Case Summary (BLD) | | | 2/1/2016 | | DONE |
|
|
|
|
Fee Review-notes | 10/24/2000 | 10/24/2000 | 12/20/2001 | | DONE |
|
|
|
check mech
|
Permanent occupancy | | | 12/6/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8938 issued 12-6-01 to the Vine Street Apts.
|
Permanent Occupancy | | 12/4/2001 | 12/4/2001 | | DONE |
|
|
|
|
Temporary occupancy | | | 10/18/2001 | | PART |
|
|
|
Temp. Occ. cert. #4620 issued 10-18-01 to Vine St. Apts.
|
BLD-Final | 10/16/2001 | 10/16/2001 | 10/16/2001 | P | PASS |
Tony Young
|
|
|
###-####
ok for perm. occ. as long as others are ok 10/16/2001 2:02:54 PM
|
FIRE-Final Inspection | 10/2/2001 | 10/3/2001 | 10/3/2001 | A | PASS |
Rick Jackson
|
|
|
###-#### they will have the extinguishers and address installed on Vine st. for structural inspector 10/3/2001 9:36:33 AM
|
BLD-Final | 10/2/2001 | 10/3/2001 | 10/3/2001 | A | FAIL |
Tony Young
|
|
|
###-####
c/n posted 10/3/2001 11:31:19 AM
|
BLD-Final | 10/2/2001 | 10/3/2001 | 10/3/2001 | A | FAIL |
Tony Young
|
|
|
###-####
c/n posted 10/3/2001 11:31:19 AM
|
BLD-Footing | 8/24/2001 | 8/27/2001 | 8/27/2001 | A | CANC |
Tony Young
|
|
|
###-#### wayne--cancel per wayne
|
BLD-Concrete | 8/27/2001 | 8/27/2001 | 8/27/2001 | P | PART |
Tony Young
|
|
|
###-####
holes for carport, wip, ok w/ verbal corrections 8/27/2001 3:47:49 PM
|
BLD-Aging Inspection | 8/6/2001 | 8/6/2001 | 8/6/2001 | | PASS |
Tony Young
|
|
|
wip 8/7/2001 12:23:44 PM
|
BLD-Energy code compliance | 5/30/2001 | 5/31/2001 | 5/31/2001 | A | PASS |
Tony Young
|
|
|
###-####
|
BLD-Framing/Rough-in | 5/25/2001 | 5/25/2001 | 5/25/2001 | P | PASS |
Tony Young
|
|
|
April ###-####
ext. shear ok also 5/25/2001 12:43:50 PM
|
BLD-Energy code compliance | 5/23/2001 | 5/24/2001 | 5/24/2001 | A | NR |
Tony Young
|
|
|
Titan const ###-####
|
BLD-Aging Inspection | 5/16/2001 | 5/16/2001 | 5/16/2001 | | CANC |
Tony Young
|
|
|
This is an aging activity,ok 5/16/2001 8:28:07 AM
|
BLD-Footing | 3/6/2001 | 3/7/2001 | 3/7/2001 | A | FAIL |
Tony Young
|
|
|
Scheduled by Inspector: 415 On 3/6/2001 4:07:44 PM
iterior ftgs still not redone , phone has been busy yesterday and today 3/7/2001 11:51:18 AM
|
BLD-Footing | 3/5/2001 | 3/6/2001 | 3/6/2001 | A | NR |
Tony Young
|
|
|
Duane ###-####
|
Plan resubmittals received | | | 3/5/2001 | | DONE |
|
|
|
Received two copies of revised sheets A2.0, A2.1. Routed to Tony Young. KMM
|
BLD-Footing | 3/2/2001 | 3/2/2001 | 3/2/2001 | P | FAIL |
Tony Young
|
|
|
###-####
interior ftgs. , need to redo per approved plans 3/2/2001 2:01:26 PM
|
Plan resubmittals received | | | 2/9/2001 | | DONE |
|
|
|
Received plan resubmittals from Mark Sanders of Tamura Architectstwio sets of sheets A3.0 and A4.0, forwarded same to Mike Phillips. 2/9/01 DAR
|
BLD-Foundation | 2/8/2001 | 2/8/2001 | 2/8/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/8/2001 10:12:02 AM partial pour back bldg; setting bolts...appears 30" sst bolts used at hd's, watch connections for proper install as bolts actually larger than req'd.
