Fee Review-notes | 8/25/2000 | 8/25/2000 | 5/23/2001 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/8/2001 | 1/8/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/8/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8529 issued 1-8-01 to Tomlinson & Assoc.
|
BLD-Final | 12/20/2000 | 12/20/2000 | 12/20/2000 | P | PART |
Carl Dependahl
|
|
|
ed ###-#### fn occ, ok for t/o, bldg has fire, bsmt corridor and handrail issues 12/20/2000 4:03:08 PM
|
FIRE-Final Inspection | 11/16/2000 | 11/17/2000 | 11/17/2000 | P | FAIL |
Rick Jackson
|
|
|
###-####
|
BLD-Final | 11/16/2000 | 11/17/2000 | 11/17/2000 | P | FAIL |
Carl Dependahl
|
|
|
ED-- ###-#### FN
|
BLD-Framing/Rough-in | 11/13/2000 | 11/14/2000 | 11/14/2000 | A | PART |
Carl Dependahl
|
|
|
suspended ceiling Ed ###-####...2nd fl. hallways & a 11/14/2000 4:08:33 PM djacent rms 11/14/2000 4:08:56 PM
|
BLD-Framing/Rough-in | 10/30/2000 | 10/30/2000 | 10/30/2000 | P | PART |
Jim Storey
|
|
|
2nd floor ed ###-####
|
BLD-Framing/Rough-in | 10/6/2000 | 10/9/2000 | 10/9/2000 | A | PART |
Jim Storey
|
|
|
fr insp ed-- ###-#### framing ok need plan change at copy rm elaator wall configuration and 2 hr stair wall change under stair. 10/9/2000 10:19:08 AM
|
Issue PAID IN FULL permit | | | 10/6/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/2/2000 | | 10/5/2000 | | PASS |
|
|
|
Passed 2nd UBC review.
|
Plan assigned to (CJW) | 8/31/2000 | | 10/5/2000 | | PASS |
Carl Westfall
|
|
|
10/5/00 11:50:53 CJW - activity updated through activity BLDA022 from case BLD00-02538.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2000 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/5/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/5/2000 | | DONE |
|
|
|
|
Telephone call | | | 10/5/2000 | | DONE |
|
|
|
called permit ready
|
Plan resubmittals received | | | 10/3/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM ZGA ARCHITECTS TWO SETS OF SHEET A-1, FORWARDED SAME TO CARL WESTFALL. 10/3/00 DAR
|
Routing - FIRE | 9/27/2000 | | 10/2/2000 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 10/2/2000 | | |
|
|
|
Failed first UBC review.
|
Routing - PLAN CHECK | 9/5/2000 | | 9/27/2000 | | |
|
|
|
Failed first UBC review.
|
Plan Reviewer's activity | | | 9/25/2000 | | |
|
|
|
UBC plan review started September 25, 2000 and finished September 27, 2000. A response from the architect was required. See the conditions list.
|
Routing - PUBLIC WORKS | 8/31/2000 | | 9/5/2000 | | PASS |
|
|
|
|
Pending Assignment by MYS | 8/25/2000 | | 8/31/2000 | | DONE |
Marlene Southard
|
|
|
|
Pending Assignment by MYS | 8/31/2000 | | 8/31/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 8/31/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 8/29/2000 | | DONE |
|
|
|
FAXED ARCH./ENG. RECORD FORM TO JIM TOMLINSON. KMM
|
Received Certificate of Value | | | 8/25/2000 | | DONE |
|
|
|
|
Application received | | | 8/25/2000 | | |
|
|
|
|