Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD00-02793
StatusFinaled
Name YEN CHING RESTAURANT
Site Address 305 N 9TH ST
Project NameYEN CHING
Customer Number 
ePlanReviewNo
Description
(YEN CHING) Remodeling and renovating an existing assembly occupancy (A-3) restaurant and (B) occupancy kitchen/service/office/storage tenant in existing 5,873 sq.ft. building per approved plans on file. Work to include miscellaneous demolition work, upgrading restrooms to meet current accessibility standards, other accessible upgrades, providing new exterior accessible route and new exterior entrance doors, new entry vestibule/waiting area with interior accessible route, windows in northeast one-hour exterior wall to be replaced with 3/4 hour rated wire glass or one-hour wall infill, relocation and new one-hour rated occupancy separation walls and 60 minute rated doors separating the office/storage room/Men's restroom/Women's restroom from the rest of the tenant area, some new interior walls and dividing partitions, new Type II Hood, interior finish changes, suspended ceiling and soffit work, mechanical work, plumbing work including new grease interceptor installation, and electrical work. NOTE: The one-hour rated occupancy separation is required to comply with 1997 UBC Section 904.2.3.1 so restaurant does not require fire sprinklers. (P.C.#757-00) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes1/30/20021/30/20021/30/2002 DONE
Permanent occupancy  1/15/2002 DONE
Perm. Occ. Cert. #8991 issued 1-15-02 to the Yen Ching Restaurant.
BLD-Final1/8/20021/8/20021/8/2002PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 1/8/2002 3:56:48 PM ok for c/o
Permanent Occupancy 1/8/20021/8/2002 DONE
Details
BLD-Final1/3/20021/3/20021/3/2002PNR
DetailsCarl Dependahl
###-#### OR ###-####
BLD-Final12/27/200112/28/200112/28/2001ANR
DetailsCarl Dependahl
###-####; need card onsite 12/28/2001 12:08:57 PM
FIRE-Final Inspection12/21/200112/26/200112/26/2001APASS
DetailsTroy Cobbley
Fire life/safety finaled 12/26/2001 2:30:07 PM
FIRE-Final Inspection12/20/200112/20/200112/20/2001PCANC
DetailsTroy Cobbley
to be rescheduled 12/20/2001 1:37:37 PM
BLD-Aging Inspection11/20/200111/20/200111/26/2001 NR
DetailsCarl Dependahl
keep c/n; wip 11/26/2001 11:40:33 AM
Conference10/5/200110/5/200110/5/2001 DONE
Carl D. said official temp. occ. should have begun on 9-20-01. He & Joe Tawney have correction notice items against this project.
FIRE-Final Inspection9/19/20019/20/20019/20/2001AFAIL
DetailsJoe Tawney
Reinsp Fail Occ separation wall penetrations, Emerg lights in restrooms. manual flush bolt on kitchen exit door 9/20/2001 3:50:22 PM
BLD-Final9/19/20019/20/20019/20/2001PFAIL
DetailsCarl Dependahl
larry ###-#### fn; c/n...dampers, bolt at rear door, ahu shut down...need hvac as built for review, fire issues 9/20/2001 5:21:59 PM
FIRE-Final Inspection9/19/20019/20/20019/19/2001PCANC
DetailsCathy Weisshaupt
already set up
BLD-Framing/Rough-in8/13/20018/14/20018/14/2001PPART
DetailsCarl Dependahl
###-#### rick; grid at rear dining area ok pend elec & hvac 8/14/2001 2:42:51 PM
BLD-Conference8/2/20018/3/20018/3/2001APASS
DetailsCarl Dependahl
###-####/ submit modification for firewall, ok to continue 8/3/2001 11:20:37 AM
BLD-Framing/Rough-in7/30/20018/1/20018/1/2001PPART
DetailsJim Storey
###-#### soffits ok for cover/ fire walls to be recalled for conf. w carl. 8/1/2001 4:45:22 PM
FIRE-Conference7/2/20017/3/20017/3/2001APART
DetailsRick Jackson
###-#### tested extinguishing system - okay 7/3/2001 10:27:27 AM
FIRE-Conference6/29/20016/29/20016/29/2001PNR
DetailsRick Jackson
Rick ###-#### kitchen extinguishing system won't be ready 6/29/2001 10:36:03 AM
Temporary occupancy  6/22/2001 PART
Temp. Occ. Cert. #4561 issused 6-22-01 to the Yen Ching restaurant.
