Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD00-03185
StatusFinaled
Name IDAHO ATHLETIC CLUB (PHASE I)
Site Address 2999 N LAKEHARBOR LN
Project NameIDAHO ATHLETIC CLUB
Customer Number 
ePlanReviewNo
Description
IDAHO ATHLETIC CLUB - TO CONSTRUCT A NEW 29,400 SQ. FT., TWO STORY, ATHLETIC CLUB BUILDING CONSTRUCTED OF MASONRY EXTERIOR WALLS, CONCRETE FLOORS AND STEEL STRUCTURAL ROOF FRAMING WITH METAL ROOF DECK. THIS PERMIT ALSO INCLUDES RELATED SITE IMPROVEMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED COMMENT LIST. THIS BUILDING IS FULLY FIRE SPRINKLED. THE SPRINKLERS ARE USED FOR ONE-HOUR CONSTRUCTION SUBSTITUTION. THIS IS THE FIRST PHASE OF A PROPOSED THREE PHASE BUILDING PROJECT. THIS BUILDING PHASE CONTAINS RACQUET BALL COURTS, EXERCISE AREAS, LOCKERS, RESTROOMS AND OFFICE AREAS. FIRST FLOOR: 14,850 SQ. FT., SECOND FLOOR: 14,550 SQ. FT.. DRH00-00117/CUP00-00060/PC#888-00/JCM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  8/12/2010 DONE
Permanent occupancy  12/31/2001 DONE
Perm. Occ. Cert. #12-31-01 to the Idaho Athletic Club.
Permanent Occupancy 12/28/200112/28/2001 DONE
Details
FIRE-Final Inspection12/27/200112/28/200112/28/2001APASS
DetailsTroy Cobbley
fire fn -- ###-####- kent fire finaled 12/28/2001 8:37:45 AM
BLD-Final12/21/200112/26/200112/26/2001APART
DetailsTony Young
###-####
ok for final after other trade inspectors are ok 12/26/2001 10:56:21 AM
Telephone call  11/8/2001 DONE
Called Kent & left msg. again re: status of temp. occ.
BLD-Aging Inspection10/24/200110/24/200110/24/2001 PART
DetailsTony Young
wip 10/24/2001 2:30:20 PM
Telephone call  10/16/2001 DONE
Talked w/Kent @ ###-#### re: status of occ. He told me they hoped to be completed by 11-15-01.
Fee Review-notes10/24/200010/24/20009/7/2001 DONE
BLD-Conference8/23/20018/24/20018/24/2001ACANC
DetailsTony Young
FIRE-Final Inspection8/23/20018/23/20018/23/2001PPART
DetailsJoe Tawney
Reinsp OK for temporary occupancy Temp FDC and access road. 2landings at rear of bldg. Fax of alarm signals 8/23/2001 4:45:30 PM
BLD-Other8/23/20018/23/20018/23/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 08/23/2001 at 07:59:32. Contact: ###-####.final,, ok for temp. occ. 8/24/2001 8:23:27 AM
Temporary occupancy  8/23/2001 DONE
Temp. Occ. Cert. #4577 issued 8-23-01 to the Idaho Athletic Club.
BLD-Final8/21/20018/22/20018/22/2001AFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 08/21/2001 at 17:20:40. Contact: ###-####.still need fire sign off, conf. on rest of final 8/22/2001 12:15:49 PM
FIRE-Final Inspection8/22/20018/22/20018/22/2001AFAIL
DetailsJoe Tawney
###-#### Reinsp Fail all issues not resolved 8/22/2001 12:20:40 PM
FIRE-Final Inspection8/21/20018/21/20018/21/2001PNR
DetailsJoe Tawney
Reinsp not ready all issues not resolved 8/21/2001 3:45:00 PM
BLD-Final8/21/20018/21/20018/21/2001PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 08/21/2001 at 09:34:06. Contact: ###-####.