|
BLD-Foundation | 2/6/2001 | 2/7/2001 | 2/7/2001 | P | PART |
Carl Dependahl
|
|
|
###-####
bldg a walls, set back appears ok; ok to set hd bolts. 2/7/2001 5:55:49 PM
|
Issue PAID IN FULL permit | | | 1/31/2001 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/12/2001 | | 1/26/2001 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 1/26/2001 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 1/26/2001 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/26/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/26/2001 | | DONE |
|
|
|
called Mark Sanders at ###-#### ext 203 permit ready for pick up
|
Inspection Record Card- Bld | | | 1/26/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/26/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/26/2001 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 10/23/2000 | | 1/26/2001 | | PASS |
Mike Phillips
|
|
|
1/26/2001 13:38:37 M_P - activity updated through activity BLDA022 from case BLD00-03155.
|
Plan Reviewer's activity | | | 1/23/2001 | | PEND |
|
|
|
Waiting for Record of Survey to be recorded prior to issuing permit.
|
Plan Reviewer's activity | | | 1/22/2001 | | FAIL |
|
|
|
Need density reduction completed.
|
Plan resubmittals received | | | 1/19/2001 | | DONE |
|
|
|
Received two sets of resubmittals from Tamura and Associates, sheets A2.0, A3.0, A4.0, A8.0, A10.0, forwarded same to Mike Phillips. 1/19/01 DAR
|
Routing - FIRE | 1/12/2001 | | 1/12/2001 | | PASS |
|
|
|
satisfactory water info provided.
|
Routing - PLAN CHECK | 12/27/2000 | | 1/9/2001 | | |
|
|
|
|
Routing - PUBLIC WORKS | 1/9/2001 | | 1/9/2001 | | PASS |
|
|
|
|
Routing - FIRE | 12/18/2000 | 12/21/2000 | 12/27/2000 | | FAIL |
Bill Alexander
|
|
|
12/20/00 Fed Exed to Floyd. KMM 12/27/00 Received plans back from Floyd. Routed to fire. KMM
Lack hydrant flow information.
|
Plan Review Completed(1st rev) | | | 12/27/2000 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/7/2000 | | 12/18/2000 | | |
|
|
|
Routing to fire.
|
Plan Reviewer's activity | | | 12/18/2000 | | FAIL |
|
|
|
Additional information required for further review.
|
Routing - PUBLIC WORKS | 11/29/2000 | | 12/7/2000 | | FAIL |
|
|
|
requires drainage plan
|
Routing - PLAN CHECK | 11/17/2000 | | 11/29/2000 | | |
|
|
|
|
Routing - PLUMBING | 11/8/2000 | | 11/17/2000 | | PASS |
|
|
|
provide 1" water service to each apartment, cleanout required on building sewer over 100'.
|
Routing - PLANNING | 10/31/2000 | | 11/8/2000 | | PASS |
|
|
|
Approved subject to revised site plan, landscape plan and building elevations submitted November 7, 2000
|
Routing - PUBLIC WORKS | 10/24/2000 | | 10/31/2000 | | FAIL |
|
|
|
Requires Drainage Plan elements. Per Brian Murphy. KMm
|
Plans ACCEPTED BY PLAN TECH | | | 10/24/2000 | | DONE |
|
|
|
REQUESTED 3 SETS OF CIVIL PLANS FOR GRADING AND DRAINAGE FROM MARK SANDERS. 10/24/00 DAR RECEIVED 3 SETS OF CIVIL PLAN FROM MARK SANDERS. 10/24/00 DAR
|
Application received | | | 10/23/2000 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | | | |
|
|
|
|
Routing - PLAN CHECK | 1/9/2001 | | | | |
|
|
|
|