Case Summary (BLD) | | | 8/12/2010 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/31/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #12-31-01 to the Idaho Athletic Club.
|
Permanent Occupancy | | 12/28/2001 | 12/28/2001 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/27/2001 | 12/28/2001 | 12/28/2001 | A | PASS |
Troy Cobbley
|
|
|
fire fn -- ###-####- kent fire finaled 12/28/2001 8:37:45 AM
|
BLD-Final | 12/21/2001 | 12/26/2001 | 12/26/2001 | A | PART |
Tony Young
|
|
|
###-####
ok for final after other trade inspectors are ok 12/26/2001 10:56:21 AM
|
Telephone call | | | 11/8/2001 | | DONE |
|
|
|
Called Kent & left msg. again re: status of temp. occ.
|
BLD-Aging Inspection | 10/24/2001 | 10/24/2001 | 10/24/2001 | | PART |
Tony Young
|
|
|
wip 10/24/2001 2:30:20 PM
|
Telephone call | | | 10/16/2001 | | DONE |
|
|
|
Talked w/Kent @ ###-#### re: status of occ. He told me they hoped to be completed by 11-15-01.
|
Fee Review-notes | 10/24/2000 | 10/24/2000 | 9/7/2001 | | DONE |
|
|
|
|
BLD-Conference | 8/23/2001 | 8/24/2001 | 8/24/2001 | A | CANC |
Tony Young
|
|
|
|
FIRE-Final Inspection | 8/23/2001 | 8/23/2001 | 8/23/2001 | P | PART |
Joe Tawney
|
|
|
Reinsp OK for temporary occupancy Temp FDC and access road. 2landings at rear of bldg. Fax of alarm signals 8/23/2001 4:45:30 PM
|
BLD-Other | 8/23/2001 | 8/23/2001 | 8/23/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/23/2001 at 07:59:32. Contact: ###-####.final,, ok for temp. occ. 8/24/2001 8:23:27 AM
|
Temporary occupancy | | | 8/23/2001 | | DONE |
|
|
|
Temp. Occ. Cert. #4577 issued 8-23-01 to the Idaho Athletic Club.
|
BLD-Final | 8/21/2001 | 8/22/2001 | 8/22/2001 | A | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/21/2001 at 17:20:40. Contact: ###-####.still need fire sign off, conf. on rest of final 8/22/2001 12:15:49 PM
|
FIRE-Final Inspection | 8/22/2001 | 8/22/2001 | 8/22/2001 | A | FAIL |
Joe Tawney
|
|
|
###-#### Reinsp Fail all issues not resolved 8/22/2001 12:20:40 PM
|
FIRE-Final Inspection | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | NR |
Joe Tawney
|
|
|
Reinsp not ready all issues not resolved 8/21/2001 3:45:00 PM
|
BLD-Final | 8/21/2001 | 8/21/2001 | 8/21/2001 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/21/2001 at 09:34:06. Contact: ###-####.
need trades signed off, misc. other items 8/21/2001 3:49:52 PM
|
BLD-Other | 8/17/2001 | 8/20/2001 | 8/20/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/17/2001 at 17:59:49. Contact: ###-####. met w/ Joe Tawney to go over job,
I had to leave to go to other jobs 8/20/2001 11:44:54 AM
|
FIRE-Final Inspection | 8/19/2001 | 8/20/2001 | 8/20/2001 | A | FAIL |
Joe Tawney
|
|
|
Final Fail Multiple items 8/20/2001 11:54:23 AM
|
BLD-Conference | 8/19/2001 | 8/20/2001 | 8/20/2001 | A | PASS |
Carl Dependahl
|
|
|
meet w/ Tony please 8/19/2001 11:09:33 PM keep c/n, no occupancy til reinsp ok'd by fire 8/20/2001 9:53:00 AM
|
BLD-Final | 8/16/2001 | 8/17/2001 | 8/17/2001 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/16/2001 at 16:23:24. Contact: ###-####.kent 8/17/2001 2:11:12 PM
met w/ 340, c/n posted , DO NOT OCCUPY 8/17/2001 5:03:19 PM
|
BLD-Conference | 8/17/2001 | 8/17/2001 | 8/17/2001 | P | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/17/2001 5:30:58 PM final walk-thru w/ Tony & Petra...c/n issued re exits, fire & other insps not complete, storage below stairs, etc. Partial insp only (to identify life-safety issues.) Phase 1 of project.
