Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-02754
StatusFinaled
Name (VANILLA FINISH-NO TENANT)
Site Address 1065 W BOEING ST
Project NameBOEING WAREHOUSE #7
Customer Number 
ePlanReviewNo
Description
*VANILLA FINISH - FUTURE TENANT SPACE - NO OCCUPANCY / USE UNDER THIS PERMIT* To construct new interior non-bearing walls and ceiling structure to create and finish areas for future use as private & open office, breakroom & two accessible complying restrooms, all approximately 950 sq. ft. in area. Remaining portion of 21,370 sq. ft. being prepared for possible storage area. This permit includes installation of smoke & heat removal vents in roof as indicated on plans and per 1997 UFC, Article 81; to complete the 1-hour tenant separation wall between this tenant space and space immediately to the North. NO OTHER WORK UNDER THIS PERMIT. REQUIRED ELECTRICAL, PLUMBING & MECHANICAL BEYOND THAT INDICATED SPECIFICALLY ON PLAN IS REQUIRED TO PART OF APPLICATION & PLAN SUBMITTAL FOR A TIME OF TENANT IMPROVEMENT PERMIT FOR NEW TENANT. FUTURE SUBMITTAL MAY REQUIRED AN OCCUPANCY SEPARATION WALL BETWEEN TENANT SPACES AND OTHER AREAS DEPENDING ON FINAL OCCUPANCY USE DECLARATIONS BY FUTURE TENANT. THIS SPACE WILL BE REQUIRED TO BE FULLY ACCESSIBLE AS A CONDITION OF THE NEW FUTURE TENANT AND DETAILS ARE TO BE PROVIDE ON FUTURE PLAN SUBMITTALS DECLARING THE ACCESSIBLE ROUTE, TO INCLUDE PARKING, RAMPS, LANDINGS, RAILINGS, DOORS, HARDWARE, ETC. PER CH. 11, APPENDIX CH. 11 & CABO/ANSI A117.1-92. NOTE: This building is fully fire sprinkled under previous permits with specific limits based on strorage heights and commodity classification per Article 81 UFC & NFPA #13. A SEPARATE SUBMITTAL OF APPLICATION, ENGINEERING FOR DESIGN & LOAD CALCULATIONS, RACK ATTACHMENT TO CONCRETE, ETC. PER SECTIONS 2222 THRU 2229, CH. 22, DIV. X, VOL.II, 1997 UBC. **NO OCCUPANCY ALLOWED UNDER THIS PERMIT**. Letter of Compliance/Completion to be issued upon final approvals by inspection agencies. (P.C.#745-00)/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  4/20/2001 DONE
Letter of Compliance #21477 issued 4-20-01.
BLD-Final4/5/20014/5/20014/5/2001PPASS
DetailsJim Storey
Gene ###-#### Please call first l/c ok 4/5/2001 4:12:49 PM
BLD-Final4/3/20014/4/20014/4/2001AFAIL
DetailsJim Storey
gene---- ###-#### fn occ---call 1st before insp need roof access. 4/4/2001 10:38:32 AM
Fee Review-notes9/15/20009/15/20003/19/2001 DONE
Temporary occupancy  2/12/2001 PART
Temp. Occ. Cert. #4514 issued 2-12-01 for a vanilla finish.
BLD-Final2/7/20012/8/20012/8/2001PFAIL
DetailsJim Storey
FN--GENE -###-####--CALL 1ST BEFORE INSP arch. to submit to planreview deleation of smoke vents on tennent occ. permit/ ada despencer must be 7 inches from fixture. 2/8/2001 5:10:50 PM
FIRE-Final Inspection2/8/20012/8/20012/8/2001PPASS
DetailsRick Jackson
Gene ###-####
FIRE-Final Inspection2/7/20012/7/20012/7/2001PFAIL
DetailsRick Jackson
Scheduled by Inspector: 409 On 2/7/2001 3:39:33 PM door hardware on rear exits; rear door blocked with construction debris; smoke vent resolution needed from architect 2/7/2001 3:40:32 PM
BLD-Conference1/22/20011/22/20011/22/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/22/2001 5:06:45 PM w/301 re trusses; last inspection. trusses are inverted
BLD-Framing/Rough-in1/18/20011/19/20011/19/2001APART
DetailsJim Storey
Gene ###-#### need truss mgf. marking on all trusses/ need to verify truss repair . 1/19/2001 9:19:04 AM
BLD-Framing/Rough-in1/12/20011/16/20011/16/2001AFAIL
DetailsCarl Dependahl
FR GENE ###-####, keep c/n...truss eng'r to reanalyze as installed 1/16/2001 3:28:11 PM
BLD-Framing/Rough-in1/8/20011/9/20011/9/2001PFAIL
DetailsJim Storey
fr insp gene- ###-#### c/n to supply change to steel framing from wood for bearing walls/how to maintane tenent walls at 6 inch pipe colums/ leager atchment/ truss engineering / truss hangers void not instaled per manufactures listing. 1/9/2001 5:13:16 PM
Issue PAID IN FULL permit  12/29/2000 DONE
Print Occupancy Form  12/15/2000 DONE
Inspection Record Card- Bld  12/15/2000 DONE
Telephone call  12/15/2000 DONE
talked to cindy gave dollar amount
Plan Review Completed(1st rev)  12/14/2000 PASS
Routing - PLAN CHECK12/14/2000 12/14/2000 PASS
APPROVED AS NOTED AND PER ATTACHED COMMENTS / CONDITIONS. TO PERMIT DESK FOR ISSUANCE.
PLANS/APPL TAKEN TO FRONT DESK  12/14/2000 PASS
To permit desk for issuance.
Plan assigned to (DRS)9/22/2000 12/14/2000 PASS
DetailsDan Stuart
12/14/2000 15:23:30 DRS - activity updated through activity BLDA022 from case BLD00-02754.
Routing - FIRE12/8/2000 12/12/2000 PASS
approved with conditions.
Routing - PLAN CHECK9/26/2000 12/8/2000 PEND
Approved for Vanilla Finish - NO OCCUPANCY OR USE - No tenant declared with specific occupancy use. Separate application and plans are required for new tenant when declared. Plans will need to be reviewed to verify existing work done meets code and to note any additional requirements for the occupancy use needing to be done before occupancy is approved. SEPARATE APPLICATION, ENGINEERING CALCS AND PLANS SHOWING FULL COMPLIANCE WITH CHAPTER 22, DIV. X, SECTIONS 2222 THRU 2229, VOL. II, 1997 UBC ARE REQUIRED FOR STEEL RACK INSTALLATION & USE AND EVIDENCE OF COMPLIANCE WITH ARTICLE 81 UFC & NFPA #13 FOR HIGH PILED STORAGE w/ SPRINKLER PROTECTION IS REQUIRED.
Routing - PUBLIC WORKS9/22/2000 9/26/2000 PASS
Plan routing begun/TENANTS  9/22/2000 DONE
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  9/18/2000 DONE
Application received  9/15/2000