Letter of compliance | | | 2/7/2001 | | DONE |
|
|
|
Letter of Compliance #21338 issued 2-7-01.
|
BLD-Final | 2/5/2001 | 2/6/2001 | 2/6/2001 | A | PASS |
Carl Dependahl
|
|
|
fn occ ###-#### don , need t/i to occupy...to be
"scotttrade" 2/6/2001 10:57:06 AM
|
BLD-Final | 1/26/2001 | 1/26/2001 | 1/26/2001 | P | FAIL |
Carl Dependahl
|
|
|
fn occ don ###-#### ok for t/o, need complete storefront, obtain other final 1/26/2001 3:07:37 PM
|
FIRE-Final Inspection | 1/24/2001 | 1/24/2001 | 1/24/2001 | P | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Conference | 1/17/2001 | 1/17/2001 | 1/17/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/17/2001 4:12:18 PM w/ bldr re c/n
|
BLD-Framing/Rough-in | 1/9/2001 | 1/10/2001 | 1/10/2001 | A | PART |
Carl Dependahl
|
|
|
fr don- ###-#### int partitions ok; landing at front being added, ok to cover 1/10/2001 3:39:32 PM
|
BLD-Framing/Rough-in | 11/1/2000 | 11/2/2000 | 11/2/2000 | A | PART |
Carl Dependahl
|
|
|
###-####; walls ok 11/2/2000 11:17:31 AM
|
BLD-Framing/Rough-in | 10/31/2000 | 11/1/2000 | 11/1/2000 | A | FAIL |
Carl Dependahl
|
|
|
FR ISNP -LARRY- ###-#### complete firestops at 1hr wall, c/n issued. 11/1/2000 10:04:35 AM
|
Print Occupancy Form | | | 10/9/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/9/2000 | | DONE |
|
|
|
|
Telephone call | | | 10/9/2000 | | DONE |
|
|
|
called permit ready
|
Issue PAID IN FULL permit | | | 10/9/2000 | | DONE |
|
|
|
|
Plan assigned to (JCB) | 9/22/2000 | | 10/6/2000 | | PASS |
Jason Blais
|
|
|
10/6/2000 15:54:18 MYS - activity updated through activity BLDA022 from case BLD00-02654.
|
Routing - PLAN CHECK | 9/25/2000 | | 10/6/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2000 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/3/2000 | | DONE |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PATRICK McKEEGAN,TWO SETS SHEETS A1.0 AND A1.1,FORWARDED SAME TO JASON BLAIS . 10/3/00 DAR.
|
Plan Review Completed(1st rev) | | | 9/25/2000 | | FAIL |
|
|
|
failed bldg review
|
Routing - FIRE | 9/23/2000 | | 9/25/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/14/2000 | | 9/23/2000 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
|
Plan resubmittals requested | | | 9/23/2000 | | |
|
|
|
Plan resubmittals and response required for further review.
|
Routing - PLANNING | 9/13/2000 | | 9/14/2000 | | PASS |
|
|
|
Due to installation of outside entry door this needs to be routed to Planning.
|
Pending Assignment by MYS | 9/7/2000 | | 9/13/2000 | | DONE |
Marlene Southard
|
|
|
|
Routing - PUBLIC WORKS | 9/7/2000 | | 9/11/2000 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 9/7/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/7/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 9/7/2000 | | DONE |
|
|
|
|
Application received | | | 9/7/2000 | | |
|
|
|
|