Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD00-03157
StatusFinaled
Name SCHUNKE DAVID E &
Site Address 1007 N VINE ST
Project NameVINE TERRACE APT.
Customer Number 
ePlanReviewNo
Description
TO CONSTRUCT A NEW 3,896 SQ.FT. TWO STORY, FOUR UNIT APARTMENT BUILDING. THERE ARE TWO UNITS ON EACH FLOOR. THE SECOND FLOOR IS 1.9.22 SQ.FT. AND THE FIRST FLOOR IS 1974 SQ.FT. EACH UNIT IS 873 SQ.FT. WITH A 66 SQ.FT DECK. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST. THIS PERMIT INCLUDES ON SITE LANDSCAPING AND PARKING LOT. CUP00-00083 MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval1/20/20051/20/20051/20/2005 DONE
Finaled without PW approval, no final inspection. Drive-by shows complete 1/20/05 R.Rokovitz
Fee Review-notes7/1/20037/1/20037/1/2003 DONE
Permanent occupancy  12/6/2001 DONE
Perm. Occ. Cert. #8940 issued 12-6-01 to the Vine St. Apts.
Temporary occupancy  11/30/2001 DONE
Temp issued 11/30/01 #4668 to the Vine Terrace Apts.
Code Occupancy Approval11/29/200111/29/200111/29/2001PPASS
DetailsMichael Garner
Added by Inspector: MSG On 11/29/2001 3:08:23 PM I met with the construction company representative, April. We reviewed the letter from Sev Jones allowing the change in the plans, (no dumpster area) - I viewed the property - signed the final occupancy
Permanent Occupancy 11/29/200111/29/2001 DONE
Details
BLD-Final10/16/200110/17/200110/17/2001ACANC
DetailsTony Young
10/16/2001 2:03:49 PM
FIRE-Final Inspection10/16/200110/17/200110/17/2001PPASS
DetailsRick Jackson
###-####
BLD-Final10/17/200110/17/200110/17/2001PPASS
DetailsTony Young
verify trades 10/17/2001 9:51:50 AM
ok if other trades are ok 10/17/2001 2:02:08 PM
BLD-Final10/16/200110/16/200110/16/2001PFAIL
DetailsTony Young
10/16/2001 2:03:41 PM
need trades 10/17/2001 8:22:58 AM
FIRE-Final Inspection10/3/200110/3/200110/3/2001PFAIL
DetailsRick Jackson
###-#### extinguisehrs 10/3/2001 4:22:38 PM
BLD-Final10/3/200110/3/200110/3/2001PFAIL
DetailsTony Young
###-#### temp only
c/n posted w/ other buildings 10/3/2001 3:00:30 PM
BLD-Footing9/6/20019/7/20019/7/2001APART
DetailsTony Young
APRIL-###-####
carport ftgs ok 9/7/2001 9:30:53 AM
BLD-Aging Inspection8/6/20018/6/20018/6/2001 PASS
DetailsTony Young
wip 8/7/2001 12:25:21 PM
BLD-Energy code compliance6/5/20016/6/20016/6/2001APART
DetailsCarl Dependahl
April ###-#### frame ok for cover 6/6/2001 5:00:47 PM
BLD-Energy code compliance6/4/20016/5/20016/5/2001ANR
DetailsTom Arcoraci
April ###-####
BLD-Framing/Rough-in6/1/20016/4/20016/4/2001ANR
DetailsRuss Owen
###-#### no approved plans on site. 1/4/2002 11:04:24 AM
BLD-Framing/Rough-in6/4/20016/4/20016/4/2001PPART
DetailsCarl Dependahl
april ###-#### reinspection; ok to insul...address a/c units at shear walls 6/4/2001 6:02:19 PM
BLD-Foundation5/3/20015/4/20015/4/2001PPASS
DetailsTony Young
###-####must be wrong permit, already poured, along w/ slab 5/4/2001 1:27:23 PM
BLD-Conference4/24/20014/24/20014/24/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 4/24/2001 10:01:47 AM w/ supt. onsitere hold-downs, bolts, etc...consult Simpson if not per specs.
