Permit Information
Permit NumberBLD00-02587
StatusFinaled
Name FLORENCE MICHAEL J & SHARON M
Site Address 140 E BOISE AVE
Project Name 
Customer Number20108
ePlanReviewNo
Description
FLORENCE/MORRIS DENTAL- TO CONSTRUCT A 2047 SQ. FT., TYPE VN, SINGLE STORY OFFICE ADDITION WITH A 478 SQ. FT. BASEMENT USED ONLY FOR MECHANCIAL EQUIPMENT. OTHER WORK INLCUDES ALL SITE WORK, PAVING AND LANDSCAPING PER APPROVED PLANS AND ATTACHMENTS. NO FLAMMABLE MEDICAL GASES ARE PROPOSED PER THIS PERMIT. DRH00-00114, PC#707-00 MLO
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/30/20036/30/20036/30/2003 DONE
Additional values from subcontractors.
Fee Review-notes8/30/20008/30/200011/9/2001 DONE
Permanent occupancy  10/26/2001 DONE
Perm. Occ. Cert. #8886 issued 10-26-01 to Florence/Morris Dental.
Permanent Occupancy 10/19/200110/19/2001 DONE
Details
BLD-Final5/17/20015/17/20015/17/2001PPART
DetailsJim Storey
###-#### call 1/2 hr. prior to meet there final ok pending plumbing signing off occ. card.// please final this insp. upon isueance of c.o./ 5/17/2001 4:53:28 PM
FIRE-Final Inspection5/16/20015/16/20015/16/2001PPASS
DetailsRick Jackson
Tim Wilson ###-#### please call 1/2 hour before you go out
Code Occupancy Approval  5/15/2001 PASS
ALL CONDITIONS HAVE BEEN MET AND FINAL OCCUPANCY SIGNED OFF.
BLD-Energy code compliance3/27/20013/27/20013/27/2001PPASS
DetailsSteven Webb
tim wilson-- ==###-#### Prior c/n items corrected. 3/27/2001 2:05:19 PM
BLD-Framing/Rough-in3/23/20013/23/20013/23/2001PFAIL
DetailsCarl Dependahl
###-#### call 1/2 hour prior to meet there , c/n, clarify shear at int & east side,ok to insul 3/23/2001 5:27:36 PM
BLD-Foundation1/2/20011/2/20011/2/2001PPART
DetailsSteven Webb
FOUND INSP ROBERT- ###-#### CELL: # 5 bar not in south stem wall as approved plans indicated, need engineering stating #4 is ok, already poured. Inspected by inspector #301 not 420. 1/2/2001 1:00:02 PM 1/2/2001 1:00:41 PM
BLD-Footing12/28/200012/28/200012/28/2000PPART
DetailsJim Storey
###-#### c/n #5 bar required 2 horr on ft only have #4 provide justafacation. 12/28/2000 3:34:15 PM
BLD-Foundation12/13/200012/14/200012/14/2000PPASS
DetailsJim Storey
FOUND WALL CLIFF ###-####
BLD-Footing12/13/200012/13/200012/13/2000PPART
DetailsJim Storey
Tim Wilson ###-#### interior basement footing rebar ok. 12/13/2000 2:54:11 PM
Routing Off Site - A.C.H.D11/22/200011/22/200011/22/2000 DONE
cert #01-00110
Issue PAID IN FULL permit  11/22/2000 DONE
Inspection Record Card- Bld  11/17/2000 DONE
Print Occupancy Form  11/17/2000 DONE
Telephone call  11/17/2000 DONE
talked to jackie gave dollar amount also needs achd
PLANS/APPL TAKEN TO FRONT DESK  11/16/2000 DONE
Plan assigned to (MLO)9/6/2000 11/16/2000 PASS
DetailsMike Otto
11/16/2000 15:26:09 MLO - activity updated through activity BLDA022 from case BLD00-02587.
Routing - PUBLIC WORKS11/13/2000 11/15/2000 PASS
Routing - PLAN CHECK11/6/2000 11/13/2000 PASS
Routing - PLUMBING10/31/2000 11/6/2000 PASS
additional cross connection protection may be required, cleaned for oxy. service and brazed joints shall be required for the compressed air system.
Additional plans submitted  11/3/2000 DONE
Received structural caculations from Larry Knopp Architects,two sets, forwarded same to Mike Otto. 11/3/00 DAR
Plan resubmittals received  10/30/2000 DONE
RECEIVED PLAN RESUBMITTALS TWO SETS OF SHEETS P-5 & P-6 FROM LARRY KNOPP'S OFFICE, FORWARDED SAME TO MIKE OTTO. 10/30/00 DAR
Plan resubmittals received  10/12/2000 DONE
RECEIVED PLAN RESUBMITTALS FROM LARRY KNOPP, TWO SETS OF SHEETS A3 AND A10 FORWARDED SAME TO MIKE OTTO. 10/12/00 DAR
Routing - FIRE10/10/200010/10/200010/10/2000 PASS
DetailsBill Alexander
Routing - PLUMBING10/10/2000 10/10/2000 FAIL
The notes on page A-3 do not meet the min. requirements of section 1304 of the 97 UPC. Please provide a complete set of medical gas and vacuum plans showing the proposed piping system layout, and sizes, location of compressed air intake and vacuum pump discharge, a list of materials specified, and equipment details.
Routing - PLAN CHECK10/4/2000 10/9/2000 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT.
Plan resubmittals requested  10/9/2000 FAIL
UBC CORRECTIONS
Plan resubmittals received  10/3/2000 DONE
RECEIVED PLAN RESUBMITTALS TWO SETS OF SHEETS P1, P2, P3 AND P4, FORWARDED SAME TO MIKE OTTO. 10/3/00 DAR
Plan resubmittals received  10/2/2000 DONE
RESUBMITTALS RECEIVED FROM LARRY KNOPPTWO SETS OF A-1 FOR BILL ALEXANDER AND TWO SETS OF SHEETS A2, A3, A5, AND A9 FORWARDED ALL PLANS RECEIVED TO MIKE OTTO. 10/2/00 DAR
Routing - FIRE9/22/20009/27/20009/27/2000 FAIL
DetailsBill Alexander
Lack sufficient information on critical UFC issues, i.e. medical gass, hydrant location and required minimum flow available. plans returned to plan review
Plan resubmittals requested  9/22/2000 FAIL
UBC CORRECTIONS
Routing - PLAN CHECK9/15/2000 9/22/2000 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT
Routing - PLANNING9/8/2000 9/11/2000 PASS
Please see approval in DRH00-114
Routing - PUBLIC WORKS9/6/2000 9/8/2000 FAIL
REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. 9/8/00 DAR
Plans ACCEPTED BY PLAN TECH  9/6/2000 DONE
Plan assigned to (MLO)9/6/2000 9/6/2000 PASS
DetailsMike Otto
Application received  8/30/2000  
Recd Pcfee & Taken To Pln CK  8/30/2000 DONE
Routing - PLUMBING9/11/2000 3/15/2000 FAIL
backwater valve required for fixtures in the basement, the floor drain in the basement must be upgraded to a floor sink to recieve the discharge from the vacuum pump, please provide a plan showing the medical gas and vacuum piping and equipment details.