|
BLD-Framing/Rough-in | 6/28/2001 | 6/29/2001 | 6/29/2001 | A | PART |
Tony Young
|
|
|
lower south 6/28/2001 9:41:23 AMok to cover lower south 6/29/2001 3:16:23 PM
|
BLD-Framing/Rough-in | 6/27/2001 | 6/28/2001 | 6/28/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 06/27/2001 at 11:05:18. Contact: ###-####.
c/n on fire blocks in stud cavitys w/ combustion, ok to cover lower south area small rooms only 6/28/2001 9:40:15 AM
|
BLD-Framing/Rough-in | 6/1/2001 | 6/11/2001 | 6/11/2001 | A | CANC |
Dave Hannah
|
|
|
6/1/2001 3:28:02 PM
|
BLD-Framing/Rough-in | 6/4/2001 | 6/5/2001 | 6/5/2001 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 06/04/2001 at 15:01:52. Contact: ###-####. WIP 6/5/2001 10:59:56 AM
|
Plan resubmittals received | | | 6/5/2001 | | DONE |
|
|
|
Received two sets of plan resubmittals forwarded same to Tony Young. 6/5/01 DAR
|
BLD-Framing/Rough-in | 5/31/2001 | 6/1/2001 | 6/1/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/31/2001 at 12:11:57. Contact: ###-####.some int. ok, pending elec. on other 6/1/2001 3:28:41 PM
|
BLD-Framing/Rough-in | 5/18/2001 | 5/21/2001 | 5/21/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 05/18/2001 at 14:18:57. Contact: ###-####.
c/n posted, ok after trade sign offs to cover 2nd floor, int. walls 5/21/2001 11:00:58 AM
|
BLD-Concrete | 3/20/2001 | 3/20/2001 | 3/20/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/20/2001 at 07:28:15. Contact: ###-####.
masonary, pending S.I. report 3/20/2001 1:05:50 PM
|
BLD-Concrete | 3/14/2001 | 3/15/2001 | 3/15/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/14/2001 at 17:02:26. Contact: ###-####.
pending S.I. report 3/15/2001 9:45:09 AM
|
BLD-Concrete | 3/13/2001 | 3/14/2001 | 3/14/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/13/2001 at 15:59:50. Contact: ###-####.
pending S.I. report 3/14/2001 10:03:26 AM
|
BLD-Concrete | 3/12/2001 | 3/13/2001 | 3/13/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/12/2001 at 08:40:10. Contact: ###-####.
pending S. I. report 3/13/2001 1:40:59 PM
|
BLD-Concrete | 3/8/2001 | 3/9/2001 | 3/9/2001 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 03/08/2001 at 16:11:30. Contact: ###-####.
|
BLD-Concrete | 3/7/2001 | 3/8/2001 | 3/8/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/07/2001 at 14:58:03. Contact: ###-####.
pending special inspector report 3/8/2001 10:26:48 AM
|
BLD-Concrete | 3/5/2001 | 3/6/2001 | 3/6/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 03/05/2001 at 14:33:41. Contact: ###-####.
masonary, bond beams, plates, wip, ok pending special inspector report 3/6/2001 9:42:36 AM
|
BLD-Concrete | 3/1/2001 | 3/2/2001 | 3/2/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/01/2001 at 20:05:37. Contact: ###-####. masonry, spec. insp onsite...wip. Met w/ new supt. 3/2/2001 9:11:17 AM
|
BLD-Concrete | 2/28/2001 | 3/1/2001 | 3/1/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/28/2001 at 16:17:32. Contact: ###-####.
pending mti report 3/1/2001 9:58:46 AM
|
BLD-Concrete | 2/26/2001 | 2/27/2001 | 2/27/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/26/2001 at 16:01:23. Contact: ###-####.
masonary, pending mti report 2/27/2001 9:44:27 AM
|
BLD-Concrete | 2/23/2001 | 2/26/2001 | 2/26/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/23/2001 at 16:25:16. Contact: ###-####.