need trades signed off, misc. other items 8/21/2001 3:49:52 PM
BLD-Other8/17/20018/20/20018/20/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 08/17/2001 at 17:59:49. Contact: ###-####. met w/ Joe Tawney to go over job,
I had to leave to go to other jobs 8/20/2001 11:44:54 AM
FIRE-Final Inspection8/19/20018/20/20018/20/2001AFAIL
DetailsJoe Tawney
Final Fail Multiple items 8/20/2001 11:54:23 AM
BLD-Conference8/19/20018/20/20018/20/2001APASS
DetailsCarl Dependahl
meet w/ Tony please 8/19/2001 11:09:33 PM keep c/n, no occupancy til reinsp ok'd by fire 8/20/2001 9:53:00 AM
BLD-Final8/16/20018/17/20018/17/2001PFAIL
DetailsTony Young
Scheduled by a contractor via Hello! on 08/16/2001 at 16:23:24. Contact: ###-####.kent 8/17/2001 2:11:12 PM
met w/ 340, c/n posted , DO NOT OCCUPY 8/17/2001 5:03:19 PM
BLD-Conference8/17/20018/17/20018/17/2001PFAIL
DetailsCarl Dependahl
Added by Inspector: 340 On 8/17/2001 5:30:58 PM final walk-thru w/ Tony & Petra...c/n issued re exits, fire & other insps not complete, storage below stairs, etc. Partial insp only (to identify life-safety issues.) Phase 1 of project.
BLD-Framing/Rough-in6/28/20016/29/20016/29/2001APART
DetailsTony Young
lower south 6/28/2001 9:41:23 AMok to cover lower south 6/29/2001 3:16:23 PM
BLD-Framing/Rough-in6/27/20016/28/20016/28/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 06/27/2001 at 11:05:18. Contact: ###-####.
c/n on fire blocks in stud cavitys w/ combustion, ok to cover lower south area small rooms only 6/28/2001 9:40:15 AM
BLD-Framing/Rough-in6/1/20016/11/20016/11/2001ACANC
DetailsDave Hannah
6/1/2001 3:28:02 PM
BLD-Framing/Rough-in6/4/20016/5/20016/5/2001APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 06/04/2001 at 15:01:52. Contact: ###-####. WIP 6/5/2001 10:59:56 AM
Plan resubmittals received  6/5/2001 DONE
Received two sets of plan resubmittals forwarded same to Tony Young. 6/5/01 DAR
BLD-Framing/Rough-in5/31/20016/1/20016/1/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 05/31/2001 at 12:11:57. Contact: ###-####.some int. ok, pending elec. on other 6/1/2001 3:28:41 PM
BLD-Framing/Rough-in5/18/20015/21/20015/21/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 05/18/2001 at 14:18:57. Contact: ###-####.
c/n posted, ok after trade sign offs to cover 2nd floor, int. walls 5/21/2001 11:00:58 AM
BLD-Concrete3/20/20013/20/20013/20/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 03/20/2001 at 07:28:15. Contact: ###-####.
masonary, pending S.I. report 3/20/2001 1:05:50 PM
BLD-Concrete3/14/20013/15/20013/15/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 03/14/2001 at 17:02:26. Contact: ###-####.
pending S.I. report 3/15/2001 9:45:09 AM
BLD-Concrete3/13/20013/14/20013/14/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 03/13/2001 at 15:59:50. Contact: ###-####.
pending S.I. report 3/14/2001 10:03:26 AM
BLD-Concrete3/12/20013/13/20013/13/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 03/12/2001 at 08:40:10. Contact: ###-####.
pending S. I. report 3/13/2001 1:40:59 PM
BLD-Concrete3/8/20013/9/20013/9/2001APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 03/08/2001 at 16:11:30. Contact: ###-####.
BLD-Concrete3/7/20013/8/20013/8/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 03/07/2001 at 14:58:03. Contact: ###-####.
pending special inspector report 3/8/2001 10:26:48 AM
BLD-Concrete3/5/20013/6/20013/6/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 03/05/2001 at 14:33:41. Contact: ###-####.
masonary, bond beams, plates, wip, ok pending special inspector report 3/6/2001 9:42:36 AM
BLD-Concrete3/1/20013/2/20013/2/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 03/01/2001 at 20:05:37. Contact: ###-####. masonry, spec. insp onsite...wip. Met w/ new supt. 3/2/2001 9:11:17 AM
BLD-Concrete2/28/20013/1/20013/1/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 02/28/2001 at 16:17:32. Contact: ###-####.
