Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-02910
StatusFinaled
Name VACANT (COUNTRY SQUARE SHOPPING CNTR)
Site Address 10533 W OVERLAND RD
Project NameCOUNTRY SQUARE SHOPPING CENTER
Customer Number 
ePlanReviewNo
Description
To upgrade to a 2-hr. rated area separation wall to full code compliance and other miscellaneous work in vacant tenant space of an existing shopping center per approved plans on file. The area separation wall is on the west side of this tenant space. This work will bring the allowable area of the shopping center into code compliance. The shopping center was recently annexed into Boise City. Work to include extending area separation parapet wall above roof 30" minimum and extending the wall horizontally to outer edge of existing roof projection, masonry work, epoxy/adhesive anchor installations, new concrete footing under masonry wall extension, two-hour rated interior infill wall in existing overhead door opening in area separation wall, new (3) coat exterior stucco work, upgrading existing draft stops in tenant space to code compliance, some fire sprinkler modifications including alleviating sagging roof insulation so sprinkler heads will not be obstructed, and some electrical work. NOTE: Work requires Special Inspections. NO OCCUPANCY allowed under this permit. A separate permit is required to occupy the space. This is a Scope of Work Permit. Letter of Completion to be issued when done. NOTE: This building has a fire sprinkler system for area increase and the system will require upgrades under separate permits. (P.C.#803-00) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Agreement of Future work2/21/20011/31/200510/1/2004 PASS
DetailsJason Blais
Upgrade work throughout shopping center completed.
DOC - Permit Finaled12/12/200212/12/200212/12/2002APASS
DetailsRuss Owen
Finaled by inspector at 12/12/2002 9:35:23 AM
BLD-Aging Inspection12/11/200212/11/200212/11/2002 CANC
DetailsRuss Owen
DOC - Permit Finaled  12/11/2002 DONE
BLD-Final3/14/20023/14/20023/15/2002PPASS
DetailsRuss Owen
john ###-#### fn occ. Ok finaled perm. 3/15/2002 3:16:15 PM
FIRE-Sprinkler Rough-in3/14/20023/14/20023/14/2002PPASS
DetailsRick Jackson
fire fn -john- ###-####
FIRE-Final Inspection3/14/20023/14/20023/14/2002PPASS
DetailsRick Jackson
john ###-#### fire fn
BLD-Conference3/13/20023/13/20023/13/2002PPART
DetailsRuss Owen
Scheduled by Inspector: 407 On 3/13/2002 11:53:22 AM Nees fire /life safety. 3/13/2002 4:21:24 PM
BLD-Aging Inspection12/19/200112/19/200112/26/2001 PART
DetailsRuss Owen
wip 12/26/2001 9:31:02 AM
BLD-Aging Inspection10/3/200110/3/200110/3/2001 PART
DetailsRuss Owen
will call for inspection soon talked with contractor. 10/5/2001 11:54:23 AM
BLD-Aging Inspection7/23/20017/23/20017/23/2001 PART
DetailsRuss Owen
no inspections called for and no contact number for the permit holder. 7/24/2001 3:41:30 PM
BLD-Aging Inspection5/23/20015/23/20015/23/2001 CANC
DetailsRuss Owen
Issue PAID IN FULL permit  3/28/2001 DONE
BLD-Conference3/23/20013/23/20013/23/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 3/23/2001 9:28:28 AM response to inquiry : insul face paper should be removed,check w/ fire safety re sprinkler placement; area sep. wall to be upgraded per Jason B...grid clg, too.
Routing - PLAN CHECK11/2/2000 3/8/2001  
Permit and plans approved and taken to front desk.
Plan resubmittals received  3/8/2001  
Faxed written response received.
PLANS/APPL TAKEN TO FRONT DESK  3/8/2001 PASS
Print Occupancy Form  3/8/2001 DONE
Inspection Record Card- Bld  3/8/2001 DONE
Telephone call  3/8/2001 DONE
called permit ready
Plan assigned to (JCB)10/6/2000 3/8/2001 PASS
DetailsJason Blais
3/8/2001 09:53:39 JCB - activity updated through activity BLDA022 from case BLD00-02910.
Routing - FIRE10/28/200011/2/200011/2/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  11/2/2000 FAIL
Plan resubmittals requested  10/28/2000  
Written response to plan review required for further review.
Routing - PLAN CHECK10/6/2000 10/28/2000 FAIL
Plan review sent to architect and leasing agent. Written response required for further review. Plans routed to Fire Dept. for review.
Plans ACCEPTED BY PLAN TECH  9/29/2000 DONE
Application received  9/27/2000  
Recd Pcfee & Taken To Pln CK  9/27/2000 DONE