bond beam wip, pending special insp. report 2/26/2001 9:30:32 AM
|
FIRE-Hydro test above ground | 2/22/2001 | 2/23/2001 | 2/23/2001 | P | CANC |
Joe Tawney
|
|
|
Cancel should be structural insp 2/26/2001 8:07:40 AM
|
BLD-Foundation | 2/15/2001 | 2/16/2001 | 2/16/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/15/2001 at 17:19:48. Contact: ###-####.
wip, pending special rpt. 2/21/2001 8:35:33 AM
|
BLD-Footing | 2/15/2001 | 2/15/2001 | 2/15/2001 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/15/2001 at 09:04:46. Contact: ###-####.
met w/ kent, new job super, wip ok pending special insp. report, also t/w s. inspector 2/15/2001 3:50:18 PM
|
BLD-Footing | 2/6/2001 | 2/7/2001 | 2/7/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/06/2001 at 12:19:06. Contact: ###-####.
east wall and more int. ftgs., wip, still waiting for survey , pending special inspection report 2/7/2001 11:36:38 AM
|
BLD-Footing | 2/5/2001 | 2/6/2001 | 2/6/2001 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 02/05/2001 at 09:47:44. Contact: ###-####.
special on site, Gary w/ mti// wip, verbal corrections to be taken care of b-4 pour, south and west wall and interior pads pending report from special 2/6/2001 9:47:01 AM
|
BLD-Footing | 1/31/2001 | 2/1/2001 | 2/1/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/31/2001 at 09:43:29. Contact: ###-####. met w/ supt. onsite; need suvey report, all spec. insp's called to city et 2/1/2001 10:11:07 AM c. 2/1/2001 10:11:13 AM
|
BLD-Footing | 1/29/2001 | 1/30/2001 | 1/30/2001 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/29/2001 at 14:43:13. Contact: ###-####. mti report pending...need surveyors statement for p.l. 1/30/2001 9:43:43 AM
|
(F) Reprint permit | | | 1/23/2001 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 10/25/2000 | | 1/22/2001 | | PASS |
John Menard
|
|
|
1/22/01 08:12:17 JCM - activity updated through activity BLDA022 from case BLD00-03185.
|
Routing - PLAN CHECK | 1/22/2001 | | 1/22/2001 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2001 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 1/22/2001 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/22/2001 | | DONE |
|
|
|
|
Telephone call | | | 1/22/2001 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/22/2001 | | DONE |
|
|
|
|
Plan resubmittals received | | | 1/19/2001 | | DONE |
|
|
|
Received plan resubmittals from Cole associates, Two copies of L1.0, forwarded same to John Menard. 1/19/01 DAR
|
Routing - PLANNING | 1/19/2001 | | 1/19/2001 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/16/2001 | | 1/18/2001 | | PASS |
|
|
|
Sent resubmittals to consultating engineer via PDQ. !/16/01 DAR Received an e-mail from the consulting engineer approving the final structural resubmittals. JCM
|
Plan resubmittals received | | | 1/16/2001 | | DONE |
|
|
|
Received three copies of revised sheets S2.1, S4.1, S5.2, S6.1, two copies of additional structural calculations and one copy of responses to the building department comments from AHJ. Routed to John M. KMM
|
Plan resubmittals requested | | | 1/11/2001 | | |
|
|
|
Faxed the architect of record with a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 12/26/2000 | | 1/10/2001 | | FAIL |
|
|
|
Revised drawings from 12/22/00. Received comment letter from consulting engineer requesting additional revisions. JCM
|
Routing - PLANNING | 12/14/2000 | | 12/22/2000 | | FAIL |
|
|
|
Landscape plan has not been revised per DR conditions, specifically the State Street streetscape. Spoke to Stan Cole about this issue, however, the plan has not been changed per phone conversation.
