Plan resubmittals received | | | 7/10/2002 | | DONE |
|
|
|
1 copy of fire flow for 1517 jefferson st from sam rogers, took to carl w. pe
|
Permanent occupancy | | | 7/10/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8749 issued 7-9-01 to K Pearson's.
|
Permanent Occupancy | | 6/4/2001 | 6/4/2001 | | DONE |
|
|
|
|
BLD-Final | 5/24/2001 | 5/24/2001 | 5/24/2001 | P | PASS |
Carl Dependahl
|
|
|
John Wyman ###-####
|
Telephone call | | | 5/22/2001 | | DONE |
|
|
|
Called John Wyman @ ###-#### re: status of temp. occ. - left msg. on voice mail
|
BLD-Final | 5/15/2001 | 5/15/2001 | 5/15/2001 | P | PART |
Carl Dependahl
|
|
|
JOHN ###-####...keep c/n re handrail/landing at rear, p& z ok. 5/15/2001 3:45:21 PM
|
Code Occupancy Approval | | | 5/15/2001 | | PASS |
|
|
|
Inspected today and passed.
|
Fee Review-notes | 10/6/2000 | 10/6/2000 | 4/25/2001 | | DONE |
|
|
|
this permit has all sub
|
Temporary occupancy | | | 4/16/2001 | | PART |
|
|
|
Temp. Occ. Cert. #4535 issued 4-6-01 to Bruce Sackron.
|
BLD-Final | 4/6/2001 | 4/6/2001 | 4/6/2001 | P | FAIL |
Carl Dependahl
|
|
|
JOHN ###-#### FN c/n , complete ext finish, extend / install rails, door hdwe 4/6/2001 2:29:49 PM 4/6/2001 2:30:48 PM
|
Temporary occupancy | | | 4/6/2001 | | PEND |
|
|
|
Temporary occupancy was signed today for DRH00-00194
|
FIRE-Final Inspection | 4/4/2001 | 4/4/2001 | 4/4/2001 | P | PASS |
Rick Jackson
|
|
|
fire fn john ###-#### extinguisehr to be tagged for structural inspector and door hardware at front door 4/4/2001 4:00:11 PM
|
BLD-Energy code compliance | 2/9/2001 | 2/9/2001 | 2/9/2001 | P | PART |
Tony Young
|
|
|
###-####
will blow in walls later, exposed walls ok to cover after caulking sole plate 2/9/2001 2:49:03 PM
|
BLD-Foundation | 2/7/2001 | 2/8/2001 | 2/8/2001 | A | PART |
Carl Dependahl
|
|
|
John Wyman ###-####, ext "ramp" wall 2/8/2001 10:51:52 AM
|
BLD-Framing/Rough-in | 2/7/2001 | 2/8/2001 | 2/8/2001 | A | PART |
Carl Dependahl
|
|
|
t duct 2/8/2001 12:09:21 PM
|
BLD-Footing | 2/7/2001 | 2/7/2001 | 2/7/2001 | P | PASS |
Carl Dependahl
|
|
|
John Wyman ###-#### walkway 2/7/2001 5:02:07 PM
|
Routing Off Site - A.C.H.D | 1/3/2001 | 1/3/2001 | 1/3/2001 | | DONE |
|
|
|
received a.c.h.d. #01-00264/fee of $2,447/mls/1/3/01
|
Issue PAID IN FULL permit | | | 1/3/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/8/2000 | | 12/11/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/11/2000 | | PASS |
|
|
|
|
Print Occupancy Form | | | 12/11/2000 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/11/2000 | | DONE |
|
|
|
|
Telephone call | | | 12/11/2000 | | DONE |
|
|
|
called permit ready
|
Plan assigned to (CJW) | 10/18/2000 | | 12/11/2000 | | PASS |
Carl Westfall
|
|
|
12/11/00 12:47:11 CJW - activity updated through activity BLDA022 from case BLD00-03031.
|
Routing - PLAN CHECK | 11/28/2000 | | 12/8/2000 | | |
|
|
|
Holding until Public Works review can be done.
|
Routing - PUBLIC WORKS | 12/8/2000 | | 12/8/2000 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 11/24/2000 | | 11/27/2000 | | |
|
|
|
Failed 2nd Public Works review. Brian spoke with Eng. Eng. stated that it will be awhile before he has Brian's information. Carl please hold until PW calls for plans. KMM
|
Routing - PLAN CHECK | 11/15/2000 | | 11/22/2000 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 11/21/2000 | | DONE |
|
|
|
Received two copies of revised sheet A2.0 one copy of plan check response letter. Routed to Carl Westfall. KMM
|
Routing - FIRE | 11/14/2000 | | 11/15/2000 | | PASS |
|
|
|
route back to sam rogers. per carl w. pe
|
Routing - PLAN CHECK | 11/13/2000 | | 11/14/2000 | | |
|
|
|
TOOK TO CARL W. PE
|
Routing - FIRE | 11/8/2000 | | 11/13/2000 | | |
|
|
|
Failed first UFC review. FAXED REVIEW TO ARCHITECT
|
Routing - PLAN CHECK | 11/6/2000 | | 11/8/2000 | | |
|
|
|
Drawings failed first review.
|
Plan Reviewer's activity | | | 11/7/2000 | | |
|
|
|
UBC plan review started November 7, 2000 and finished the next day. A response from the architect was required. See the conditions list.
|
Routing - PLANNING | 10/20/2000 | | 11/6/2000 | | PASS |
|
|
|
Please see conditions of approval in DRH00-194.
|
Plan Review Completed(1st rev) | | | 11/3/2000 | | |
|
|
|
Failed first UBC and UFC reviews.
|
Routing - PUBLIC WORKS | 10/18/2000 | | 10/20/2000 | | |
|
|
|
Failed first Public Works review. REQUIRES DRAINAGE PLAN PER BRIAN MURPHY. 10/20/00
|
Pending Assignment by MYS | 10/6/2000 | | 10/18/2000 | | DONE |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/12/2000 | | DONE |
|
|
|
|
Application received | | | 10/6/2000 | | |
|
|
|
|