Fee Review-notes | 6/30/2003 | 6/30/2003 | 6/30/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/4/2002 | | DONE |
|
|
|
Perm. Occ. Cert. #9055 issued 3-4-02 to St. Luke's Regional Medical Center for offices.
|
BLD-Final | 2/27/2002 | 2/27/2002 | 2/27/2002 | P | PASS |
Carl Dependahl
|
|
|
This is the one we talked about, Carl... ok for perm. occ. 2/27/2002 4:25:07 PM
|
Permanent Occupancy | | 2/27/2002 | 2/27/2002 | | DONE |
|
|
|
|
BLD-Final | 8/24/2001 | 8/24/2001 | 8/24/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-#### dan; C/n, firestop bsmt lid penetrations, manual bolts at doors, etc...ok for t/o. 8/24/2001 5:35:07 PM
|
DOC - Permit Finaled | 8/24/2001 | 8/24/2001 | 8/24/2001 | P | PASS |
Carl Dependahl
|
|
|
Finaled by inspector at 8/24/2001 4:39:38 PM
|
FIRE-Final Inspection | 8/22/2001 | 8/23/2001 | 8/23/2001 | A | PASS |
Rick Jackson
|
|
|
###-#### delilah
|
FIRE-Final Inspection | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/14/2001 at 08:53:41. Contact: ###-####. FM 200 panel in trouble; strobe in basement must ceiling mount 8/14/2001 11:37:44 AM
|
FIRE-Final Inspection | 8/8/2001 | 8/9/2001 | 8/9/2001 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/08/2001 at 13:06:12. Contact: ###-####. items from previous correction notice weren't completed; fire sprinkler preaction system air pressure switch activated the "general fire alarm". alarm system not tested properly. reinspection fee added with parcel hold by Marsha per my request 8/9/2001 9:34:03 AM
|
BLD-Aging Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | | PASS |
Carl Dependahl
|
|
|
wip 8/6/2001 9:23:57 AM
|
BLD-Wall cover | 6/5/2001 | 6/6/2001 | 6/6/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/05/2001 at 13:41:12. Contact: ###-####.ALL ROOMS OK TO COVER & TILE 6/6/2001 11:56:01 AM
|
BLD-Conference | 5/17/2001 | 5/17/2001 | 5/17/2001 | P | PASS |
Carl Dependahl
|
|
|
ED ###-####
|
FIRE-Conference | 5/11/2001 | 5/14/2001 | 5/14/2001 | A | PART |
Rick Jackson
|
|
|
###-#### 10 am pressure test of FM 200 room pass 5/14/2001 11:06:37 AM
|
BLD-Framing/Rough-in | 5/11/2001 | 5/14/2001 | 5/14/2001 | A | PART |
Carl Dependahl
|
|
|
for comp room for pres test---10:00 ??????????/ed -###-####..grid ok, seal membrane penetrations at 1hr walls 5/14/2001 10:37:21 AM
|
BLD-Conference | 5/7/2001 | 5/7/2001 | 5/7/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/7/2001 1:23:16 PM w/ Ed re handraills
|
BLD-Other | 4/17/2001 | 4/17/2001 | 4/17/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/17/2001 at 07:35:42. Contact: ###-####. grid at computer rm ok, add spacer bars, obtain elec. r/i... chk at final... 4/17/2001 3:48:18 PM
|
BLD-Framing/Rough-in | 4/6/2001 | 4/9/2001 | 4/9/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/06/2001 at 14:22:57. Contact: ###-####. southwest area partitions ok. C/N issued re ID label on fire glazing and grid install at rooms 4/9/2001 11:17:35 AM, 4/9/2001 11:18:36 AM
|
BLD-Framing/Rough-in | 4/2/2001 | 4/3/2001 | 4/3/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/02/2001 at 17:05:12. Contact: ###-####. west end ok to cover. 4/3/2001 12:42:18 PM
|
BLD-Framing/Rough-in | 3/30/2001 | 4/2/2001 | 4/2/2001 | A | PART |
Carl Dependahl
|
|
|
###-####...rec'd termite reports, eng'r ok'd straps for holes in joists...add stud shoes at overbored studs at west end; ok to cover except as noted; submit comple ER for ext stucco ( 1hr) gaps at windows at N. & E. 4/2/2001 5:25:19 PM