|
Plan resubmittals received | | | 12/22/2000 | | DONE |
|
|
|
Received three copies of revised sheets A2.1, A5.0, A5.1, S1.1, S2.0, S2.1, S2.2, S3.2, S4.1, S4.2, S5.1, S5.2, S6.1. One copy of structural review letter and two copies of revised structural calcs. Routed to John M. KMM
|
Plan Reviewer's activity | | | 12/14/2000 | | PASS |
|
|
|
REVIEWED AND APPROVED RESUBMITTED ARCHITECTURAL PLANS AS SUBMITTED. JCM
|
Routing - PLAN CHECK | 12/8/2000 | | 12/14/2000 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/25/2000 | | 12/11/2000 | | FAIL |
|
|
|
SENT PLANS TO CONSULTING STRUCTURAL ENGINEER VIA PDQ . 10/25/00 DAR RECEIVED A COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER, VIA E-MAIL, REQUESTING REVISIONS. JCM
|
Routing Off Site - STRUCTURAL | 10/30/2000 | | 12/11/2000 | | FAIL |
|
|
|
SENT SOILS REPORT TO CONSULTANTING ENGINEER VIA PDQ.
|
Routing - FIRE | 12/5/2000 | 12/8/2000 | 12/8/2000 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 12/8/2000 | | DONE |
|
|
|
Received plan resubmittals from Cole Architects Civil and Architectural sheets two sets, forwarded same to John Menard. 12/8/00 DAR
|
Plan resubmittals requested | | | 12/8/2000 | | |
|
|
|
FAXED THE ARCHITECT OF RECORD A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS. JCM
|
Plan Review Completed(1st rev) | | | 12/8/2000 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 11/20/2000 | | 12/5/2000 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 12/5/2000 | | |
|
|
|
MAILED MATT RHEESE AT COLE ASSOCIATES A COPY OF THE COMMENT LIST REQUESTING REVISIONS. JCM
|
Plan Reviewer's activity | | | 12/5/2000 | | |
|
|
|
INSERTED REVISED CIVIL PLANS. THESE PLANS ARE TO MATCH THE REVISED PLANS THAT WERE SUBMITTED WITH THE GRADING PACKAGE.
|
Plan resubmittals received | | | 12/1/2000 | | DONE |
|
|
|
Received two copies of revised sheets C1.0, C2.0, C3.0, C4.0, C5.0, C6.0, C7.0, C8.0, C9.0, C10.0 Routed to John Menard. KMM
|
Routing - PUBLIC WORKS | 11/17/2000 | | 11/20/2000 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/15/2000 | | 11/17/2000 | | |
|
|
|
|
Routing - PLUMBING | 11/6/2000 | | 11/15/2000 | | PASS |
|
|
|
|
Plan resubmittals received | | | 11/13/2000 | | DONE |
|
|
|
Received three copies of revised sheets FP1.0, E1.0, E2.0, E2.1, E3.0, E3.1, E4.0, E5.0, E5.1, P0.0, P0.1, P1.0, P1.1, P1.2, P1.3, P2.0, M0.0, M0.1, M1.0, M1.1, M1.2, M2.0, M3.0, from Petra ( Michael Nigh). Routed to John Menard. KMM
|
Plan Reviewer's activity | | | 11/13/2000 | | |
|
|
|
INSERTED SUBMITTED PLUMBING, MECHANICAL AND ELECTRICAL PLANS AND RETURNED PLANS TO PLUMIBING FOR REVIEW. JCM
|
Routing - PLANNING | 10/31/2000 | | 11/6/2000 | | FAIL |
Martin Santoyo
|
|
|
Passed CU per Scott S. Failed DR per Marty.
|
Routing - PUBLIC WORKS | 10/25/2000 | | 10/31/2000 | | FAIL |
|
|
|
Architect to supply a full set of plumbing of plumbing plans for sewer review Per Louise Waldorf. Also to have developer return signed copy of Flood Control Agreement Letter prior to release of plans. per Jim Wylie. 10/31/00 DAR
|
Plans ACCEPTED BY PLAN TECH | | | 10/25/2000 | | DONE |
|
|
|
ARCHITECT ADVISED THAT GEOOTECH ENGINEERING REPORT REQUIRED AS DESIGN BEARING PRESSURE IS OVER 1,500 PSF. ALSO A COMPLETE LEGAL DESCRIPTION AND STAMPED AND SIGNED MECHANICAL AND PLUMBING PLANS ARE REQUIRED TO BE SUBMITTED. 10/25/00 DAR 10/27/00 RECEIVED GEOTECH REPORT FROM COLE AND ASSOCIATES.
|
Application received | | | 10/24/2000 | | |
|
|
|
|
Routing - PLAN CHECK | 12/22/2000 | | | | |
|
|
|
|