Fee Review-notes | 7/1/2003 | 7/1/2003 | 7/1/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Fee Review-notes | 10/2/2000 | 10/2/2000 | 5/23/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/7/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8669 issued 5-7-01 to Dr. Mark Boerner.
|
Permanent Occupancy | | 4/11/2001 | 4/11/2001 | | DONE |
|
|
|
|
BLD-Final | 4/11/2001 | 4/11/2001 | 4/11/2001 | P | PASS |
Carl Dependahl
|
|
|
###-#### call first to meet there , card not onsite, c/n ok, ok for c/o 4/11/2001 5:04:13 PM
|
BLD-Final | 3/27/2001 | 3/27/2001 | 3/27/2001 | P | CANC |
Jim Sly
|
|
|
###-#### Contractor opted to wait for original inspector to final. 3/27/2001 3:52:08 PM
|
BLD-Final | 3/15/2001 | 3/16/2001 | 3/16/2001 | P | FAIL |
Carl Dependahl
|
|
|
###-#### Walter; need hvac, door closer 3/16/2001 3:39:58 PM
|
FIRE-Final Inspection | 3/14/2001 | 3/15/2001 | 3/15/2001 | P | PASS |
Rick Jackson
|
|
|
###-#### early pm call first to meet there
|
BLD-Final | 3/14/2001 | 3/15/2001 | 3/15/2001 | P | NR |
Carl Dependahl
|
|
|
###-####
|
BLD-Final | 2/21/2001 | 2/23/2001 | 2/23/2001 | P | FAIL |
Carl Dependahl
|
|
|
Walter ###-####..need fire, dampers at ducts 2/23/2001 5:01:49 PM
|
FIRE-Final Inspection | 2/21/2001 | 2/23/2001 | 2/23/2001 | A | FAIL |
Rick Jackson
|
|
|
Walter ###-#### need clarification on duct penetrations at 1 hr walls; need closures on all rated doors; overhead door requires smoke detectors for release 2/23/2001 9:44:12 AM
|
BLD-Framing/Rough-in | 2/14/2001 | 2/15/2001 | 2/15/2001 | P | PART |
Carl Dependahl
|
|
|
ceiling grid ###-#### and a conference add spreader bars, some perimete rwires, ok to tile, chk at final 2/15/2001 3:44:34 PM
|
BLD-Conference | 2/14/2001 | 2/14/2001 | 2/14/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/14/2001 11:31:54 AM w/ Bob Ross re final: may not have roll-down assy in place for final, will consult 325
|
BLD-Framing/Rough-in | 1/16/2001 | 1/18/2001 | 1/18/2001 | P | PART |
Carl Dependahl
|
|
|
###-####, ok to cover walls & 1st layer at floor 1/18/2001 3:51:45 PM
|
Issue PAID IN FULL permit | | | 12/26/2000 | | DONE |
|
|
|
|
Routing - FIRE | 12/4/2000 | 12/7/2000 | 12/6/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan assigned to (JCB) | 10/7/2000 | | 12/6/2000 | | PASS |
Jason Blais
|
|
|
12/6/2000 14:08:05 JCB - activity updated through activity BLDA022 from case BLD00-02964.
|
Plan Review Completed(1st rev) | | | 12/6/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/6/2000 | | 12/6/2000 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/6/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 12/6/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/6/2000 | | DONE |
|
|
|
|
Telephone call | | | 12/6/2000 | | DONE |
|
|
|
TALKED TO BOB HESS TO VERIFY PLANS ARE READY
|
Routing - PLAN CHECK | 12/4/2000 | | 12/4/2000 | | PEND |
|
|
|
Plan review notes sent and faxed to architect. No response required. Permit approval dependent on Fire Dept. approval of plans. Plans routed to Fire Dept.
|
Plan resubmittals received | | | 11/30/2000 | | DONE |
|
|
|
Received two copies of revised sheets A-1, D-1, MEP, one copy of structural calcs. for B1, B2, & floor joists, one copy of cut sheet for Cookson Counter Fire Door. Routed to Jason Blaise. KMM
|
Routing - PLAN CHECK | 10/9/2000 | | 11/8/2000 | | HOLD |
|
|
|
Numerous issues to address, especially with existing exiting system in the building. Met with architect, Bob Hess, in person to discuss several of the issues. He concurred and said that he would address and resubmit new plans. Plans will be held until reviewable plans are submitted.
|
Plan Reviewer's activity | | | 11/8/2000 | | |
|
|
|
Met with architect, Bob Hess, on numerous issues to address with this tenant improvement project. Exiting issues and accessibility issues were among the problems with the project. The architect concurred that there were problems and that he would address and resubmit plans showing code compliance. Plans on hold until new drawings that are reviewable are provided.
|
Routing - PUBLIC WORKS | 10/7/2000 | | 10/9/2000 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/9/2000 | | 10/9/2000 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/3/2000 | | DONE |
|
|
|
|
Application received | | | 10/2/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/2/2000 | | DONE |
|
|
|
|