|
BLD-Framing/Rough-in | 3/30/2001 | 3/30/2001 | 3/30/2001 | P | CANC |
Jim Storey
|
|
|
###-#### out of time contractor will recall. 4/2/2001 2:03:00 PM
|
BLD-Framing/Rough-in | 3/22/2001 | 3/22/2001 | 3/22/2001 | P | FAIL |
Carl Dependahl
|
|
|
Ed ###-####, keep c/n, do not cover lids til joist holes resolved; submit termite report and eifs info... 3/22/2001 5:20:05 PM
|
BLD-Framing/Rough-in | 3/21/2001 | 3/21/2001 | 3/21/2001 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/21/2001 at 10:12:52. Contact: ###-####. 2nd c/n issued, ok to cover walls at cental areas pend other insps; need submittal for eifs, ok for holes at joists, etc; infill gaps at 1hr walls3/21/2001 2:32:53 PM 3/21/2001 2:34:23 PM
|
BLD-Framing/Rough-in | 3/20/2001 | 3/20/2001 | 3/20/2001 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/20/2001 at 07:42:13. Contact: ###-####. center area, seal/ fireblock; add straps; engr to chk holes at joists 3/20/2001 6:03:39 PM
|
BLD-Final | 3/19/2001 | 3/19/2001 | 3/19/2001 | P | NR |
Carl Dependahl
|
|
|
###-####\\nailing
|
BLD-Framing/Rough-in | 3/19/2001 | 3/19/2001 | 3/19/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/19/2001 10:00:29 AM west portion roof heathing ok; need termite report info
|
BLD-Framing/Rough-in | 3/15/2001 | 3/16/2001 | 3/16/2001 | A | PART |
Carl Dependahl
|
|
|
ED ###-#### partial rough in ; ok to 1 side central portion int walls & elec room walls. 3/16/2001 12:23:10 PM
|
BLD-Framing/Rough-in | 3/9/2001 | 3/12/2001 | 3/12/2001 | P | PART |
Carl Dependahl
|
|
|
###-####, central section roof deck nailing ok; ok to cover int partition walls at east end only...awaiting termite report. 3/12/2001 4:30:20 PM
|
BLD-Framing/Rough-in | 2/27/2001 | 2/28/2001 | 2/28/2001 | A | FAIL |
Carl Dependahl
|
|
|
late am ###-####;c/n: fireblocks, tighten nuts at col's & saddles; arch to clarify beam brg condition at ext wall. Possible termite damage noted at existing ext walls. OK to insul walls at east end only. 2/28/2001 3:49:20 PM
|
BLD-Framing/Rough-in | 2/28/2001 | 2/28/2001 | 2/28/2001 | P | PART |
Carl Dependahl
|
|
|
roofing deck insp-- john- ###-#### low section south side center 1/3 ok 2/28/2001 3:40:51 PM
|
BLD-Framing/Rough-in | 2/27/2001 | 2/27/2001 | 2/27/2001 | P | PART |
Carl Dependahl
|
|
|
nail insp--john-- ###-#### ok, s.e. corner low roof area...watch over driv 2/27/2001 4:45:24 PM ennails 2/27/2001 4:45:29 PM
|
BLD-Conference | 2/23/2001 | 2/26/2001 | 2/26/2001 | P | PASS |
Carl Dependahl
|
|
|
###-####; new supt. on job for Petra....WIP 2/26/2001 10:48:09 AM
|
BLD-Framing/Rough-in | 2/23/2001 | 2/26/2001 | 2/26/2001 | P | NR |
Carl Dependahl
|
|
|
###-####; need elec & plbg r/i. complete nailing at roof 2/26/2001 10:48:49 AM
|
BLD-Framing/Rough-in | 2/20/2001 | 2/20/2001 | 2/20/2001 | P | PART |
Russ Owen
|
|
|
ROOF NAILING\\PARTIAL###-#### ###-#### JOHN.need more nailing painted areas in blue with contractor. 2/20/2001 2:55:06 PM
|
BLD-Framing/Rough-in | 2/15/2001 | 2/16/2001 | 2/16/2001 | A | PART |
Tom Arcoraci
|
|
|
###-#### roof sheeting nailing ok parapet sheeting nailing ok parapet sheet rock wip nailing ok ok to rock int walls of elec room at north side of building 2/16/2001 10:59:14 AM
|
BLD-Foundation | 2/14/2001 | 2/15/2001 | 2/15/2001 | P | PART |
Carl Dependahl
|
|
|
