resubmittals received  10/12/2000 DONE
RECEIVED TWO COPIES OF REVISED SHEETS A0, A1, A2, A3, A4, A6. TWO COPIES OF RESPONSE TO CITY COMMENTS. PUT WITH PLANS. KMM
Plan resubmittals received  10/11/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM LARRY KNOPP, TWO SETS OF SHEET A1, FORWARDED SAME TO MIKE OTTO. 10/11/00 DAR
Routing - PLUMBING9/29/2000 10/2/2000 FAIL
please provide a plan showing the routing of the domestic water and sanitary sewer services
Routing - FIRE9/25/20009/28/20009/28/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  9/28/2000 FAIL
Plan resubmittals requested  9/26/2000 FAIL
STRUCTURAL CORRECTIONS
Routing Off Site - STRUCTURAL8/31/2000 9/26/2000 FAIL
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM CORRECTIONS FAXED TO ARCHITECT. MLO
Routing - PLAN CHECK9/20/2000 9/25/2000 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT
Plan resubmittals requested  9/25/2000 FAIL
UBC CORRECTIONS
Plan resubmittals received  9/21/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM LARRY KNOPP, 4 SHEETS OF A-1, TWO SHEETS OF A-3 AND P-1, FORWARDED SAME TO MIKE OTTO. 9/21/00 DAR
Routing - PLUMBING9/18/2000 9/20/2000 FAIL
requested information not provided
Routing - PLAN CHECK9/13/2000 9/18/2000  
PLANS ROUTED TO PLUMBING AND FIRE FOR EXCAVATION PERMIT UBC PLAN REVIEW ON HOLD. MLO
Routing - PLUMBING9/6/2000 9/12/2000 FAIL
increase of venting cross sectional area required, dcva and thermol expantion protection required on building water service, cleanouts required on waste lines over 5'. provide a plan showing size and location of building water and sewer services.
Routing - PLANNING9/1/2000 9/6/2000 PASS
Approve per DRH00-129
Routing - PUBLIC WORKS8/28/2000 9/1/2000 PASS
Telephone call  9/1/2000 DONE
RECEIVED TELEPHONE CALL FROM KEITH JONES STATING THAT WITHOUT THE FOUNDATION CALCULATIONS HE MUST PUT THE STRUCTURAL REVIEW ON HOLD. ARCHITECT WILL BE CONTACTED AGAIN TO PROVIDE CALCS ASAP. MLO
Plans ACCEPTED BY PLAN TECH  8/31/2000 DONE
Additional plans submitted  8/29/2000 DONE
RECEIVED THREE COPIES OF ENG. STEEL PLANS AND CALCS FOR THE BUILDING. JOHN MENARD STATED PLANS SHOW THE LOADS BUT NOT CALCULATIONS. BOB LEMOINE SAID THOSE WILL BE ENROUTE. KMM
Telephone call  8/28/2000 DONE
SPOKE WITH LARRY KNOPP'S OFFICE REQUESTING THREE COPIES OF STEEL ENG. PLANS FOR THE BUILDING WITH STRUCTURAL CALCULATION. KMM
Plans ACCEPTED BY PLAN TECH  8/28/2000 HOLD
ROUTED ONE COPY OF PLANS AND STRUCT. CALCS. TO MARLENE FAXED LARRY ABOUT STEEL BUILDING PLANS AND ENG. BEING REQUIRED. COPY OF PLAN FOR OUTSIDE REVIEW ARE IN MY HOLD BOX. KMM
Received Certificate of Value  8/28/2000 DONE
INITIAL CERT. OF VALUE WAS $469.000. MR. LEMOINE REQUESTED A GRADING PERMIT. NEW CERT. OF VALUE * PROJECT VALUE $400,400 ELECT. $28,200 PLUMB. $6,000 MECH. $9,200
Plan routing begun/NEW & ADDTN  8/28/2000 DONE
Recd Pcfee & Taken To Pln CK  8/24/2000 DONE