pending mti report 3/1/2001 9:58:46 AM
BLD-Concrete2/26/20012/27/20012/27/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 02/26/2001 at 16:01:23. Contact: ###-####.
masonary, pending mti report 2/27/2001 9:44:27 AM
BLD-Concrete2/23/20012/26/20012/26/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 02/23/2001 at 16:25:16. Contact: ###-####.
bond beam wip, pending special insp. report 2/26/2001 9:30:32 AM
FIRE-Hydro test above ground2/22/20012/23/20012/23/2001PCANC
DetailsJoe Tawney
Cancel should be structural insp 2/26/2001 8:07:40 AM
BLD-Foundation2/15/20012/16/20012/16/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 02/15/2001 at 17:19:48. Contact: ###-####.
wip, pending special rpt. 2/21/2001 8:35:33 AM
BLD-Footing2/15/20012/15/20012/15/2001PPART
DetailsTony Young
Scheduled by a contractor via Hello! on 02/15/2001 at 09:04:46. Contact: ###-####.
met w/ kent, new job super, wip ok pending special insp. report, also t/w s. inspector 2/15/2001 3:50:18 PM
BLD-Footing2/6/20012/7/20012/7/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 02/06/2001 at 12:19:06. Contact: ###-####.
east wall and more int. ftgs., wip, still waiting for survey , pending special inspection report 2/7/2001 11:36:38 AM
BLD-Footing2/5/20012/6/20012/6/2001APART
DetailsTony Young
Scheduled by a contractor via Hello! on 02/05/2001 at 09:47:44. Contact: ###-####.
special on site, Gary w/ mti// wip, verbal corrections to be taken care of b-4 pour, south and west wall and interior pads pending report from special 2/6/2001 9:47:01 AM
BLD-Footing1/31/20012/1/20012/1/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 01/31/2001 at 09:43:29. Contact: ###-####. met w/ supt. onsite; need suvey report, all spec. insp's called to city et 2/1/2001 10:11:07 AM c. 2/1/2001 10:11:13 AM
BLD-Footing1/29/20011/30/20011/30/2001APART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 01/29/2001 at 14:43:13. Contact: ###-####. mti report pending...need surveyors statement for p.l. 1/30/2001 9:43:43 AM
(F) Reprint permit  1/23/2001 DONE
Plan assigned to (JCM)10/25/2000 1/22/2001 PASS
DetailsJohn Menard
1/22/01 08:12:17 JCM - activity updated through activity BLDA022 from case BLD00-03185.
Routing - PLAN CHECK1/22/2001 1/22/2001 PASS
PLANS/APPL TAKEN TO FRONT DESK  1/22/2001 PASS
Inspection Record Card- Bld  1/22/2001 DONE
Print Occupancy Form  1/22/2001 DONE
Telephone call  1/22/2001 DONE
Issue PAID IN FULL permit  1/22/2001 DONE
Plan resubmittals received  1/19/2001 DONE
Received plan resubmittals from Cole associates, Two copies of L1.0, forwarded same to John Menard. 1/19/01 DAR
Routing - PLANNING1/19/2001 1/19/2001 PASS
Routing Off Site - STRUCTURAL1/16/2001 1/18/2001 PASS
Sent resubmittals to consultating engineer via PDQ. !/16/01 DAR Received an e-mail from the consulting engineer approving the final structural resubmittals. JCM
Plan resubmittals received  1/16/2001 DONE
Received three copies of revised sheets S2.1, S4.1, S5.2, S6.1, two copies of additional structural calculations and one copy of responses to the building department comments from AHJ. Routed to John M. KMM
Plan resubmittals requested  1/11/2001  
Faxed the architect of record with a copy of the comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL12/26/2000 1/10/2001 FAIL
Revised drawings from 12/22/00. Received comment letter from consulting engineer requesting additional revisions. JCM
Routing - PLANNING12/14/2000 12/22/2000 FAIL
Landscape plan has not been revised per DR conditions, specifically the State Street streetscape. Spoke to Stan Cole about this issue, however, the plan has not been changed per phone conversation.
