Permit Information
Permit NumberBLD00-03231
StatusFinaled
Name ALASKA AIRLINES
Site Address 1399 W EAGLE FLIGHT WAY
Project NameWHITETAIL PLACE
Customer Number 
ePlanReviewNo
Description
New tenant to occupy a 14,433 sq. ft. shell building (done under BLD00-01836) for (B) office use with assembly (A-3) training room and accessory assembly (A-3) lunch room per approved plans on file. Work to include new accessible restrooms, new unisex accessible bathing/toilet room, new interior walls with doors and windows, draft stop installation, structural support (steel beam/columns) for operable partition in training room, interior finish, new suspended ceiling, fire sprinkler/alarm work, new mechanical, new plumbing, and new electrical work. NOTE: This building is fully fire sprinklered. (PC# 907-00) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes10/30/200010/30/20004/18/2001 DONE
Permanent occupancy UNPAID FEE  3/22/2001 DONE
Perm. Occ. Cert. #8603 issued 3-22-01 to Alaska Airlines.
Permanent Occupancy 3/21/20013/21/2001 DONE
Details
BLD-Final3/20/20013/21/20013/21/2001APASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 03/20/2001 at 16:45:34. Contact: ###-####.ok perm oc. 3/21/2001 1:08:55 PM
DOC - Permit Finaled3/21/20013/21/20013/21/2001PPASS
DetailsRuss Owen
Added by Inspector: 407 On 3/21/2001 1:10:54 PM
BLD-Final3/14/20013/15/20013/15/2001ANR
DetailsRuss Owen
Scheduled by a contractor via Hello! on 03/14/2001 at 13:15:37. Contact: ###-####.still needs items addressed by prior inspection s-i final letter and structural engineer. all other perm- oc have signed card ok. 3/15/2001 11:04:16 AM
BLD-Final2/21/20012/20/20012/20/2001PPASS
DetailsJoe Tawney
Added by Inspector: 406 On 2/21/2001 8:24:27 AM Reinsp ok for permanant occupancy

BLD-Final2/1/20012/2/20012/2/2001APART
DetailsRuss Owen
Scheduled by a contractor via Hello! on 02/01/2001 at 17:02:19. Contact: ###-####.ok for temp oc. 2/2/2001 11:14:52 AM
FIRE-Final Inspection2/1/20012/1/20012/1/2001PPART
DetailsRick Jackson
###-#### temp occ until alarms complete for shell; duct detectors not tested 2/1/2001 4:12:50 PM
FIRE-Conference1/23/20011/24/20011/24/2001APART
DetailsJoe Tawney
j c ###-#### fire conference Conf with JC on spklr monitoring 1/24/2001 1:23:53 PM
BLD-Other1/17/20011/17/20011/17/2001PPASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 01/17/2001 at 09:10:57. Contact: ###-####.ceiling grid.ok to tile. 1/17/2001 2:55:17 PM
BLD-Other1/17/20011/17/20011/17/2001PPASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 01/17/2001 at 09:10:57. Contact: ###-####.ceiling grid.ok to tile. 1/17/2001 2:55:17 PM
FIRE-Conference12/14/200012/15/200012/15/2000PPART
DetailsJoe Tawney
###-####. Conf regarding location of fire ext 12/17/2000 8:32:08 PM
BLD-Framing/Rough-in12/13/200012/14/200012/14/2000AFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 12/13/2000 at 15:55:41. Contact: ###-####.need approved plans and plumbing inspection,ele has ok. 12/14/2000 11:00:38 AM
BLD-Energy code compliance12/13/200012/14/200012/14/2000AFAIL
DetailsRuss Owen
Scheduled by a contractor via Hello! on 12/13/2000 at 16:01:47. Contact: ###-####.
BLD-Framing/Rough-in12/14/200012/14/200012/14/2000PPASS
DetailsRuss Owen
Scheduled by a contractor via Hello! on 12/14/2000 at 11:25:25. Contact: ###-####.
PLANS/APPL TAKEN TO FRONT DESK  11/21/2000 PASS
Print Occupancy Form  11/21/2000 DONE
Inspection Record Card- Bld  11/21/2000 DONE
Telephone call  11/21/2000 DONE
called permit ready
Plan assigned to (JCB)10/30/2000 11/21/2000 PASS
DetailsJason Blais
11/21/2000 08:59:02 JCB - activity updated through activity BLDA022 from case BLD00-03231.
Routing - PLAN CHECK11/3/2000 11/21/2000 PASS
Plans and permit approved and taken to front desk.
Plan resubmittals received  11/20/2000  
Written response from structural engineer provided.
Plan resubmittals received  11/9/2000 DONE
Received two copies of revised sheets G-0, A-100, A-101, A-103, A0200, A-502, A-600, copy of revised cert. of value, two copies of struct. calc. Routed to Jason.
Routing - FIRE11/2/200011/4/200011/3/2000 PASS
DetailsBill Alexander
Plan Review Completed(1st rev)  11/3/2000 FAIL
Routing - PLAN CHECK11/1/2000 11/2/2000 FAIL
Plan review report sent and faxed to architect. Plan resubmittals and response required for further review. Plans routed to Fire Dept. for review.
Plan resubmittals requested  11/2/2000  
Plan resubmittals and response required for further review.
Routing - PUBLIC WORKS10/30/2000 11/1/2000 PASS
Plan Reviewer's activity  10/30/2000 DONE
PARTIAL PERMIT ISSUED AT THE REQUEST OF THE CONTRACTOR. THIS JOB IS A PRIORITY JOB AS DESIGNATED BY J. JONES.
Early Start Permit  10/30/2000 DONE
Telephone call  10/30/2000 DONE
called Jerry Frank at ###-#### partial permit ready for pickup
Plans ACCEPTED BY PLAN TECH  10/30/2000 DONE
Pending Assignment by MYS10/30/2000 10/30/2000 DONE
DetailsMarlene Southard
Application received  10/30/2000  
Recd Pcfee & Taken To Pln CK     
Issue PAID IN FULL permit