Fee Review-notes | 10/17/2000 | 10/17/2000 | 5/24/2001 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/2/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8657 issued 5-2-01 to Business Psychology in the Lakepointe Centre Bldg. #1, 3rd floor.
|
Permanent Occupancy | | 4/12/2001 | 4/12/2001 | | DONE |
|
|
|
|
BLD-Final | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | PASS |
Jim Storey
|
|
|
Doc ###-#### card on site c/o ok 4/12/2001 2:12:40 PM
|
FIRE-Final Inspection | 2/13/2001 | 2/14/2001 | 2/14/2001 | A | FAIL |
Rick Jackson
|
|
|
###-#### need exit repaired at door 24 and fire alarm test 2/14/2001 4:16:36 PM
|
BLD-Final | 2/13/2001 | 2/14/2001 | 2/14/2001 | P | FAIL |
Jim Storey
|
|
|
###-#### c/n 2/14/2001 4:26:19 PM
|
Issue PAID IN FULL permit | | | 11/20/2000 | | DONE |
|
|
|
|
Routing - FIRE | 11/13/2000 | 11/16/2000 | 11/16/2000 | | PASS |
Bill Alexander
|
|
|
|
Routing - PLAN CHECK | 11/16/2000 | | 11/16/2000 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/16/2000 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 11/16/2000 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/16/2000 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/20/2000 | | 11/16/2000 | | PASS |
Carl Westfall
|
|
|
11/16/00 14:34:54 CJW - activity updated through activity BLDA022 from case BLD00-03096.
|
Routing - PLAN CHECK | 11/8/2000 | | 11/13/2000 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan resubmittals received | | | 11/9/2000 | | |
|
|
|
2 copies EACH drawings A-2 A-3 A-4/ TOOK TO CARL W. 11/9/2000
|
Routing - FIRE | 10/4/2000 | | 11/8/2000 | | FAIL |
Bill Alexander
|
|
|
Failed first review. Require related exit access, certificate of value and infor on existing alarm system or not?
|
Plan Review Completed(1st rev) | | | 11/8/2000 | | |
|
|
|
Failed first UBC and UFC plan reviews.
|
Meeting | | | 11/7/2000 | | |
|
|
|
Met with Stan Cole to work out a solution to the exiting problem from the left office area. He decided to create a 1-hr tenant demising wall to create 2 spaces, each requiring one exit.
|
Routing - PLAN CHECK | 10/20/2000 | | 11/4/2000 | | |
|
|
|
Drawings failed first UBC plan review.
|
Plan Reviewer's activity | | | 11/2/2000 | | |
|
|
|
UBC plan review started November 2, 2000 and finished November 4, 2000. A response from the architect was required. See the conditions list.
|
Pending Assignment by MYS | 10/17/2000 | | 10/20/2000 | | DONE |
Marlene Southard
|
|
|
|
Plan resubmittals received | | | 10/19/2000 | | DONE |
|
|
|
PLAN RESUBMITTALS RECEIVED FROM ERIC PETERSON OF COLE AND ASSOCIATES TWO SETS OF SHEETS A1.0 AND A2.0.10/18/00 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 10/18/2000 | | DONE |
|
|
|
FAXED STAN COLE NOTICE THAT THE PLANS NEED TO BE FULLY DIMENSIONED. 10/18/00 DAR
|
Application received | | | 10/17/2000 | | |
|
|
|
|