Fee Review-notes | 6/30/2003 | 6/30/2003 | 6/30/2003 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/23/2002 | | |
|
|
|
|
Fee Review-notes | 9/18/2000 | 9/18/2000 | 12/20/2001 | | DONE |
|
|
|
5/18/01- split permits so had to split value and paid fees. bld01-01286 9/18/00paid 20,048.73 on one permit and should have been 16...split money out on to each permit...lh
|
Telephone call | | | 12/8/2001 | | DONE |
|
|
|
Called and requested letter stating which types of alternates the architect want to use.
|
Permanent occupancy | | | 12/5/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8930 issued 12-5-01 to the Linger Lodge Apts., Bldg. #3, Sec. 1.
|
Permanent Occupancy | | 11/29/2001 | 11/29/2001 | | DONE |
|
|
|
|
BLD-Final | 11/29/2001 | 11/29/2001 | 11/29/2001 | P | PASS |
Russ Owen
|
|
|
JOHN ###-#### ok perm oc. 11/29/2001 2:39:32 PM
|
FIRE-Final Inspection | 11/8/2001 | 11/9/2001 | 11/9/2001 | A | PASS |
Troy Cobbley
|
|
|
Fire/life safety finaled. OK for perm occ 11/9/2001 9:56:24 AM
|
BLD-Final | 11/9/2001 | 11/9/2001 | 11/9/2001 | P | PART |
Russ Owen
|
|
|
JOHN ###-####. ok temp oc c/n posted. 11/9/2001 4:35:30 PM
|
BLD-Aging Inspection | 10/29/2001 | 10/29/2001 | 10/29/2001 | | PART |
Russ Owen
|
|
|
|
BLD-Framing/Rough-in | 8/29/2001 | 8/29/2001 | 8/29/2001 | P | PART |
Russ Owen
|
|
|
###-#### john
|
Print Occupancy Form | | | 8/16/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/16/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/16/2001 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 8/16/2001 | | TEMP |
|
|
|
Temp Approved, Bond posted.
|
Code Occupancy Approval | | | 8/16/2001 | | TEMP |
|
|
|
Temp Approved, Bond Posted.
|
BLD-Framing/Rough-in | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PART |
Russ Owen
|
|
|
bldg #3-John ###-####. soffit areas ok . 8/14/2001 4:24:59 PM
|
BLD-Framing/Rough-in | 8/9/2001 | 8/9/2001 | 8/9/2001 | P | FAIL |
Russ Owen
|
|
|
###-#### john fr insp
|
BLD-Framing/Rough-in | 8/8/2001 | 8/8/2001 | 8/8/2001 | P | NR |
Dave Hannah
|
|
|
###-####
|
BLD-Framing/Rough-in | 7/17/2001 | 7/18/2001 | 7/18/2001 | A | PART |
Tom Arcoraci
|
|
|
###-#### shear wall building 3 shear ok corridors 7/17/2001 11:20:41 PM
|
BLD-Framing/Rough-in | 7/6/2001 | 7/6/2001 | 7/6/2001 | P | FAIL |
Russ Owen
|
|
|
|
BLD-Framing/Rough-in | 6/27/2001 | 6/28/2001 | 6/27/2001 | A | CANC |
Russ Owen
|
|
|
shear wall partial framing Tim ###-####
|
CHANGE STATUS TO (ISS) | | | 6/27/2001 | | |
|
|
|
|
Receive PAYMENT IN FULL | | | 6/27/2001 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 6/5/2001 | 6/5/2001 | 6/5/2001 | A | PASS |
Dave Hannah
|
|
|
Added by Inspector: 425 On 6/5/2001 11:45:59 AM shear panels contractor has letter from engineer for alternate shear panels using sheet rock on inter walls
|
Print Occupancy Form | | | 5/23/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 5/23/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/23/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/23/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 5/23/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/23/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/23/2001 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 5/23/2001 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/23/2001 | | DONE |
|
|
|
|
FIRE-Alarm Testing | 5/18/2001 | 5/21/2001 | 5/21/2001 | A | PASS |
Joe Tawney
|
|
|
###-#### Conf with Lea Elect reg exit signs. Adv not req by code 5/22/2001 10:52:55 AM
|
Override - Parcel Holds | | | 5/18/2001 | | |
|
|
|
|
Plan Reviewer's activity | | | 5/15/2001 | | PASS |
|
|
|
Plan Modification approved.
|
Override - Parcel Holds | | | 5/15/2001 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/15/2001 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/15/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 4/26/2001 | | 5/15/2001 | | PASS |
Mike Phillips
|
|
|
5/15/2001 10:45:42 M_P - activity updated through activity BLDA022 from case BLD00-02769.
