Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD00-02729
StatusExpired
Name LOG CABIN LITERARY CENTER
Site Address 801 S CAPITOL BLVD
Project Name 
Customer Number 
ePlanReviewNo
Description
**LOG CABIN LITERARY CENTER** THIS BUILDING IS AN HISTORICAL BUILDING. This permit is for construction of an accessible ramp to the basement area, the remodel of two restrooms in the basement area to make fully accessible, the installation of a wheelchair lift at the front entrance to the first floor for convinece (this level is not required to be accessible), the installation of a sprinkler system in the basement, the installation of a new HVAC system throughout, the construction of a one-hour wall and installation of a 20minute fire rated door which will separate the basement area from the first floor, construction of a trash enclosre. Separate permits required for Mechanical, electrical, plumbing and fire sprinklers required. The fire sprinkler system shall be installed per NFPA #13 as regulated by the fire department. (P.C.#737-00)*RMH* PLAN MODIFICATION 5/12/03 : INSTALLATION OF NEW ELEVATOR IN LIEU OF PLATFORM LIFT, CHANGING HVAC, CHANGING LOCATION OF RESTROOMS, ADDING BREAKROOM AREA, ALTERING THE BASEMENT AREAS & STAIRWAY CONFIGURATION (RMH / 5/12/03)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Framing/Rough-in10/1/200310/1/200310/1/2003PPASS
DetailsDave Hannah
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung ok to cover basement 10/1/2003 12:42:58 PM
BLD-Framing/Rough-in9/9/20039/10/20039/10/2003APART
DetailsDave Hannah
HARVEY; Phone #: ###-#### Internet Inspection Request from: Marc Lileks ok to cover basement walls 1st and 2nd floors 9/10/2003 10:36:25 AM
BLD-Framing/Rough-in9/8/20039/9/20039/9/2003AFAIL
DetailsDave Hannah
harvey; Phone #: ###-#### Internet Inspection Request from: Annette Moore needs fire blocking ok to insulate 9/9/2003 10:06:28 AM
BLD-Conference8/26/20038/27/20038/27/2003ADONE
DetailsDave Hannah
###-#### harvery 8/27/2003 8:59:35 AM
BLD-Framing/Rough-in7/22/20037/23/20037/23/2003ANR
DetailsCarl Dependahl
nel; Phone #: ###-#### Internet Inspection Request from: Annette Moore
BLD-Conference7/23/20037/23/20037/23/2003PPART
DetailsCarl Dependahl
chimney ok to remain, doesn't obstruct door 7/23/2003 1:04:10 PM
BLD-Aging Inspection6/17/20036/17/20036/17/2003 PASS
DetailsCarl Dependahl
see history, WIP. 6/17/2003 10:22:36 AM
(F) Reprint permit  5/30/2003  
CHANGE STATUS TO (ISS)  5/30/2003 DONE
CHANGE TO ISS PLAN MOD
Print Occupancy Form  5/28/2003  
Telephone call  5/28/2003  
LEFT MESS THAT PERMIT IS READY
Case Summary (BLD)  5/27/2003  
PLANS/APPL TAKEN TO FRONT DESK  5/27/2003 DONE
Inspection Record Card- Bld  5/27/2003  
Print Occupancy Form  5/27/2003  
Plan assigned to (R_H)4/15/2003 5/27/2003 PASS
Details
5/27/2003 10:58:27 RMH - activity updated through activity BLDA022 from case BLD00-02729.
