Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-03153
StatusFinaled
Name TEMPORARY ACCESS ROAD
Site Address 3201 W AIRPORT WAY
Project NameAIRPORT-GRADING
Customer Number 
ePlanReviewNo
Description
BOISE AIRPORT * TO EXCAVATE , GRADE, AND PAVE A TEMPORARY ACCESS ROADPER ENGINEERED PLANS ON FILE AS APPROVED BY THE PUBLIC WORKS DEPARTMENT. INSTALL CURBING, STRIPING AND LIGHTING AS NOTED ON THE PLANS. NO BUILDINGS TO BE CONSTRUCTED OR INSTALLED UNDER THIS PERMIT.CUP99-00130 DRH99-00206, PC#875-00 DAR
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection6/5/20016/6/20016/6/2001APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 06/05/2001 at 09:55:08. Contact: ###-####.
BLD-Final6/5/20016/6/20016/6/2001APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 06/05/2001 at 09:55:53. Contact: ###-####. final ok pending ele. 6/6/2001 10:36:20 AM
Letter of compliance  6/6/2001 DONE
Letter of Compliance #21520 issued 6-6-01.
Code Occupancy Approval  6/5/2001 PASS
THIS IS A TEMPORARY AREA, NO REAL CONDITIONS NOTED SO FINAL SIGNED OFF.
Issue PAID IN FULL permit  4/9/2001 DONE
(F) Reprint permit  4/9/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  12/19/2000 DONE
Print Pending Permit.LaserJet4  12/19/2000 DONE
Inspection Record Card- Bld  12/19/2000 DONE
Print Occupancy Form  12/19/2000 DONE
Telephone call  12/19/2000 DONE
called Brett Labrie at ###-####
Plan assigned to (DAR)10/23/2000 12/19/2000 PASS
12/19/00 07:44:45 DAR - activity updated through activity BLDA022 from case BLD00-03153.
Routing - FIRE12/14/200012/18/200012/18/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  12/18/2000 PASS
Routing - PLANNING12/12/2000 12/14/2000 PASS
Routing - PUBLIC WORKS10/23/2000 12/12/2000 PASS
Routing - AIRPORT10/24/2000 12/8/2000 PASS
10/26/00 CONTACTED PDQ TO SEND BRIAN M. THREE EXTRA COPIES TO MATT P. KMM
Additional plans submitted  10/23/2000 DONE
Plans ACCEPTED BY PLAN CHECK  10/23/2000 DONE
Application received  10/20/2000  
Routing - PLAN CHECK