|
CHANGE STATUS TO (PND) | | | 4/26/2001 | | DONE |
|
|
|
per kathy miller /pln modification/mls
|
Plans ACCEPTED BY PLAN TECH | | | 4/26/2001 | | DONE |
|
|
|
Plan Modification for Building 3.
|
Received Certificate of Value | | | 4/26/2001 | | DONE |
|
|
|
Plan modification
|
BLD-Footing | 3/27/2001 | 3/28/2001 | 3/28/2001 | A | PART |
Dave Hannah
|
|
|
###-####
|
Plan resubmittals received | | | 2/28/2001 | | DONE |
|
|
|
Received one copy of letter for on site inspector. Put in file. There is a copy of this letter on the job site and on is going to be faxed to Russ Owens.
|
BLD-Foundation | 2/26/2001 | 2/27/2001 | 2/27/2001 | A | PART |
Russ Owen
|
|
|
###-####PORE , OK'D BY STRATA. 2/27/2001 12:04:06 PM,also compaction report .as prior inspection required. 2/27/2001 12:04:37 PM
|
BLD-Footing | 2/16/2001 | 2/16/2001 | 2/16/2001 | P | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/16/2001 at 07:31:19. Contact: ###-####.ok subject to a compaction report for north side garage,talked with contractor at site. 2/20/2001 1:29:23 PM
|
Override - Parcel Holds | | | 2/2/2001 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/2/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/18/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/18/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/17/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/17/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 9/20/2000 | | 1/17/2001 | | PASS |
Mike Phillips
|
|
|
1/17/2001 11:13:20 M_P - activity updated through activity BLDA022 from case BLD00-02769.
|
Routing - PLANNING | 1/8/2001 | 1/8/2001 | 1/9/2001 | | PASS |
|
|
|
Approved per CUP00-00061 & DRH00-00126.
|
Plan Reviewer's activity | | | 12/28/2000 | | FAIL |
|
|
|
Additional information required for further review.
|
Routing - FIRE | 12/27/2000 | 12/27/2000 | 12/27/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 12/18/2000 | 12/18/2000 | 12/27/2000 | | PEND |
|
|
|
took to mike phillips
|
Plan resubmittals received | | | 12/27/2000 | | DONE |
|
|
|
Received five copies of revised sheet FP 1 OF 1. Routed to Bill A. KMM
|
Routing - FIRE | 12/14/2000 | 12/18/2000 | 12/18/2000 | | FAIL |
Bill Alexander
|
|
|
Lack sprinkler water supply design criteria. Lack fire line supply information, taps, size, locations, etc.
|
Routing Off Site - STRUCTURAL | 12/7/2000 | | 12/15/2000 | | DONE |
|
|
|
Contacted PDQ to take resubmitted plans dated 12/4/00 to outside eng. atten. Michael Brown. KMM
|
Plan Reviewer's activity | | | 12/8/2000 | | DONE |
|
|
|
Called and requested additional information. Need code alternate letter and information to review and approve design for alternates.
|
Routing - PUBLIC WORKS | 11/29/2000 | | 12/1/2000 | | PASS |
|
|
|
|
Routing - FIRE | 10/24/2000 | 10/27/2000 | 10/25/2000 | | FAIL |
Bill Alexander
|
|
|
Lack sufficient UFC, UBC related information.
|
Plan Review Completed(1st rev) | | | 10/25/2000 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/26/2000 | | 10/24/2000 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
SECOND REVIEW REQUIRED.
|
Routing - PLAN CHECK | 10/10/2000 | | 10/24/2000 | | |
|
|
|
ROUTING TO FIRE
|
Plan Reviewer's activity | | | 10/24/2000 | | FAIL |
|
|
|
ADDITIONAL INFORMATION REQUIRED FOR FURTHER REVIEW.
|
Routing - PLUMBING | 10/5/2000 | | 10/9/2000 | | PASS |
|
|
|
|
Routing - PLANNING | 10/5/2000 | | 10/5/2000 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 9/28/2000 | | 10/5/2000 | | FAIL |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/28/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/25/2000 | | DONE |
|
|
|
|
Received Certificate of Value | | | 9/25/2000 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/18/2000 | | HOLD |
|
|
|
THERE ARE EIGHT BUILDINGS ON THIS SET OF PLANS THAT WILL REQUIRE EIGHT SEPARATE FOUNDATION PERMITS AND SIXTEEN BUILDING PERMITS. APPLICANT WILL SUBMIT REQUIRED APPLICATIONS. ALSO NO STRUCTURAL CACULATIONS WERE INCLUDED WITH THE PLANS.
|
Application received | | | 9/18/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/18/2000 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/10/2001 | | | | |
|
|
|
|
Routing - PLAN CHECK | 4/26/2001 | | | | |
|
|
|
Plan modification.
|