Case Summary (BLD) | | | 2/1/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 10/8/2002 | | |
|
|
|
|
Permanent Occupancy | | 12/6/2001 | 12/6/2001 | | DONE |
|
|
|
|
BLD-Final | 12/6/2001 | 12/6/2001 | 12/6/2001 | P | PASS |
Tom Arcoraci
|
|
|
Cathy has the card ok for perm occ 12/6/2001 1:53:41 PM
|
Permanent occupancy | | | 12/6/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8943 issued 12-6-01 to the Liberty St. Apts.
|
FIRE-Final Inspection | 8/14/2001 | 8/15/2001 | 8/15/2001 | P | PASS |
Rick Jackson
|
|
|
APRIL ###-#### FIRE FN
|
Temporary occupancy | | | 8/15/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4575 issued 8-15-01 to the Liberty St. Apts.
|
BLD-Final | 8/13/2001 | 8/13/2001 | 8/13/2001 | P | CANC |
Tom Arcoraci
|
|
|
###-#### april ... please call first
|
FIRE-Final Inspection | 8/13/2001 | 8/13/2001 | 8/13/2001 | P | FAIL |
Joe Tawney
|
|
|
april Final Fail Fire Ext and FD acess marking 8/13/2001 4:24:04 PM
|
FIRE-Final Inspection | 8/3/2001 | 8/6/2001 | 8/6/2001 | A | FAIL |
Joe Tawney
|
|
|
Fail plans not on site 8/6/2001 2:05:51 PM
|
FIRE-Final Inspection | 8/3/2001 | 8/3/2001 | 8/3/2001 | P | FAIL |
Joe Tawney
|
|
|
Final Fail Plans not on site 8/3/2001 2:58:52 PM
|
BLD-Final | 8/1/2001 | 8/2/2001 | 8/2/2001 | P | NR |
Tom Arcoraci
|
|
|
###-####
|
Print Occupancy Form | | | 8/2/2001 | | DONE |
|
|
|
|
BLD-Footing | 7/25/2001 | 7/26/2001 | 7/26/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 07/25/2001 at 13:16:10. Contact: ###-####.
|
BLD-Energy code compliance | 5/3/2001 | 5/3/2001 | 5/3/2001 | P | PASS |
Tom Arcoraci
|
|
|
DAryl ###-#### ok to cover 5/3/2001 3:16:01 PM
|
BLD-Framing/Rough-in | 5/1/2001 | 5/1/2001 | 5/1/2001 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### cn issued 5/1/2001 4:34:24 PM
|
BLD-Footing | 1/10/2001 | 1/11/2001 | 1/11/2001 | A | PASS |
Tom Arcoraci
|
|
|
Curtis ###-####
|
Issue PAID IN FULL permit | | | 12/19/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/15/2000 | | DONE |
|
|
|
|
Telephone call | | | 12/15/2000 | | DONE |
|
|
|
called permit ready
|
Plan Reviewer's activity | | | 12/14/2000 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 12/14/2000 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2000 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 12/14/2000 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 10/5/2000 | | 12/14/2000 | | PASS |
Mike Phillips
|
|
|
12/14/2000 14:16:30 M_P - activity updated through activity BLDA022 from case BLD00-02999.
|
Routing - FIRE | 12/13/2000 | 12/13/2000 | 12/13/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 10/26/2000 | | 12/13/2000 | | |
|
|
|
routing to fire
|
Plan Reviewer's activity | | | 12/13/2000 | | PENE |
|
|
|
Waiting for others to approve.
|
Routing - FIRE | 11/24/2000 | 11/29/2000 | 11/30/2000 | | FAIL |
Bill Alexander
|
|
|
Lack FD access and fire flows.
|
Plan Review Completed(1st rev) | | | 11/30/2000 | | FAIL |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 10/31/2000 | | 11/24/2000 | | |
|
|
|
Routing to fire.
|
Plan Reviewer's activity | | | 11/24/2000 | | FAIE |
|
|
|
Additional informaiton required for further review.
|
Routing - PUBLIC WORKS | 10/27/2000 | | 10/31/2000 | | PASS |
|
|
|
|
Routing - PLANNING | 10/25/2000 | | 10/26/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/19/2000 | | 10/25/2000 | | |
|
|
|
Routing to P & Z
|
Plan resubmittals received | | | 10/25/2000 | | DONE |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEET A.1.1 ROUTED TO MIKE P. KMM
|
Routing - PLANNING | 10/11/2000 | | 10/19/2000 | | FAIL |
|
|
|
|
Routing - PLUMBING | 10/19/2000 | | 10/19/2000 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/6/2000 | | 10/19/2000 | | PASS |
|
|
|
No further review required.
|
Routing - PUBLIC WORKS | 10/9/2000 | | 10/11/2000 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN PER BRIAN MURPHY. 10/11/00 DAR
|
Application received | | | 10/3/2000 | | |
|
|
|
|