Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-02787
StatusFinaled
Name ROTH DESIGN/BUILD
Site Address 4108 S BARBER STATION WAY
Project Name 
Customer Number323-2233
ePlanReviewNo
Description
To construct a 2137 sq. ft. two story single family dwelling with a 689 sq. ft. attached two car garage, a 204 sq. ft. covered entry porch and a 172 sq. ft. partially covered concrete patio per approved plans, all engineering/red-lining and attached requirement lists. (1st floor 1352 sq. ft.)(2nd floor 785 sq. ft.) PC #874 CU #98-0116 DJO
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/23/20017/23/20017/23/2001PPASS
DetailsSteven Webb
Terry, ###-#### - late this afternoon C. of C. #20462 issued. 7/23/2001 12:54:53 PM
DOC - Permit Finaled7/23/20017/23/20017/23/2001PPASS
DetailsSteven Webb
Finaled by inspector at 7/23/2001 12:54:59 PM
BLD-Final7/17/20017/18/20017/18/2001AFAIL
DetailsSteven Webb
Terry, ###-#### - code is 9876 enter for access thru garage C/N -- Plumbing final needed. 7/18/2001 10:38:44 AM
BLD-Other7/12/20017/12/20017/12/2001ACANC
DetailsSteven Webb
Added by Inspector: 420 On 7/12/2001 7:56:14 AM
BLD-Other7/12/20017/12/20017/12/2001PFAIL
DetailsSteven Webb
Scheduled by Inspector: 420 On 7/12/2001 1:31:34 PM C/N informing contractor that no c. of c. has been issued--Posted on site. 7/12/2001 1:34:54 PM
BLD-Energy code compliance12/21/200012/21/200012/21/2000PPASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 12/21/2000 at 07:34:40. Contact: ###-####.ok to cover 12/21/2000 3:11:19 PM
BLD-Framing/Rough-in12/20/200012/20/200012/20/2000APART
DetailsSteven Webb
Scheduled by a contractor via Hello! on 12/20/2000 at 07:23:30. Contact: ###-####. c/n issued, ok to insulate, will verity changes at Energy 12/20/2000 10:41:55 AM
BLD-Other12/20/200012/20/200012/20/2000ACANC
DetailsSteven Webb
Scheduled by a contractor via Hello! on 12/20/2000 at 07:28:52. Contact: ###-####. cancel by contractor 12/20/2000 9:24:47 AM
BLD-Framing/Rough-in12/5/200012/5/200012/5/2000APASS
DetailsSteven Webb
Scheduled by a contractor via Hello! on 12/05/2000 at 07:22:16. Contact: ###-####. ok to side, c/n for interior shear posted. 12/5/2000 10:17:26 AM
Issue PAID IN FULL permit  11/21/2000 DONE
Plan assigned to (DJO)10/20/200010/20/200010/25/2000 PASS
DetailsDan Overy
10/25/2000 09:40:54 DJO - activity updated through activity BLDA022 from case BLD00-02787.
Print Pending Permit.LaserJet4  10/25/2000 DONE
Plan Reviewer's activity  10/25/2000 DONE
revised plans received indicating new bearing, roof frame and installation of window from bonus room.
PLANS/APPL TAKEN TO FRONT DESK  10/25/2000 DONE
Inspection Record Card- Bld  10/25/2000 DONE
Telephone call  10/25/2000 DONE
called ###-#### permit ready for pickup
Plans ACCEPTED BY PLAN CHECK  10/20/2000  
Plan Reviewer's activity  10/20/2000 PEND
plans returned to contractor for revisions on 10-20-2000
Plan Review Report  10/20/2000 PEND
BLD-Foundation10/13/200010/13/200010/13/2000PPART
DetailsTony Young
FOUND WALL-- MANA ###-####
WIP, TOLD THEM TO CLEAN UP CONCRETE OFF OF ROAD, OK W/ VERBAL CORRECTIONS 10/13/2000 3:19:27 PM
BLD-Footing10/10/200010/11/200010/11/2000APART
DetailsRuss Owen
FT INSP -MANA ###-####- OR RANDY ###-#### early start appears ok. 10/11/2000 1:28:08 PM
Routing - PUBLIC WORKS9/19/20009/19/200010/10/2000 PASS
Early Start Permit  10/10/2000 DONE
Routing - PLANNING10/9/200010/9/200010/9/2000 PASS
Application received  9/19/2000  
Routing - PLAN CHECK10/10/200010/10/2000  PEND
Pending Assignment by DJO9/19/2000   PEND
DetailsDan Overy
Office Staff conference/action    PASS
Plan Reviewer's activity