BLD-Footing4/23/20014/23/20014/23/2001PPART
DetailsCarl Dependahl
dwayne ###-####;steel in place, sst bolts onsite, ok to set. Need insulate slab per B.E.C. 4/23/2001 4:52:42 PM
BLD-Footing4/17/20014/18/20014/18/2001APASS
DetailsTony Young
###-####
Issue PAID IN FULL permit  3/21/2001 DONE
Plan Reviewer's activity  3/1/2001 PASS
Print Pending Permit.LaserJet4  3/1/2001 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/1/2001 DONE
Case Summary (BLD)  3/1/2001 DONE
Inspection Record Card- Bld  3/1/2001 DONE
Print Occupancy Form  3/1/2001 DONE
Telephone call  3/1/2001 DONE
Left message w/mark sanders gave dollar amount told him we also needed achd.mps
Routing - PLAN CHECK1/30/2001 3/1/2001 DONE
Plan assigned to (M_P)10/23/2000 3/1/2001 PASS
DetailsMike Phillips
3/1/2001 10:17:25 M_P - activity updated through activity BLDA022 from case BLD00-03157.
Routing - PUBLIC WORKS2/9/2001 2/9/2001 PASS
Routing - FIRE1/25/2001 1/30/2001 PASS
Plan Reviewer's activity  1/25/2001 PENE
Waitng tfor others to approve prior to issuance of permit.
Routing - PLAN CHECK12/28/2000 1/25/2001  
Routing to fire.
Plan resubmittals received  1/24/2001 DONE
received two copies of reviesd sheets A2.0A3.0, A7.0,A8.0 and one copy of letter addressed to Mike P.from John P. Routed to Mike P. KMM
BLD-Framing/Rough-in1/22/20011/22/20011/22/2001PFAIL
DetailsJim Storey
Added by Inspector: 301 On 1/22/2001 4:59:54 PM c/n 1. submital for roof supports not perplan at wall weld plate embeds.
2. s-5.2/11 deck attchment to roof drag angle 6" oc 1/2 dia..
3. grid 20/a typ. tilt slab pannel attchment not complet inside corner detail.
4. must maintane 2hr area wall configration at tilt slab joint splice.
5. grid 18-20 line i missing nuts and one side not welded at wall conection.
6. roof decking weld attchment at wall ledger missing welds 16" oc.
Routing - PUBLIC WORKS12/22/2000 12/28/2000 FAIL
No sewer at indicated tie-in spot. Letter attached to plans. 12/29/00 DAR
Routing - PLAN CHECK12/14/2000 12/22/2000  
Routing - PUBLIC WORKS12/12/2000 12/14/2000 FAIL
Address already assigned to existing house. Jim Rich to obtain legal for new address. KMM
Routing - PLAN CHECK12/4/2000 12/12/2000  
Routing - FIRE11/30/200012/4/200012/4/2000 FAIL
DetailsBill Alexander
Plan Review Completed(1st rev)  12/4/2000 FAIL
DetailsBill Alexander
Routing - PLAN CHECK11/8/2000 11/30/2000  
Routing to fire.
Plan Reviewer's activity  11/30/2000 FAIL
Additional information required for further review.
Routing - PLUMBING11/8/2000 11/8/2000 PASS
Routing - PLUMBING10/27/2000 11/7/2000 FAIL
Routing - PLANNING10/26/2000 10/27/2000 PASS
DetailsTom Curren
Routing - PUBLIC WORKS10/24/2000 10/26/2000 FAIL
REQUIERS DRAINAGE PLAN REVISION ACCORDING TO BRIAN MURPHY. 10/26/00 DAR
Plans ACCEPTED BY PLAN TECH  10/24/2000 DONE
SPOKE WITH MARK ABOUT FIRE HYDRANT LOCATIONS. I COULD NOT FIND THEM. HE IS AWARE. KMM
Received Certificate of Value  10/24/2000 DONE
Plan routing begun/NEW & ADDTN  10/24/2000 DONE
Application received  10/23/2000  
Print Pending Permit.LaserJet4     
Recd Pcfee & Taken To Pln CK     
Print Pending Permit.LaserJet4     
Print Pending Permit.LaserJet4