Plan resubmittals received  12/22/2000 DONE
Received three copies of revised sheets A2.1, A5.0, A5.1, S1.1, S2.0, S2.1, S2.2, S3.2, S4.1, S4.2, S5.1, S5.2, S6.1. One copy of structural review letter and two copies of revised structural calcs. Routed to John M. KMM
Plan Reviewer's activity  12/14/2000 PASS
REVIEWED AND APPROVED RESUBMITTED ARCHITECTURAL PLANS AS SUBMITTED. JCM
Routing - PLAN CHECK12/8/2000 12/14/2000  
Routing Off Site - STRUCTURAL10/25/2000 12/11/2000 FAIL
SENT PLANS TO CONSULTING STRUCTURAL ENGINEER VIA PDQ . 10/25/00 DAR RECEIVED A COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER, VIA E-MAIL, REQUESTING REVISIONS. JCM
Routing Off Site - STRUCTURAL10/30/2000 12/11/2000 FAIL
SENT SOILS REPORT TO CONSULTANTING ENGINEER VIA PDQ.
Routing - FIRE12/5/200012/8/200012/8/2000 PASS
DetailsBill Alexander
Plan resubmittals received  12/8/2000 DONE
Received plan resubmittals from Cole Architects Civil and Architectural sheets two sets, forwarded same to John Menard. 12/8/00 DAR
Plan resubmittals requested  12/8/2000  
FAXED THE ARCHITECT OF RECORD A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS. JCM
Plan Review Completed(1st rev)  12/8/2000 FAIL
Routing - PLAN CHECK11/20/2000 12/5/2000 FAIL
Plan resubmittals requested  12/5/2000  
MAILED MATT RHEESE AT COLE ASSOCIATES A COPY OF THE COMMENT LIST REQUESTING REVISIONS. JCM
Plan Reviewer's activity  12/5/2000  
INSERTED REVISED CIVIL PLANS. THESE PLANS ARE TO MATCH THE REVISED PLANS THAT WERE SUBMITTED WITH THE GRADING PACKAGE.
Plan resubmittals received  12/1/2000 DONE
Received two copies of revised sheets C1.0, C2.0, C3.0, C4.0, C5.0, C6.0, C7.0, C8.0, C9.0, C10.0 Routed to John Menard. KMM
Routing - PUBLIC WORKS11/17/2000 11/20/2000 PASS
Routing - PLAN CHECK11/15/2000 11/17/2000  
Routing - PLUMBING11/6/2000 11/15/2000 PASS
Plan resubmittals received  11/13/2000 DONE
Received three copies of revised sheets FP1.0, E1.0, E2.0, E2.1, E3.0, E3.1, E4.0, E5.0, E5.1, P0.0, P0.1, P1.0, P1.1, P1.2, P1.3, P2.0, M0.0, M0.1, M1.0, M1.1, M1.2, M2.0, M3.0, from Petra ( Michael Nigh). Routed to John Menard. KMM
Plan Reviewer's activity  11/13/2000  
INSERTED SUBMITTED PLUMBING, MECHANICAL AND ELECTRICAL PLANS AND RETURNED PLANS TO PLUMIBING FOR REVIEW. JCM
Routing - PLANNING10/31/2000 11/6/2000 FAIL
DetailsMartin Santoyo
Passed CU per Scott S. Failed DR per Marty.
Routing - PUBLIC WORKS10/25/2000 10/31/2000 FAIL
Architect to supply a full set of plumbing of plumbing plans for sewer review Per Louise Waldorf. Also to have developer return signed copy of Flood Control Agreement Letter prior to release of plans. per Jim Wylie. 10/31/00 DAR
Plans ACCEPTED BY PLAN TECH  10/25/2000 DONE
ARCHITECT ADVISED THAT GEOOTECH ENGINEERING REPORT REQUIRED AS DESIGN BEARING PRESSURE IS OVER 1,500 PSF. ALSO A COMPLETE LEGAL DESCRIPTION AND STAMPED AND SIGNED MECHANICAL AND PLUMBING PLANS ARE REQUIRED TO BE SUBMITTED. 10/25/00 DAR 10/27/00 RECEIVED GEOTECH REPORT FROM COLE AND ASSOCIATES.
Application received  10/24/2000  
Routing - PLAN CHECK12/22/2000