Plan resubmittals received  5/21/2003 DONE
letter of transmittal, Response letter to Ron, letter to Tim H. letter to Jack Rayne (State of Idaho) Memo, two sets of A2.0, A2.1, A2.2, A5.0, A6.0, and taken to Ron H,
Routing - PLAN CHECK4/24/2003 5/13/2003 FAIL
Plan modification. Faxed and mailed requirements to the architect on 5/12/03. Fire department already reviewed and approved
Case Summary (BLD)  5/13/2003 DONE
Routing - PLANNING4/22/2003 4/24/2003 PASS
Plan Modification. Approve
Routing - FIRE4/16/2003 4/22/2003 PASS
DetailsBill Alexander
Plan modification
Routing - PLAN CHECK4/15/2003 4/16/2003  
Plan modification
Routing - PUBLIC WORKS4/15/2003 4/16/2003 PASS
Plan modification
Plan routing begun/TENANTS  4/15/2003 DONE
Plan modification 4/15/03
Plan Modification Accepted  4/15/2003 DONE
Received three copies of plan mod sheets Cover shet. A2.0, A2.1, A2.2, A3.0, A4.0, A5.0, A6.0, M1.0, M1.1, M2.0, M2.1, M3.0, M3.1, M3.2, M4.0, M4.1, M4.2, M5.0, E1.1, E2.1, E3.1, E4.1. KMM
BLD-Aging Inspection4/1/20034/1/20034/1/2003 PASS
DetailsCarl Dependahl
Log cabin, WIP... 4/1/2003 9:48:10 AM
BLD-Conference1/28/20031/29/20031/29/2003APASS
DetailsCarl Dependahl
MARGIE; Phone #: ###-#### Internet Inspection Request from: Darla Downs..."phase 1" handrail changes approved verbally by Marty Santoyo; much of work is via grants & donations and is slow, apparently Armstrong Arch's has taken on this job (Margie Kennedy)...ok...this is a "city project" 1/29/2003 9:08:17 AM
PubWorks Occupancy Approval12/16/200212/16/200212/16/2002 DONE
Drainage project appears complete 12/16/02, no inspections since 1/9/01. R.Rokovitz
BLD-Conference12/11/200212/12/200212/12/2002APASS
DetailsCarl Dependahl
w/ designer...referred to design review 12/12/2002 8:46:15 AM
BLD-Conference12/10/200212/11/200212/11/2002PPASS
DetailsCarl Dependahl
john; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie...W/ DESIGNER/PROJ. MGR: NEED DESIGN REVIEW OK FOR CHANGES TO RAILS; CONTACT p&Z 12/11/2002 2:59:24 PM
FIRE-Supply Line Cover3/5/20013/5/20013/5/2001PPASS
DetailsRick Jackson
Scheduled by Inspector: 409 On 3/5/2001 11:03:11 AM okay to cover 3/5/2001 11:06:48 AM
BLD-Conference2/14/20012/15/20012/15/2001APART
DetailsCarl Dependahl
###-####, c/n...need historical review, comply w/UBC509 2/15/2001 3:40:49 PM
BLD-Footing1/16/20011/17/20011/17/2001APART
DetailsCarl Dependahl
###-#### PLANS ARE INSIDE THE DOOR; ftg at bsmt ramp, pend mti report 1/17/2001 11:48:43 AM
Issue PAID IN FULL permit  12/13/2000 DONE
Routing - PLAN CHECK11/7/2000 12/6/2000 PASS
DetailsRon Hill
Plan assigned to (R_H)9/21/2000 12/6/2000 PASS
Details
12/6/2000 09:15:12 RMH - activity updated through activity BLDA022 from case BLD00-02729.
Routing - PLAN CHECK11/28/2000 12/6/2000 PASS
DetailsRon Hill
PLANS/APPL TAKEN TO FRONT DESK  12/6/2000 PASS
DetailsRon Hill
Print Occupancy Form  12/6/2000 DONE
Inspection Record Card- Bld  12/6/2000 DONE
Telephone call  12/6/2000 DONE
called permit ready
Routing - FIRE11/27/2000 11/28/2000 PASS
DetailsBill Alexander
Plan resubmittals received  11/27/2000 DONE
RECEIVED ONE COPY OF COVER LETTER TWO COPIES OF REVISED SHEETS A1.2, A2.1 TWO COPIES OF STRUCTURAL CALCULATIONS. ROUTED TO RON HILL. KMM
Routing - FIRE11/1/2000 11/7/2000 FAIL
faxed comments to architect
Plan Review Completed(1st rev)  11/7/2000 FAIL
failed bldg and fire reviews.
Routing - PLAN CHECK9/29/2000 11/1/2000 FAIL
DetailsRon Hill
Route to fire,
Plan Reviewer's activity  11/1/2000 FAIL
DetailsRon Hill
Faxed and mailed requirements to the architect, Cathy Sewell of ZGA Architects, WIll route to fire department.
Routing - PLANNING9/26/2000 9/27/2000 PASS
TEMPRA WILSON.
Routing - PUBLIC WORKS9/21/2000 9/26/2000 PASS
Plan routing begun/TENANTS  9/21/2000 DONE
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  9/15/2000 DONE
Received Certificate of Value  9/13/2000 DONE
Application received  9/13/2000  
Fee Review-notes9/13/20009/13/2000