Permit Information
Permit NumberBLD00-02994
StatusExpired
Name THE BIG EASY (MEZZ EXPANSION)
Site Address 416 S 9TH ST Unit: 106
Project Name9TH STREET WAREHOUSES
Customer Number 
ePlanReviewNo
Description
(THE BIG EASY - MEZZANINE EXPANSION) Fire sprinklers substitute for 1-hr fire-resistive construction of the building. To expand an existing 1,122 square foot mezzanine to 1,696 square feet (574 square foot addition). Work is to include 3" x 10" floor joists, wood beams, and wood floor sheathing for the East expansion. Work is to include concrete footings, steel columns, steel beams, and a concrete floor for the Northwest expansion. All work shall comply with the approved drawings, engineering, and plan review conditions on file. The tenant improvement work (including stairways and guardrails) is under permit BLD00-02658. **CJW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Framing/Rough-in11/9/200011/9/200011/9/2000PPART
DetailsJim Storey
Phil ###-#### east mez floor ok 11/9/2000 4:31:04 PM
BLD-Framing/Rough-in11/9/200011/9/200011/9/2000PPART
DetailsJim Storey
Phil ###-#### east mez floor ok 11/9/2000 4:31:04 PM
Print Occupancy Form  11/9/2000 DONE
Override - Parcel Holds  11/9/2000  
Inspection Record Card- Bld  11/9/2000 DONE
Telephone call  11/9/2000 DONE
called permit ready
Override - Parcel Holds  11/9/2000  
Issue PAID IN FULL permit  11/9/2000 DONE
Override - Parcel Holds  11/9/2000  
Plan assigned to (CJW)10/4/2000 11/8/2000 PASS
DetailsCarl Westfall
11/8/00 15:59:14 CJW - activity updated through activity BLDA022 from case BLD00-02994.
Routing - PLAN CHECK10/4/2000 11/8/2000 PASS
Failed 1st UBC plan review. Passed 2nd review.
Routing Off Site - STRUCTURAL11/3/2000 11/8/2000 PASS
Sent structural caculations to consultanting engineer via PDQ. 11/3/00 DAR
Plan Reviewer's activity  11/8/2000 PASS
Drawings approved, with conditions, after 2nd UBC plan review.
PLANS/APPL TAKEN TO FRONT DESK  11/8/2000 PASS
Plan resubmittals received  11/3/2000 DONE
Received two sets of structural caculations from Armstrong Architects, for warded same to Carl Westfalll. 11/3/00 DAR
Plan Reviewer's activity  10/26/2000  
UBC plan review started October 26, 2000 and finished the next day. A response from the architect is required. See the conditions report.
Plan routing begun/TENANTS  10/4/2000 DONE
ROUTE TO OUTSIDE ENGINEER (CH2M HILL) AND TO PLAN CHECK.
Application received  10/4/2000  
Routing Off Site - STRUCTURAL10/5/2000    
Contacted PDQ to take plans out to outside eng. kmm
Case Summary (BLD)     
Plan Review Report