###-#### pend spec insp report 2/15/2001 3:42:33 PM
|
BLD-Conference | 2/8/2001 | 2/8/2001 | 2/8/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/8/2001 11:07:19 AM w/ supt re fire rated windows...req'd at n. & e. sides, rated assy needed
|
BLD-Foundation | 2/6/2001 | 2/7/2001 | 2/7/2001 | A | PART |
Carl Dependahl
|
|
|
re-bar Bill ###-#### pouring concrete at 11; int col. ftgs; also has spec insp report for epoxy inserts 2/7/2001 11:26:44 AM
|
BLD-Conference | 1/25/2001 | 1/25/2001 | 1/25/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/25/2001 9:38:58 AM w/ bldr re fire windows
|
BLD-Framing/Rough-in | 1/23/2001 | 1/24/2001 | 1/24/2001 | A | NR |
Steven Webb
|
|
|
###-####
|
BLD-Framing/Rough-in | 1/24/2001 | 1/24/2001 | 1/24/2001 | P | PART |
Carl Dependahl
|
|
|
###-####, parapet frame ok to sheath,add dens-deck gold at north & east sides for 1hr. 1/24/2001 4:22:55 PM
|
Issue & PRINT to be Invoiced | | | 1/17/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/16/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/16/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/16/2001 | | DONE |
|
|
|
E-MAILED CURTIS
|
Routing - FIRE | 1/8/2001 | 1/8/2001 | 1/12/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 1/12/2001 | | 1/12/2001 | | PASS |
|
|
|
ROUTED TO PERMIT DESK TO ISSUE.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2001 | | PASS |
|
|
|
ROUTING TO ISSUE
|
Plan assigned to (DRS) | 9/21/2000 | | 1/12/2001 | | PASS |
Dan Stuart
|
|
|
1/12/2001 15:39:04 DRS - activity updated through activity BLDA022 from case BLD00-02752.
|
Routing - PLAN CHECK | 12/14/2000 | | 1/8/2001 | | PEND |
|
|
|
Resubmittals received and approved. Complete sets of new plans on 1/4/01 & clarifications on 8-1/2" x 11" sheets 0n 1/8/00. Routing to fire code analyst for review.
|
Plan resubmittals received | | | 1/4/2001 | | DONE |
|
|
|
Two sets of plan resubmittals received from St. Lukes, CSHQA, and small documents. Forwarded same to Dan Stuart. 1/4/01 DAR
|
Routing - PUBLIC WORKS | 12/8/2000 | | 12/14/2000 | | PASS |
|
|
|
|
Routing - FIRE | 12/5/2000 | 12/8/2000 | 12/8/2000 | | FAIL |
Bill Alexander
|
|
|
Lack sufficient info relating with UBC to finish review.
|
Plan Review Completed(1st rev) | | | 12/8/2000 | | FAIL |
|
|
|
|
Routing - PLANNING | 12/4/2000 | 12/4/2000 | 12/5/2000 | | DONE |
|
|
|
Approved as per DRH00-00147
|
Plan resubmittals requested | | | 12/2/2000 | | |
|
|
|
Faxed & mailed copy of plan review comments to John Maulin, Architect, CSHQA for response / resubmittals.
|
Routing - PLAN CHECK | 10/2/2000 | | 12/2/2000 | | FAIL |
|
|
|
Copy of plan review comments to John Maulin, mailed & faxed. Corrections / resubmittals required. Routing to planning & fire code analysts for review while waitng for response.
|
Routing - PUBLIC WORKS | 9/22/2000 | | 10/2/2000 | | FAIL |
|
|
|
GEO THERMAL SERVICE ALREADY EXISTS TO THIS BUILDING.NO INFORMATION PROVIDED AS TO HOW THIS WILL BE ABANDONED. 10/2/00 DAR
|
Plan routing begun/TENANTS | | | 9/22/2000 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 9/15/2000 | | DONE |
|
|
|
|
Application received | | | 9/15/2000 | | |
|
|
|
|
BLD-Framing/Rough-in | 3/6/2001 | 3/6/2001 | 3/7/2000 | A | PART |
Carl Dependahl
|
|
|
John ###-#### roof nailing; 65 sq. west of penthouse ok 3/7/2001 9:23:24 AM
|
BLD-Framing/Rough-in | 2/26/2001 | 2/26/2001 | 2/27/2000 | P | NR |
Carl Dependahl
|
|
|
###-#### John
|