FIRE-Final Inspection6/20/20016/21/20016/21/2001AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/20/2001 at 08:39:29. Contact: ###-####. kitchen extinguishing problems. dave miller will approve temp occ if conditions are met. 6/21/2001 12:51:50 PM
BLD-Final6/20/20016/21/20016/21/2001PFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/20/2001 at 08:41:18. Contact: ###-####. ok for t/o front 1/2...complete work 6/21/2001 5:52:22 PM
BLD-Conference6/21/20016/21/20016/21/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 6/21/2001 9:55:25 AM w/ Rick...need hood upgrade agreement(w/ Dave Miller) for final.
FIRE-Final Inspection6/21/20016/21/20016/21/2001PPART
DetailsRick Jackson
Scheduled by Inspector: 409 On 6/21/2001 12:50:42 PM per dave miller a temp occ approved pending extinguishing system resolution to code 6/21/2001 3:14:25 PM
BLD-Conference6/20/20016/20/20016/20/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 6/20/2001 11:10:52 AM w/ bldr re "partial" final for 1/2 of project...need arch's letter for changes
BLD-Framing/Rough-in6/15/20016/18/20016/18/2001PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 06/15/2001 at 13:12:31. Contact: ###-####. clg grid at front ok per 425 6/18/2001 1:24:26 PM
BLD-Framing/Rough-in6/12/20016/13/20016/13/2001PPART
DetailsCarl Dependahl
Scheduled by Inspector: 408 On 6/12/2001 1:15:25 AM rick ###-#### not ready on tues resced for wed...ok to cover soffit only; resub. for 1hr separation locations(>5000 sf/alcohol/sprinklers) also for a.d.a.ramp at entry...need archs detail or?6/13/2001 6:03:19 PM 6/13/2001 6:04:20 PM
BLD-Framing/Rough-in6/12/20016/12/20016/12/2001PCANC
DetailsTom Arcoraci
Rick ###-####
BLD-Conference5/31/20016/1/20016/1/2001APART
DetailsCarl Dependahl
Rick ###-####...w/ bldr re req'd modification 6/1/2001 2:18:09 PM
BLD-Conference4/25/20014/26/20014/26/2001APASS
DetailsCarl Dependahl
###-####; w/ Rick, supt. for EKC....need to analyze occupancy separation for complete closure; if 1hr wall moved, no dbl acting doors allowed ( from kitchen) 4/26/2001 11:43:29 AM
Issue PAID IN FULL permit  4/17/2001 DONE
Print Pending Permit.LaserJet4  4/2/2001  
Inspection Record Card- Bld  3/19/2001 DONE
Print Occupancy Form  3/19/2001 DONE
Telephone call  1/25/2001 DONE
talked to gwen-will give mess to brian ellsworth -that permit is ready
Print Occupancy Form  11/6/2000 DONE
Inspection Record Card- Bld  11/6/2000 DONE
Telephone call  11/6/2000 DONE
called permit ready
PLANS/APPL TAKEN TO FRONT DESK  11/4/2000 PASS
Plan assigned to (JCB)9/21/2000 11/4/2000 PASS
DetailsJason Blais
11/4/2000 10:15:47 JCB - activity updated through activity BLDA022 from case BLD00-02793.
Routing - PLAN CHECK10/27/2000 11/4/2000 PASS
Permit and plans approved and taken to front desk.
Plan resubmittals received  11/3/2000 DONE
Received plan resubmittals from Cole and Associates, Ryan Drew, two sets of sheets A1.0, A2.0 and A3.0 plus small documents, forwarded same to Jason Blais. 11/3/00 DAR
Routing - FIRE10/24/200010/27/200010/27/2000 DONE
DetailsBill Alexander
On condition UBC related issues are provided and approved.
Plan Review Completed(1st rev)  10/27/2000 FAIL
Routing - PLAN CHECK10/2/2000 10/24/2000 FAIL
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
Plan resubmittals requested  10/24/2000  
Plan resubmittals and response required for further review.
Routing - PLUMBING9/26/2000 10/2/2000 PASS
per plans and 97 upc
Routing - PUBLIC WORKS9/24/2000 9/26/2000 PASS
Routing - PLANNING9/26/2000 9/26/2000 PASS
Marty Santoyo.
Plan routing begun/TENANTS  9/24/2000 DONE
Route to PUBLIC WORKS, PLANNING, PLUMBING, PLAN CHECK and FIRE.
Plans ACCEPTED BY PLAN TECH  9/20/2000 DONE
Received Certificate of Value  9/19/2000 DONE
Application received  9/19/2000  
Recd Pcfee & Taken To Pln CK  9/19/2000 DONE
Recd Pcfee & Taken To Pln CK