Letter of compliance | | | 6/27/2002 | | DONE |
|
|
|
Letter of Compliance #22535 issued 6-27-02.
|
BLD-Final | 6/13/2002 | 6/13/2002 | 6/13/2002 | | DONE |
|
|
|
Final - approved/L.C.
|
Temporary occupancy | | | 2/19/2002 | | PART |
|
|
|
Temp. Occ. Cert. #4732 issued 2-19-02 to the Renaissance @ Liberty Lake, Bldg. #17.
|
FIRE-Final Inspection | 2/8/2002 | 2/8/2002 | 2/8/2002 | P | PASS |
Troy Cobbley
|
|
|
Added by Inspector: 430 On 2/8/2002 2:28:23 PM Fire life/safety finaled
|
BLD-Aging Inspection | 1/21/2002 | 1/21/2002 | 1/21/2002 | | PART |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 11/19/2001 | 11/19/2001 | 11/19/2001 | | PART |
Tom Arcoraci
|
|
|
wip 11/20/2001 8:23:46 AM
|
Print Occupancy Form | | | 10/10/2001 | | DONE |
|
|
|
|
BLD-Wall cover | 9/17/2001 | 9/18/2001 | 9/18/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 09/17/2001 at 16:39:01. Contact: ###-####. ok to cover garage 9/18/2001 3:21:01 AM
|
BLD-Wall cover | 7/27/2001 | 7/27/2001 | 7/27/2001 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 07/27/2001 at 07:39:25. Contact: ###-####.
|
BLD-Footing | 6/8/2001 | 6/8/2001 | 6/8/2001 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/08/2001 at 07:21:51. Contact: ###-####.
|
BLD-Footing | 5/17/2001 | 5/18/2001 | 5/18/2001 | A | PASS |
Tom Arcoraci
|
|
|
###-####
|
Issue PAID IN FULL permit | | | 3/15/2001 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/7/2001 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/3/2000 | | 3/6/2001 | | PASS |
Carl Westfall
|
|
|
3/6/01 13:40:06 CJW - activity updated through activity BLDA022 from case BLD00-03078.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2001 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 2/24/2001 | | PASS |
|
|
|
Approved after resubmittal review.
|
Routing - FIRE | 2/14/2001 | 2/20/2001 | 2/21/2001 | | PASS |
Bill Alexander
|
|
|
|
Routing - FIRE | 10/18/2000 | 10/23/2000 | 10/23/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan Review Completed(1st rev) | | | 10/23/2000 | | |
|
|
|
Failed first UBC plan review.
|
Plan Reviewer's activity | | | 10/14/2000 | | |
|
|
|
Failed first UBC plan review. UBC plan review started October 14, 2000 and finished October 16, 2000. A response from the architect was required. See the conditions list.
|
Application received | | | 8/3/2000 | | |
|
|
|
|
Plan Reviewer's activity | | | | | |
|
|
|
See permit BLD00-02250 for routing information.
|