Permit Information
Permit NumberBLD00-03060
StatusFinaled
Name JERRY TEAL
Site Address 7004 W FAIRVIEW AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
ROSS' VALLEY AUTO SALES - TO CONSTRUCT A NEW 1690 SQ. FT., ONE STORY, AUTO DETAILING SHOP AND AUTO SALES OFFICE BUILDING. THIS BUILDING IS CONSTRUCTED OF MASONRY EXTERIOR WALLS AND WOOD FRAMED ROOF SYSTEM. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. DRH00-00181/PC#852-00/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes10/12/200010/12/20005/24/2001 DONE
Permanent occupancy UNPAID FEE  4/26/2001 DONE
Perm. Occ. Cert. #8648 issued 4-26-01 to Ross' Valley Auto Sales.
FIRE-Final Inspection4/23/20014/24/20014/24/2001PPASS
DetailsJoe Tawney
###-#### Reinap OK for permanant occupancy 4/24/2001 2:50:46 PM
BLD-Final4/23/20014/24/20014/24/2001PPASS
DetailsTom Arcoraci
ok for perm occ 4/24/2001 3:57:06 PM
Code Occupancy Approval  4/24/2001 PASS
20' x 3' juniper hedge was removed as it was displaced with the change in grade and addition of parking lot lights - Planter filled in with junipers. They have 4 arbs in the NW corner instead of 5 and will be adding more plants because they fell this l;ooks pretty sparse. Meets requirements. Signed Final.
Permanent Occupancy 4/23/20014/23/2001 DONE
Details
FIRE-Final Inspection4/20/20014/23/20014/23/2001AFAIL
DetailsJoe Tawney
###-#### Final Fail C/N issued 4/23/2001 12:14:32 PM
FIRE-Final Inspection4/20/20014/20/20014/20/2001PFAIL
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 04/20/2001 at 08:43:14. Contact: ###-####. Final Fail Approved plans not on site 4/20/2001 2:44:20 PM
BLD-Wall cover3/8/20013/8/20013/8/2001PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 03/08/2001 at 07:52:38. Contact: ###-####. wip ok to cover 3/8/2001 3:36:25 PM
BLD-Framing/Rough-in3/5/20013/6/20013/6/2001APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 03/05/2001 at 09:41:48. Contact: ###-####.
BLD-Framing/Rough-in2/26/20012/27/20012/27/2001ACANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 02/26/2001 at 15:16:12. Contact: ###-####.
BLD-Framing/Rough-in2/27/20012/27/20012/27/2001PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 02/27/2001 at 08:41:54. Contact: ###-####. roof nailing ok 2/27/2001 3:25:47 PM
BLD-Other2/19/20012/20/20012/20/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/19/2001 at 08:31:00. Contact: ###-####.appears to be final pour.20/2001 4:51:19 PM 2/20/2001 4:52:10 PM
BLD-Other2/13/20012/13/20012/13/2001PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 02/13/2001 at 08:48:52. Contact: ###-####.
BLD-Other2/8/20012/9/20012/9/2001APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 02/08/2001 at 15:54:11. Contact: ###-####. 2/9/2001 10:33:59 AM Last (lift) Grout pour and (top) bond beam on N, E, and W. walls OK. 2/9/2001 10:36:08 AM
BLD-Other2/6/20012/6/20012/6/2001PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 02/06/2001 at 09:45:25. Contact: ###-####. wip grout pour 2/6/2001 12:41:39 PM
BLD-Other2/2/20012/5/20012/5/2001APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 02/02/2001 at 14:36:05. Contact: ###-####. wip masonary pour 2/5/2001 11:14:36 AM
BLD-Other2/1/20012/2/20012/2/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 02/01/2001 at 13:25:36. Contact: ###-####. ok to grout wip 2/2/2001 11:11:24 AM
(F) Reprint permit  1/31/2001 DONE
Plan resubmittals received  1/18/2001 DONE
Received two copies of revised sheets A2-4, A3-1, A4-1, A4-2, A7-1, A7-4. One copy of structural calculations by Briggs Eng. dated December 19, 2000. One copy of structural calculations by Briggs Eng. dated Jan. 12,2001. One copy of letter dated December 18, from Tempra Wilson. One copy of cover letter. Routed to John M. KMM
BLD-Conference1/17/20011/17/20011/17/2001PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/17/2001 at 10:39:17. Contact: ###-####.
BLD-Conference1/17/20011/17/20011/17/2001PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/17/2001 at 10:39:17. Contact: ###-####.
BLD-Framing/Rough-in1/17/20011/17/20011/17/2001PCANC
DetailsTom Arcoraci
mike ###-####
BLD-Foundation1/11/20011/12/20011/12/2001APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/11/2001 at 12:29:10. Contact: ###-####.
BLD-Footing1/9/20011/10/20011/10/2001PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/09/2001 at 09:58:32. Contact: ###-####.
