Fee Review-notes | 6/30/2003 | 6/30/2003 | 6/30/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Fee Review-notes | 8/30/2000 | 8/30/2000 | 11/9/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/26/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8886 issued 10-26-01 to Florence/Morris Dental.
|
Permanent Occupancy | | 10/19/2001 | 10/19/2001 | | DONE |
|
|
|
|
BLD-Final | 5/17/2001 | 5/17/2001 | 5/17/2001 | P | PART |
Jim Storey
|
|
|
###-#### call 1/2 hr. prior to meet there final ok pending plumbing signing off occ. card.// please final this insp. upon isueance of c.o./ 5/17/2001 4:53:28 PM
|
FIRE-Final Inspection | 5/16/2001 | 5/16/2001 | 5/16/2001 | P | PASS |
Rick Jackson
|
|
|
Tim Wilson ###-#### please call 1/2 hour before you go out
|
Code Occupancy Approval | | | 5/15/2001 | | PASS |
|
|
|
ALL CONDITIONS HAVE BEEN MET AND FINAL OCCUPANCY SIGNED OFF.
|
BLD-Energy code compliance | 3/27/2001 | 3/27/2001 | 3/27/2001 | P | PASS |
Steven Webb
|
|
|
tim wilson-- ==###-#### Prior c/n items corrected. 3/27/2001 2:05:19 PM
|
BLD-Framing/Rough-in | 3/23/2001 | 3/23/2001 | 3/23/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-#### call 1/2 hour prior to meet there , c/n, clarify shear at int & east side,ok to insul 3/23/2001 5:27:36 PM
|
BLD-Foundation | 1/2/2001 | 1/2/2001 | 1/2/2001 | P | PART |
Steven Webb
|
|
|
FOUND INSP ROBERT- ###-#### CELL: # 5 bar not in south stem wall as approved plans indicated, need engineering stating #4 is ok, already poured. Inspected by inspector #301 not 420. 1/2/2001 1:00:02 PM 1/2/2001 1:00:41 PM
|
BLD-Footing | 12/28/2000 | 12/28/2000 | 12/28/2000 | P | PART |
Jim Storey
|
|
|
###-#### c/n #5 bar required 2 horr on ft only have #4 provide justafacation. 12/28/2000 3:34:15 PM
|
BLD-Foundation | 12/13/2000 | 12/14/2000 | 12/14/2000 | P | PASS |
Jim Storey
|
|
|
FOUND WALL CLIFF ###-####
|
BLD-Footing | 12/13/2000 | 12/13/2000 | 12/13/2000 | P | PART |
Jim Storey
|
|
|
Tim Wilson ###-#### interior basement footing rebar ok. 12/13/2000 2:54:11 PM
|
Routing Off Site - A.C.H.D | 11/22/2000 | 11/22/2000 | 11/22/2000 | | DONE |
|
|
|
cert #01-00110
|
Issue PAID IN FULL permit | | | 11/22/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/17/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/17/2000 | | DONE |
|
|
|
|
Telephone call | | | 11/17/2000 | | DONE |
|
|
|
talked to jackie gave dollar amount also needs achd
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2000 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 9/6/2000 | | 11/16/2000 | | PASS |
Mike Otto
|
|
|
11/16/2000 15:26:09 MLO - activity updated through activity BLDA022 from case BLD00-02587.
|
Routing - PUBLIC WORKS | 11/13/2000 | | 11/15/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/6/2000 | | 11/13/2000 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/31/2000 | | 11/6/2000 | | PASS |
|
|
|
additional cross connection protection may be required, cleaned for oxy. service and brazed joints shall be required for the compressed air system.
|
Additional plans submitted | | | 11/3/2000 | | DONE |
|
|
|
Received structural caculations from Larry Knopp Architects,two sets, forwarded same to Mike Otto. 11/3/00 DAR
|
Plan resubmittals received | | | 10/30/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS TWO SETS OF SHEETS P-5 & P-6 FROM LARRY KNOPP'S OFFICE, FORWARDED SAME TO MIKE OTTO. 10/30/00 DAR
|
Plan resubmittals received | | | 10/12/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM LARRY KNOPP, TWO SETS OF SHEETS A3 AND A10 FORWARDED SAME TO MIKE OTTO. 10/12/00 DAR
|
Routing - FIRE | 10/10/2000 | 10/10/2000 | 10/10/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLUMBING | 10/10/2000 | | 10/10/2000 | | FAIL |
|
|
|
The notes on page A-3 do not meet the min. requirements of section 1304 of the 97 UPC. Please provide a complete set of medical gas and vacuum plans showing the proposed piping system layout, and sizes, location of compressed air intake and vacuum pump discharge, a list of materials specified, and equipment details.
|
Routing - PLAN CHECK | 10/4/2000 | | 10/9/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT.
|
Plan resubmittals requested | | | 10/9/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Plan resubmittals received | | | 10/3/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS TWO SETS OF SHEETS P1, P2, P3 AND P4, FORWARDED SAME TO MIKE OTTO. 10/3/00 DAR
|
Plan resubmittals received | | | 10/2/2000 | | DONE |
|
|
|
RESUBMITTALS RECEIVED FROM LARRY KNOPPTWO SETS OF A-1 FOR BILL ALEXANDER AND TWO SETS OF SHEETS A2, A3, A5, AND A9 FORWARDED ALL PLANS RECEIVED TO MIKE OTTO. 10/2/00 DAR
|
Routing - FIRE | 9/22/2000 | 9/27/2000 | 9/27/2000 | | FAIL |
Bill Alexander
|
|
|
Lack sufficient information on critical UFC issues, i.e. medical gass, hydrant location and required minimum flow available. plans returned to plan review
|
Plan resubmittals requested | | | 9/22/2000 | | FAIL |
|
|
|
UBC CORRECTIONS
|
Routing - PLAN CHECK | 9/15/2000 | | 9/22/2000 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT
|
Routing - PLANNING | 9/8/2000 | | 9/11/2000 | | PASS |
|
|
|
Please see approval in DRH00-114
|
Routing - PUBLIC WORKS | 9/6/2000 | | 9/8/2000 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. 9/8/00 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 9/6/2000 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 9/6/2000 | | 9/6/2000 | | PASS |
Mike Otto
|
|
|
|
Application received | | | 8/30/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/30/2000 | | DONE |
|
|
|
|
Routing - PLUMBING | 9/11/2000 | | 3/15/2000 | | FAIL |
|
|
|
backwater valve required for fixtures in the basement, the floor drain in the basement must be upgraded to a floor sink to recieve the discharge from the vacuum pump, please provide a plan showing the medical gas and vacuum piping and equipment details.
|