(F) Reprint permit  1/10/2001 DONE
Issue PAID IN FULL permit  1/8/2001 DONE
Plan resubmittals received  12/19/2000 DONE
Received 5 copies of sheet A2-1, forwarded same to John Menard. 12/19/00 DAR 12/21/00 The five copies of sheet A2-1, and C-1 were denied in plumbing per Bill and Jerry. The issued sets are correct. Jerry T. submitted to us in error. The revised plans should have gone to the bench sewer district. These resubmitted plans of 12/18/00 were thrown out. KMM
Routing - PLAN CHECK12/5/2000 12/11/2000  
Plan resubmittals received  12/11/2000 DONE
Received plan resubmittals three sheets of P-1 from Jerry Teal, forwarded same to John Menard. 12/11/00 DAR
Routing - PLUMBING12/11/2000 12/11/2000 PASS
Routing - PLAN CHECK12/11/2000 12/11/2000 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/11/2000 PASS
Print Occupancy Form  12/11/2000 DONE
Inspection Record Card- Bld  12/11/2000 DONE
Telephone call  12/11/2000 DONE
called permit ready
Plan assigned to (JCM)10/17/2000 12/11/2000 PASS
DetailsJohn Menard
12/11/00 12:00:29 JCM - activity updated through activity BLDA022 from case BLD00-03060.
Routing - PLUMBING11/30/2000 12/5/2000 FAIL
THE FLOOR DRAINAGE IN THE SHOP AREA MUST BE CONNECTED TO AN OIL AND FLAMMABLE LIQUIDS INTERCEPTOR PRIOR TO CONNECTION TO THE SEWER
Routing - FIRE11/28/200011/30/200011/30/2000 PASS
DetailsBill Alexander
Routing - PLAN CHECK11/30/2000 11/30/2000  
Plan Reviewer's activity  11/28/2000 PASS
RESUBMITTED PLANS REVIEWED AND APPROVED AS SUBMITTED. I ALSO REVIEWED AND APPROVED RESUBMITTED STRUCTURAL CALCULATIONS. JCM
Routing - PLAN CHECK11/17/2000 11/28/2000  
Plan resubmittals received  11/27/2000 DONE
Received three copies of revised sheets A1.1, A2.4, A4-1, A4-2, A7-1, M-1, P-1, one copy of response to November 13,2000 plan check report, one copyof respopnse to November 1, 2000 plan review, one copy of response to November 16, 2000 plan review, and one copy of United Water Availabel Volume Information. routed to John M. KMM.
Routing - FIRE11/13/2000 11/17/2000 FAIL
DetailsSam Rogers
Lack hydrant location and flows.
Plan resubmittals requested  11/13/2000 FAIL
MAILED A COPY OF THE COMMENT LIST TO JERRY TEAL REQUESTING REVISIONS. JCM
Routing - PLAN CHECK11/7/2000 11/13/2000  
Routing - PLUMBING11/7/2000 11/7/2000 FAIL
Routing - PUBLIC WORKS11/6/2000 11/7/2000 PASS
Routing - PLANNING10/30/2000 11/6/2000 PASS
Please see approval in DRH00-181
Routing - PUBLIC WORKS10/26/2000 10/30/2000 FAIL
REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. 1/30/00 DAR
Plans ACCEPTED BY PLAN TECH  10/26/2000 DONE
Plan resubmittals received  10/25/2000 DONE
RECEIVED STRUCTURAL ENG. CALCULATION SHEET #2 WITH DESIGN SOIL BEARING HIGHLIGHTED.
DRAINAGE CALCULATIONS FOR ROSS' VALLEY AUTO SALES
DRAINAGE CALCULATIONS FOR THE PREVIEOUS CENTRAL PARK DRIVE-UP FACILITY.
O&M PLAN.
H OCCUPANCY QUESTIONAIRE. ALL FROM JERRY TEAL.
PUT WITH PLANS AND STARTED ROUTING. KMM
DRAINAGE PLANS (TWO SHEETS) FOR CENTRAL PARK DRIVE-UP FACILITY.
Routing Off Site - STRUCTURAL10/17/2000 10/24/2000 FAIL
RECEIVED A FAX FROM THE CONSULTING ENGINEER REQUESTING REVISIONS. JCM
Plan resubmittals requested  10/24/2000  
FAXED JERRY TEAL A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS. JCM
Plan routing begun/NEW & ADDTN  10/17/2000 PEND
WILL ROUTE TO OUTSIDE ENG. HOWEVER AM WAITING FOR O & M MANUAL AND DRAINAGE CALCS. BEFORE SENDING TO PW. KMM
Plans ACCEPTED BY PLAN TECH  10/17/2000 HOLD
REQUIRES 1. O & M MANUAL
2. DRAINAGE CALCULATIONS.
FAXED AND CONTACTED JERRY TEAL. TOLD CANNOT ROUTE UNTIL ITEMS RECEIVED.
10/24/00 CONTACTED JERRY TEAL. HE IS WORKING ON ABOVE ITEMS. KMM
PLANS IN MY HOLD BOX. SENT OUTSIDE ENG. COPY. KMM
Received Certificate of Value  10/12/2000 DONE
Application received  10/12/2000